Sign inSign upSign in
Menu
Skills level · Public Sector Accounting and Finance

Public Sector Accounting and Finance · May 2025

Every objective and theory question in this paper, with answers where we have them, and the topic notes to revise each one.

7 questions7 theory8 topics to revise
Source: ICAN Pathfinder, Skills Level Examination, Public Sector Accounting and Finance, May 2025

May 2025 diet

0 objective and 7 theory
Time allowed: 31/4 hours (including 15 minutes reading time). Attempt five out of seven questions.
0 objective7 theory135 theory marks set
No.SectionMarksCovers
Q1Section A (compulsory)30Asks for brief explanations of materiality and other qualitative characteristics.
Q2Section B20The question opens by defining accountability and its link to openness and honest public reporting, then asks for mea...
Q3Section B20Explain what is meant by fair presentation of financial statements for public entities.
Q4Section B20Part (b)(i) (4 marks) asks for the conditions under which an entity need not present consolidated financial statement...
Q5Section C15The design of fiscal transfers is critical to ensuring the efficiency and equity of local service provision and the f...
Q6Section C15Debt Management, a key component of Public Finance Management (PFM), enables the government meet its financing needs ...
Q7Section C15Part (a) (5 marks) asks for five general reasons for borrowing; part (b) (10 marks) for the cost effectiveness of two...

Theory questions Written questions

1
Theory question 1Section A (compulsory)
30 marks
a

The following information relates to one of the ten Local Council Development Authority of Wazobia State. Trial balance Ogogo Local Council Development Authority for the year ended December 31, 2023 N’000 N’000 Consultancy cost 85,500 - Interest on loan notes 103,320 Interest on financial assets - 18,900 Repairs and maintenance 174,960 Conferences 262,440 Commission to revenue collectors 284,220 Office stationaries (1/1/2023) 329,220 Court fines - 1,969,200 Donations - 1,453,860 Accumulated fund - 1,275,660 Gift from Philanthropist - 1,054,800 Hawker’s license - 668,700 Car Park rates - 454,860 Motor vehicles 1,101,240 327,960 Contract retention fee – payables - 251,460 Advertisement and promotions for immunisation - 207,000 Furniture and fittings 450,000 180,000 Buildings 2,145,600 134,100 Councillors’ allowances 1,422,000 - Loans and advances to staff 372,600 - Lock-up shops rents - 1,540,800 Long-term loan notes - 1,355,940 Market tolls - 459,900 96 Marriage and divorce registration - 789,120 Warehouse rent - 373,500 Special emergency grant from Wazobia - 544,680 Open shop licenses - 568,620 Withholding tax - 817,200 Telecommunication cost 338,940 - Other expenses 461,160 - Special audit fees 488,340 - Purchase of office stationaries 856,440 - Printing and publication 1,189,980 - Revenue receivable 3,754,260 - Salary for non-established post 4,793,040 - Salary for established post 5,671,620 - Property rate - 1,318,140 Payables - 1,741,680 Share from federation account - 10,574,100 Town-hall meetings 1,168,020 - Transport 984,060 - Utility bills 360,720 - Work-in-progress 369,360 - Cash and cash equivalents 913,140 - Total 28,080,180 28,080,180 Additional information: (i) Included in the work-in-progress is an amount of N36 million relating to a Building which was completed and commissioned by the state Governor on June 1, 2023. After an additional amount of N14.4 million was spent on tiling, the building was put to use for half of the accounting year. This expenditure has not yet been paid. (ii) Interest on loans to staff is at the rate of 7% per annum. (iii) Interest on long-term loans is at the rate of 10% per annum. (iv) Office stationaries and other items bought for N32.4 million remained unused during the year. The fair value of the inventories is now N27.9 million. (v) Property rates received in respect of 2024 financial year amounted to N36.9 million. (vi) Salaries outstanding during the year amounted to N13.5 million. (vii) Other expenses amounting to N19.89 million was paid in respect of 2024 financial year. 97 (viii) Depreciation of non-current assets is charged on straight line basis for the year as follows: Assets Useful life Building 50 years Furniture and fittings 5 years Motor vehicles 10 years The State Government and all Local Council Development Authority have adopted a policy of preparing financial statements in compliance with International Public Sector Accounting Standards (IPSAS) using Accrual Basis.

Requiredi. Prepare a statement of financial performance for Ogogo LCDA for the year ended December 31, 2023. (13 Marks) ii. Prepare a statement of financial position for Ogogo LCDA as at December 31, 2023. (14 Marks)
b

IPSAS – 3 Accounting policies, changes in accounting estimates and errors requires the development of accounting policies to ensure that financial statements provide information that meets a number of qualitative characteristics. You are required to briefly explain the following: i. Materiality (1½ Marks) ii. Substance over form (1½ Marks)

Suggested answer

a (i) Ogogo LCDA Statement of financial performance for the year ended December 31, 2023.

Workings N’000 N’000 Revenue: Allocation from Federal Government. 10,574,100 Special emergency grant from Wazobia 544,680 Internally Generated Revenue (IGR): Court fines 1,969,200 Lock-up shops rent 1,540,800 Hawker slicense 668,700 Car park rate 454,860 Warehouse rent 373,500 Advertisement and promotion 207,000 Open shop license 568,620 Market tolls 459,900 Marriage and divorce registration 789,120 Property rate i. 1,281,240 Interest on loans to staff ii. 26,082 8,339,022 Donation and gifts: Donations 1,453,860 Gift from philanthropist 1,054,800 2,508,660 Total revenue 21,966,462 Expenditure: Employee emoluments iii. 10,478,160 Interest on loan notes iv. 135,594 Office consumables v. 1,157,760 Councillor's allowance 1,422,000 Printing and publication 1,189,980 Commission to revenue collectors 284,220 Conferences 262,440 Consultancy 85,500 Repairs and Maintenance 174,960 Telecommunication cost 338,940 Town hall meeting 1,168,020 Travel and transport 984,060 Utility bills 360,720 Special audit fees 488,340 Other expenses vi. 441,270 105 Depreciation of non- current assets: vii.

- Buildings 43,416 - Furniture and fittings 90,000 - Motor vehicles 110,124 Total expenditure 19,215,504 Surplus 2,750,958

Workings i. Property rate N’000 As per trial balance 1,318,140 Less receipts in advance 36,900 Credited to statement of financial performance 1,281,240

ii. Interest on loans to staff N’000 As per trial balance 18,900 Add accrued interest (7% X 372,600) – 18,900) 7,182 Credited to statement of financial performance 26,082

iii. Employees’ emoluments N’000 Salary of non- established post 4,793,040 Salary for established post 5,671,620 Add: Salaries outstanding 13,500 Charged to statement of financial performance 10,478,160

iv. Interest on loan notes N’000 As per trial balance 103,320 Interest payables 32,274 Charged to statement of financial performance 135,594

v. Office consumables N’000 Office consumables (1/1/23) 329,220 Add: Purchases 856,440 1,185,660 Less: closing stock at fair value 27,900 Office consumables consumed 1,157,760 106

vi. Other expenses N’000 As per trial balance 461,160 Less: Amount paid in advance c/f 19,890 Charged to statement of financial performance 441,270

(ii) Ogogo LCDA Statement of financial position as at December 31, 2023 Non-current assets: Workings N’000 N’000 Property, plant and equipment vii. 2,861,640 Financial assets (Loans and advances to staff) 372,600 Work-in-progress viii. 333,360 Current assets: Receivables ix. 3,781,332 Inventory 27,900 Cash and cash equivalents 913,140 Total assets 8,289,972 Liabilities Non-current liabilities: Loan notes 1,355,940 Current liabilities: Payable x. 2,907,414 Total liabilities 4,263,354 Net assets 4,026,618 Equity Accumulated fund b/f 1,275,660 Surplus for the year 2,750,958 Total equity 4,026,618 107

Workings i. Non- current assets schedule Life (years) 10 5 50 MV F&F Building Total N’000 N’000 N’000 N’000 Cost as at 1/1/2023 1,101,240 450,000 2,145,600 3,696,840 Additions during the year - - 50,400 50,400 Cost as at 31/12/2023 1,101,240 450,000 2,196,000 3,747,240 Depreciation: Accumulated depreciation. 1/1/2023 327,960 180,000 134,100 642,060 Annual depreciation. 110,124 90,000 43,416 243,540 Accumulated depreciation 31/12/2023 438,084 270,000 177,516 885,600 Carrying amount at 31/12/2023 663,156 180,000 2,018,484 2,861,640

ii. Work in Progress N’000 Per trial balance 369,360 Less completed portion 36,000 Balance c/f 333,360 iii. Receivables N’000 Per trial balance 3,754,260 Interest 7,182 Other expenses paid in advance 19,890 Total 3,781,332

iv. Payables N’000 Per trial balance 1,741,680 Salaries outstanding 13,500 Withholding taxes 817,200 Property rate 36,900 Interest 32,274 Contract retention 251,460 Cost to complete building 14,400 Total 2.907,414 108

b. Explanation of some terms i Materiality: The relevance of information is affected by its nature and materiality. Information is material if its omission or misstatement could influence the decisions of users or assessments made on the basis of the financial statements. Materiality depends on the nature or size of the item or error judged in the particular circumstances of its omission or misstatement. Thus, materiality provides a threshold or cut-off point rather than being a primary qualitative characteristic which information must have if it is to be useful ii Substance over form: If information is to represent faithfully the transactions and other events that it purports to represent, it is necessary that they are accounted for and presented in accordance with their substance and economic reality and not merely their legal form. The substance of transactions or other events is not always consistent with their legal form.

Examiner’s comment The question is in two parts. Part (a) of the question tests candidates’ knowledge of the preparation of financial performance and position of a local council development authority. Part (b) requires the candidates to explain the concept of materiality and substance over form in public sector accounting. All the candidates attempted the question and their performance was below average. The common pitfalls were candidates’ inability to explain the concepts of materiality and substance over form in details. Candidates are advised to pay more attention to the various sections of the syllabus and to make use of the Institute’s Pathfinder and the Study Texts for better performance in future examinations.

Marking guide Marks Marks a. (i) Preparation of statement of financial performance Title ½ Calculations in the statement (38 ticks @ ¼ each) 9½ Relevant workings (6 ticks @ ½ each) 3 13

(ii) Preparation of statement of financial position Title ½ Calculations in the statement of financial position (14 ticks @ ½ each) 7 Relevant workings (26 ticks @ ¼ each) 6½ 14 109

b. Definition of some terms

(i) Materiality 1½ (ii) Substance over form 1½ 3 Total 30

SECTION B

Source: ICAN Pathfinder, Skills Level Examination, Public Sector Accounting and Finance, May 2025, Question 1
2
Theory question 2Section B
20 marks
a

Accountability is an obligation to answer for the execution of one’s assigned responsibilities. It is the requirement to provide explanation about the stewardship of public money and how this money has been used. Accountability, requires government to carry out all aspects of its financial responsibilities with openness, trust, basic values and ethical standards so that its activities are transparent to the public. Where a government has something to hide, public reporting is more likely to be unreliable and less comprehensive in order to obscure material facts. Included in the four IMF Codes of practices and fiscal transparency is assurances of integrity. 98

Requiredi. Identify and explain SIX conditions or measures to be put in place to enhance public accountability. (6 Marks) ii. From the IMF codes of good practices and fiscal transparency on Assurances of integrity, identify any TWO good practices. (4 Marks)
b

The following initiatives have recently been taken by Ojaja State Polytechnic, a publicly subsidised institution of higher learning which was established by an Act of the State House of Assembly. First, Ojaja State Polytechnic allowed a property developer to use a portion of the campus to construct a mall that will be available for rent, and it is projected that N10.5 billion will be needed to complete and furnish the building. The developer will be responsible for a portion of the cost, and after ten years of operating the asset, the property will be transferred to Ojaja State Polytechnic. It is also agreed that during the period the developer will operate the mall, a percentage of earnings will be distributed to employees of the polytechnic. A former Rector of Ojaja State Polytechnic currently serves as the Chairman of the Board and Chief Executive Officer of the real estate development firm. The administration at Ojaja State Polytechnic reportedly chose him without advertising the post because they believe he is a well-known person of integrity. This Build, Operate and Transfer arrangement will no doubt boost the internally generated revenue of the polytechnic. Secondly, exceptional students from low-income backgrounds can apply for one of ten available scholarships at Ojaja State Polytechnic. The scholarship scheme includes a matrix for evaluating and ranking applicants considering the two main factors of brilliance and low-income level background. Officers from the Ministry of Social and Humanitarian Affairs routinely investigate the list of awardees to confirm compliance with the requirements of the scheme. Evidence show that one of the supervisors working on the external audit of Ojaja State Polytechnic approached the Rector of Ojaja State Polytechnic for two spots in respect of students with very low income level background and the Rector granted him, his request. Thirdly, prior to joining the Office of the Auditor - General as a Senior Auditor, Mr. Koko had a position in the accounting department of Ojaja State Polytechnic. At different times, he was in charge of internal auditing and preparation of financial report at the polytechnic. As a staff of the office of the Audior-General, Mr. Koko led the latest audit of the polytechnic after two years of leaving the polytechnic. Subsequent to the audit, allegation on mismanagement of finances surfaced in the media titled “Former accounting department worker sues Ojaja State Polytechnic for unfair termination after being accused of theft” during the year. This led to negative public perception 99 of the Polytechnic and Mr. Koko was contacted by management with the request to testify in court. During that period, a government-funded initiative to educate chartered accountants on the International Public Sector Accounting Standards (IPSAS) and International Standards on Auditing (ISA) for public auditors got under way. The functioning of the International Organisation for Supreme Audit Institutions (INTOSAI) will be discussed as part of the training workshop. In addition, at the end of the session, attendees are expected to be able to prepare both targeted and broad financial reports and apply a conceptual framework for public sector financial statements.

Requiredi. Describe THREE ethical concerns (one from each of the initiatives) that you will identify as an experienced public sector auditor and provide appropriate audit responses. (6 Marks) ii. Explain FOUR criteria for adopting external confirmations as part of substantive procedures as an auditor. (2 Marks) iii. Explain FOUR conditions under which an entity can carry out a direct procurement. (2 Marks)
Suggested answer

a.(i) Conditions or measures to be put in place to enhance public accountability To enhance the promotion of accountability in the public sector management in Nigeria the following conditions are canvassed:

• Rendering of account: It is expected that accounts should be rendered in all public organisations. Public accountability can be achieved only if those who receive the accounts have the power and ability to take actions on the basis of those accounts;

• Accountable leadership: The existence of leadership that genuinely believes and is committed to the notion of public accountability and will therefore ensure that the laws to safeguard public fund are enforced irrespective of the might of the public officer concerned;

• Investigative reporting/media attention: Public accountability needs the presence of active investigative media that will help to keep the leadership on their toes;

• Public enlightenment: Public accountability will be enhanced if the generality of the populace does not believe that embezzlement of public funds is part of the “political manifesto” which the political leaders must achieve while in office;

• Whistle blowing policy: “Whistle blowing’ should be encouraged in the public sector whereby any public official who encounters mismanagement or wrong doing in the conduct of government business may” blowthe whistle”” by taking the case to the public arena. The prospect that somebody may go public can deter some officials contemplating wrongdoing;

• Openness in governance: All unethical and corrupt practices should be exposed as much as possible while those who indulge in them should be promptly and severely punished in accordance to the law. To this end, there should be full implementation of the Freedom of Information Act (FOIA), 2011 so as to promote openness and feedback in public governance and management; 110

• Encouragement of due process: There should be strict compliance with due process and public procurement procedure as spelt out in the Public Procurement Act (Nigeria, 2007), this will curb corrupt practices and instil financial discipline in budget implementation by the public bureaucracy. Moreover, there should also be strict adherence to the provisions of the Fiscal Responsibility Act;

• Review of current method of asset declaration: The present method of secret declaration of assets by public officers leave much to be desired. As such there is need to institute a more open method of declaring assets so as to afford the opportunity for patriotic citizens to scrutinise and report any incorrectly declared assets to the appropriate authorities;

• Strengthening of anti-graft bodies: All anti-graft bodies such as the EFCC, ICPC, CCB and CCT should be further strengthened by way of being adequately staffed, equipped and funded to make them more effective institutional mechanisms for fighting corruption. Furthermore, other law enforcement agencies notably the police should be strengthened so as to build their capacity to detect, investigate, prosecute and deter or prevent corruption; and

• Deletion of immunity clause: The immunity clause should be expunged from the Nigerian constitution. By so doing, political leaders who are fingered for corrupt practices can be prosecuted while in office.

• Freedom of Information (FOI) Act: The FOI Act grants citizens the right to access public records, ensuring transparency in government activities. It helps expose corruption and mismanagement by making government documents available upon request.

• E-governance and Digital transparency: The adoption of electronic payment systems, online budget tracking, and digital procurement platforms has reduced fraud and improved accountability in public financial management.

• Auditor-General’s oversight: The Office of the Auditor-General audits government accounts to ensure funds are used appropriately. It provides reports to the legislature, helping to hold officials accountable for financial mismanagement.

• Judicial reforms and special anti-corruption courts: Special courts have been established to handle corruption cases efficiently, reducing delays in prosecution and ensuring swift justice.

• Legislative oversight and public hearings: The National Assembly and State Houses of Assembly conduct public hearings and investigations to scrutinise government spending and policies, ensuring accountability.

• Public Accounts Committee (PAC): The PAC is a legislative body responsible for examining audited accounts of government entities and ensuring financial transparency. It plays a crucial role in:

• Reviewing financial reports submitted by the Auditor-General. 111

• Investigating financial irregularities in government spending.

• Ensuring compliance with financial regulations and budgetary allocations.

• Holding public officials accountable for mismanagement of funds.

ii. Assurances of integrity:

• Fiscal data should meet accepted data quality standards and budget forecasts and updates should reflect recent revenue and expenditure trends, underline macroeconomic development;

• Data in fiscal reports should be internally consistent and reconciled with relevant data from other sources. Major revisions to historical fiscal data and any changes to data classification should be explained;

• Ethical standards of behaviour for public servants should be clear and made public;

• Purchases and sales of public assets should be internally audited and audit procedures should be open to review;

• Fiscal information should be independently scrutinised. All public finances and policies should be subject to scrutiny by national audit body or an equivalent organisation that is independent of the executive and

• The national audit body or equivalent organisation should submit all reports, including its annual report to the legislature and publish them.

b. i. Some of the ethical issues are as follows: Details Ethical concern Audit response Conflict of interest (Mall development) The appointment of the former Rector as the Chairman and CEO of the real estate firm without public advertisement raises concerns about favouritism and conflict of interest. Verify the selection process to ensure transparency and review documentation on the appointment, justification, and any potential conflicts of interest that may arise. Fairness in scholarship distribution The Rector granting a request for two scholarship spots outside the established evaluation process may indicate undue influence and lack of fairness. Assess whether the selection of scholarship recipients aligns with the predefined criteria. Cross- check applicant records with oversight reports from the Ministry of Social and Humanitarian Affairs. 112 Mr. Independence of Koko previously aauditor (Mr. Koko’s worked for Ojaja State involvement) Polytechnic and later audited it, which may compromise objectivity. Examine the audit methodology to ensure independence was maintained. Assess whether alternative auditors should have been engaged. Transparency in handling financial mismanagement allegations Negative media perception and a lawsuit involving an ex-employee could impact stakeholder confidence in financial reporting. Investigate the financial mismanagement claims by reviewing audit findings and legal records. Ensure disciplinary actions and termination decisions are backed by proper documentation. Training pprogramme integrity If the IPSAS and ISA training lacks proper oversight, it could lead to inefficiencies and misuse of public funds. Review the procurement and contracting process for trainers. Ensure that training materials align with best practices and objectives. Public sector accountability in financial reporting Ensuring that trained public auditors apply IPSAS correctly in financial reporting to maintain credibility. Evaluate post-training audits to determine if attendees implement standards properly. Conduct compliance tests on financial statements prepared under IPSAS

ii. Criteria that auditors can use to decide if external confirmations can be considered under substantive procedures The following factors will be used to assist auditors to determine whether confirmations can be used as substantive procedures:

• The ability of the willing intended third party to respond o the request of the auditors.

• The cost involved maybe more and the auditors will decide to use substantive procedures instead of information from the third party.

• Where the responsible party operates in an environment in which confirmations are not an aspect of day-to-day operations.

• Where the respondent is close to the entity and responding to a confirmation maybe less reliable. 113

iii. An entity may carry out any direct procurement where:

• Goods, works or services are only available from a particular supplier or contractor, or if a particular supplier or contractor has exclusive rights in respect of the goods, works or services, and no reasonable alternative or substitute exits;

• There is an urgent need for the goods, works or services and engaging in tender proceedings or any other method of procurement is impracticable due to unforeseeable circumstances giving rise to the urgency which is not the result of dilatory conduct on the part of the procuring entity;

• Owing to a catastrophic event, there is an urgent need for the goods, works or services, making it impracticable to use other methods of procurement because of the time involved in using those methods;

• An entity which has procured goods, equipment, technology or services from a supplier or contractor, determines that:

• Additional supplies need to be procured from that supplier or contractor because of standardization;

• There is a need for compatibility with existing goods, equipment, technology or services, taking into account the effectiveness of the original procurement in meeting the needs of the procurement entity;

• The limited size of the proposed procurement in relation to the original procurement provides justification;

• The reasonableness of the price and the unsuitability of alternatives to the goods or services in question merit the decision.

• The procuring entity seeks to enter into a contract with the supplier or contractor for research, experiment, study or development, except where the contract includes the production of goods in quantities to establish commercial viability or recover research and development costs; and

• The procuring entity applies this Act for procurement that concerns national security, and determines that single-source procurement is the most appropriate method of procurement.

• The entity may procure the goods, works or services by inviting a proposal or price quotation from a single supplier or contractor. Also, the entity shall include in the record of procurement proceedings a statement of 114 the grounds for its decision and the circumstances in justification of single source procurement.

Examiner’s report The question is in two parts. Part (a) of the question is in two sections, section (i) requires the candidates to identify and explain the conditions or measures to be put in place to enhance public accountability, while section (ii) require candidates to identify IMF codes of good practices and fiscal transparency on assurance of integrity. Part (b) is in three sections, section (i) requires the candidates to describe the ethical concerns that an experienced public sector auditor will identify while providing appropriate audit responses when auditing a public sector entity, while section (ii) requires the candidates to explain the criteria for adopting external confirmation as part of substantive procedures as an auditor. Section (iii) of the question however, requires the candidates to explain the conditions under which an entity can carry out a direct procurement. Few candidates attempted the question and their performance was below average. The commonest pitfall was the inability of the candidates to properly understand the requirement of the question. Candidates are advised to make use of ICAN Pathfinders and the Study Text for better performance in the Institute’s future examinations.

Marking guide Marks Marks a. Conditions or measures to be put in place to enhance public accountability b. Identification any six conditions or measures to be put in place to enhance public accountability 3 Explanation of six conditions identified 3 Four good practices and transparency under IMF Code of practices and fiscal transparency 4 10 b.i. Ethical issues and audit response Identification of any three ethical concerns at ½ mark each 1½ Explanation of the three ethical issues identifyied at ½ mark each 1½ Explanation audit response to ethical issues identified at 1 mark each 3 ii. Criteria for adopting external confirmation Explanation of four (4) criteria that auditors can use to decide if external confirmations can be considered under substantive 115 procedures at ½ mark each. 2 iii. Conditions for direct procurement Four conditions under which an entity can carry out a direct procurement at ½ mark each 2 10 Total 20

Source: ICAN Pathfinder, Skills Level Examination, Public Sector Accounting and Finance, May 2025, Question 2
3
Theory question 3Section B
20 marks
a

Explain what is meant by fair presentation of financial statements for public entities.

2 marks
b

University of Wazobia is a public funded entity established by an Act of parliament in 2019. In its recent trial balance for the year ended December 31, 2024, two items which are listed below have caught the attention of the new Vice Chancellor. Item 1: The research and development costs of N61,295,000 included in the trial balance are made up of the following elements: Project 1: N13,325,000 was spent on applied research. It is hoped that this will ultimately lead to the development of a new vaccine. Project 2: N21,320,000 was spent on research into how renewable energy can be used to support technology for economic development. Project 3: N26,650,000 was spent on the development of a new scanner. Subsequently, the University considers this project no longer a priority of national government and by December 31, 2024 no funding had been identified to continue with the project in 2025. However, on February 15, 100 2024, a loan was obtained from a commercial organisation which means that the project can be completed and the scanner sold commercially. The costs to complete all three projects have been estimated by the University. Item 2: The research grant contracts of N67,957,500 included in the trial balance are to fund the three projects referred to in item 1 above. It is the policy of the University to recognise revenue on the basis of percentage completion of the project. Project Revenue included in the Trial Balance

Required(i) With reference to relevant IPSAs, explain your treatment of the costs of N26,650,000 which relate to project 3. (10 Marks) (ii) With reference to the relevant IPSAs explain your treatment of the revenue of N67,957,500 from research grants contracts. (8 Marks)
Suggested answer

(a) Fair presentation of financial statements for public entities entails the following

(i) Financial statements shall present fairly the financial position, financial performance and cash flows of an entity. (ii) Fair presentation requires the faithful representation of the effects of transactions, other events and conditions in accordance with the definition and recognition criteria for assets, liabilities, revenues and expenses set out in IPSASs. (iii) The application of IPSASs is presumed to result in fair presentation. (iv) Select and apply accounting policies in accordance with IPSAS 3. (v) Present information including accounting policies in a manner that meets qualitative characteristics of information. (vi) Provides additional disclosures when compliance with the special requirements of IPSASs is not sufficient to enable users understand the impact of particular transactions, other events and conditions on the entity’s financial position and financial performance.

(b) (i) Analysis of university funding With reference to relevant IPSAs, the costs of N26,650,000 which relate to project 3 can be treated as follows:

• IPSAS 31 governs the treatment of intangible assets including research and development cost;

• IPSAS 14 governs events after the reporting date;

• Development costs can be capitalised if they meet the six criteria which are listed below: Criteria Project 3 appraisal Saleable or useable by the entity Yes - Can be sold once complete Technically feasible to complete Yes - Technically feasible Economic benefits expected to flow Yes - Can be sold commercially to generating economic benefits to university Measurable expenditure Yes - Expenditure has been measured and included in trial balance 116 Intention to complete Yes - Intending to complete Compellable Yes - Although no funding in place at year end, shortly after year end a loan was obtained so that project can be completed. Treatment: ➢ Project 3 meets the six criteria and therefore can be capitalised. Although the loan was obtained after the balance sheet date it provides information about balances at the balance sheet date i.e., the costs of project 3. ➢ The intangible asset should not be amortised until the expected economic benefits commence.

(i) With reference to the relevant IPSAs the income of N67,957,500 from research grants contracts are as follows: ➢ IPSAS 9 governs the treatment of revenue from exchange transactions including income from research grants and contracts. ➢ IPSAS 23 governs revenue from grants based on percentage of completion ➢ Revenue is recognised when it is probable that future economic benefits or service potential will flow to the entity and these benefits can be measured reliably. ➢ Where revenue relates to ’rendering of services’ it must also be possible toreliably measure the stage of completion,the costs incurred and the costs to complete. ➢ In relation to the research grants and contracts, economic benefits of N67,957,500 have already flowed to the entity and can be measured reliably. ➢ Information is available on stage of completion (percentages given in note 3 of the question paper) and costs to complete are known to the university. ➢ Revenue of N60,905,910 should therefore be recognized based on the percentage of completion (see working 1 below). ➢ The remaining amount of N7,051,590 should be held as deferred income on the statement of financial position. Project Amount % complete Revenue for recognition N N 1 15,990,000 80% 12,792,000 2 22,386,000 96% 21,490,560 3 29,581,500 90% 26,623,350 Total 67,957,500 60,905,910 117

Examiner’s report The question examines candidates’ knowledge of the meaning of fair representation of financial statements for public sector entities. It also requires the candidates’ to explain with reference to relevant IPSASs the treatment of development costs and revenue from research grants contracts. Majority of the candidates attempted the question and their performance was below average. The commonest pitfall was the inability of the candidates to properly explain the treatment of development costs and revenue from research grants contracts in accordance with provisions of relevant IPSASs. Candidates are advised to read widely and ensure that they have adequate knowledge of the relevant sections of the syllabus. They should also make use of the Institute’s Pathfinders, Study Texts and other relevant learning materials for better performance in future examinations.

Marking guide Marks Marks a. Fair presentation of financial statements Stating any four points @ ½ mark each 2

b. (i) Treatment of the costs of N26,650,000 which relate to project 3 Identification of ten points @ 1 mark each 10

(ii) Treatment of the revenue of N67,957,500 from research grants contracts Identification of eight points @ 1 mark each 8 Total 20 118

Source: ICAN Pathfinder, Skills Level Examination, Public Sector Accounting and Finance, May 2025, Question 3
4
Theory question 4Section B
20 marks
a

Ekenga Local Government known for production of edible agricultural crops in large quantity, is linked to other towns in Okoh State by a bridge constructed over a decade ago. This bridge suffered damage caused by ecological disaster lately. The importance of this bridge led to the commissioning of its total reconstruction by the Governor of Okoh State. Alongside this decision to reconstruct the bridge, the Governor also constituted a panel of enquiry comprising of engineers, quantity surveyors and accountants to identify the immediate and remote causes of the ecological challenge with a view to forestalling such in the future. A make-shift, temporary bridge was constructed for temporary use by the inhabitants pending when the construction of the main bridge is completed. The State’s Department of Works and Services also bid for the construction contract and won the contract having participated in the procurement process for contract award. The Department of Works and Services is funded by appropriation. The construction contract has requirements which include anticipated costs, technical specifications and timing of completion. The Department of Roads and Highways does not provide for any recovery of construction costs directly from the department. % complete N 1 15,990,000 80% 2 22,386,000 96% 3 29,581,500 90% Total 67,957,500 101 The initial estimate of the contract costs is N100 million. The construction of the bridge will take three years to complete. At the end of Year 1, the estimate of contract cost has increased to N108 million. An aid-giving NGO has agreed to provide funding of 60% of the costs for constructing the bridge which is N60 million and this is stated in the construction contract. In Year 2, a variation in the contract costs was approved on the advice of the Federal Department of Roads and Rural Infrastructures estimated at N15 million. The aid agency agrees to fund 50% of this variation. At the end of Year 2, costs incurred include N8 million for standard materials stored at the site to be used in Year 3 to complete the project. The Department of Works and Services determines the stage of completion of the contract by calculating the proportion that contract costs incurred for work performed to date, bears to the latest estimated total contract cost.

RequiredIn line with IPSA 11 - Construction contracts, i. Prepare a summary of financial data during the construction period of the construction contract assuming the following stages of completion 28%, 77% and 100% for Year 1, Year 2 and Year 3 respectively. (5 Marks) ii. Prepare the amount of revenue and expenses to be recognised in the statement of financial performance in Year 1, Year 2 and Year 3. (5 Marks)
b

IPSAS 35 on “Consolidated Financial Statements” is one of the standards issued by International Public Sector Accounting Standard Board (IPSASB) in replacement of IPSAS 6 on “Consolidated and Separate Financial Statements”. The objective of this Standard is to establish principles for the presentation and preparation of consolidated financial statements when an entity controls one or more other entities. In light of the above you are required to: (i) Identify the conditions that will warrant entity not to present consolidated financial statements in accordance to IPSAS 35. (4 Marks) (ii) Identify THREE examples each of financial and non-financial benefits that an entity may receive from its involvement with another entity.(6 Marks) 102

Suggested answer

Ekenga Local Government a. (i) Summary of financial data during the construction period of the construction contract Year 1 Year 2 Year 3 N’000 N’000 N’000 Initial amount of revenue agreed in contract 60,000 60,000 60,000 Variation (4,000 + 7,500) - 11,500 11,500 Total contract value 60,000 71,500 71,500 Total contract revenue 60,000 71,500 71,500 Contract costs incurred to date 30,240 88,550 123,000 Contract costs to complete 66,760 34,450 - Total estimated costs 108,000 123,000 123,000 Stage of completion 28% 77% 100%

(ii) Amounts of contract revenue and expenses recognised in the statement of financial performance To date Recognised in the prior years Recognised in the prior years Year 1 Revenue (60,000 x 28%) 16,800 - 16,800 Expenses (108,000 x 28%) 30,240 - 30,240 Year 2 Revenue (71,500 x 77% 55,055 (16,800) 38,255 Expenses (123,000 x 77%) 94,710 (30,240) 64,470 Year 3 Revenue (71,500 x 100%) 71,500 (55,055) 16,445 Expenses (123,000 x 100%) 123,000 (94,710) 28,290

b. (i) A controlling entity need not present consolidated financial statements if it meets all the following conditions: ➢ It is itself a controlled entity and the information needs of users are met by its controlling entity’s consolidated financial statements, and, in the case of a partially owned controlled entity, all its other owners, including those not otherwise entitled to vote, have been informed about, and do not object to, the entity not presenting consolidated financial statements; ➢ Its debt or equity instruments are not traded in a public market (a domestic or foreign stock exchange or an over-the-counter market, including local and regional markets); 119 ➢ It did not file, nor is it in the process of filing, its financial statements with a securities commission or other regulatory organisation for the purpose of issuing any class of instruments in a public market; and ➢ Its ultimate or any intermediate controlling entity produces financial statements that are available for public use and comply with International Public sector accounting Standards (IPSASs), in which controlled entities are consolidated or are measured at fair value through surplus or deficit in accordance with this Standard. ➢ If the subsidiaries’ financial statements are prepared under different reporting dates and the consolidation would not materially affects the reports ➢ If the parent entity has significant legal or operational restrictions. ➢ IPSAS 17, if the subsidiary is classified as “held for sale”.

ii. The following examples illustrate financial benefits that an entity may receive from its involvement with another entity:

• Dividends, variable interest on debt securities, other distributions of economic benefits;

• Exposure to increases or decreases in the value of an investment in another entity;

• Exposure to loss from agreements to provide financial support, including financial support for major projects;

• Cost savings (for example, if an entity would achieve economies of scale or synergies by combining the operations or assets of the other entity with its own operations or assets);

• Residual interests in the other entity’s assets and liabilities on liquidation of that other entity; and

• Other exposures to variable benefits that are not available to other entities. Examples of non-financial benefits include:

• The ability to benefit from the specialized knowledge of another entity;

• The value to the entity of the other entity undertaking activities that assist the entity in achieving its objectives;

• Improved outcomes;

• More efficient delivery of outcomes;

• More efficient or effective production and delivery of goods and services; 120

• Having an asset and related services available earlier than otherwise would be the case; and

• Having a higher level of service quality than would otherwise be the case

Examiner’s report The question is in two parts. Part (a) of the question is in two sections. Section (i) requires candidates to prepare a summary of financial data during construction period of the contract with given stages of completion, while section (ii) requires the candidates to prepare the amount of revenue and expenses to be recognised in the statements of financial performance. Part (b) of the question requires the candidates to identify the conditions that will warrant an entity not to present consolidated financial statements in accordance to IPSAS 35 and identify examples of financial and non-financial benefits that an entity may receive from its involvement with another entity. Most of the candidates attempted the question and performance was below average. The common pitfalls were the inability of the candidates to identify the conditions that will warrant an entity not to present consolidated financial statements in accordance to IPSAS 35. Candidates are advised to read widely and to ensure that they have adequate knowledge of relevant regulations relating to public sector accounting for better performance in the Institute’s future examinations.

Marking guide Marks Marks a. (i) Preparation of summary of financial data Title ¼ Nineteen ticks at ¼ mark each 4¾ 5 (ii) Calculation of amount of revenue and expenses to be recognised in the statement of financial performance Title 1 Sixteen ticks at ¼ mark each 4 5 b.(i) Conditions that will warrant entity not to present consolidated financial statements Four conditions at 1 mark each 4 (ii) Examples of financial and non-financial benefits Identification of three financial benefits at 1 mark each 3 Identification of three non-financial benefits at 1 mark each 3 10 Total 20 121

SECTION C

Source: ICAN Pathfinder, Skills Level Examination, Public Sector Accounting and Finance, May 2025, Question 4
5
Theory question 5Section C
15 marks
a 7½b 7½
a

The design of fiscal transfers is critical to ensuring the efficiency and equity of local service provision and the fiscal health of sub-national governments. You are required to identify and explain FIVE principles that should guide grant design of fiscal transfers.

7½ marks
b

Omidan State Government is considering investing in one of the five available projects using cost – benefit method. The following estimated costs and benefits relate to five different projects. A ₦’m Assume that the state government has budgeted a sum of ₦520 million to be invested in undertaking the different projects.

RequiredCalculate the cost benefit ratio of each project and using other appropriate techniques, rank the projects and advice the state government on the project that should be undertaken and the cost involved.
7½ marks
Suggested answer

a. Guidelines for grant design

i. Clarity in grant objectives. Grant objectives should be specified clearly and precisely. ii. Autonomy. Sub-national governments should have complete independence and flexibility in setting priorities. They should not be constrained by the categorical structure of programs and uncertainty associated with decision making by national officials. Tax-base sharing – allowing sub-national governments to introduce their own tax rates on national bases, formula-based revenue sharing, or block grants – is consistent with this objective. iii. Revenue adequacy. Sub-national governments should have adequate revenues to discharge designated responsibilities. iv. Responsiveness. The grant program should be flexible enough to accommodate unforeseen changes in the fiscal condition of the recipients. v. Equity (fairness). Allocated funds should vary directly with fiscal-need factors and inversely with the tax capacity of each jurisdiction. vi. Predictability. The grant mechanism should ensure predictability of sub- national governments’ shares by publishing five-year projections of funding availability. The grant formula should specify ceilings and floors for yearly fluctuations. Any major changes in the formula should be accompanied by harmless or grandfathering provisions. vii. Transparency. Both the formula and the allocations should be disseminated widely in order to achieve as broad a consensus as possible on the objectives and operation of the program. viii. Efficiency. The grant design should be neutral with respect to sub- national governments’ choices of resource allocation to different sectors or types of activity. ix. Incentive. The design should provide incentives for sound fiscal management and should discourage inefficient practices. Specific transfers should not be made to finance sub-national government deficits. x. Accountability for results. The grantor must be accountable for the design and operation of the program. The recipient must be accountable to the grantor and its citizens for financial integrity and results (i.e., 122 improvements in service delivery performance). Citizens’ voice and exit options in grant design can help advance bottom-up accountability objectives.

b. Omidan State Government Cost Benefit Ratio for each project A – E A B C D E ₦’m ₦’m ₦’m ₦’m ₦’m Estimated benefit 250 220 200 260 360 Estimated cost of investment 100 200 120 240 300 Cost benefit ratio (Benefit / Cost) 250/100 = 2.5 220/200 = 1.1 200/120 = 1.67 260/240 = 1.08 360/300 = 1.2 Ranking 1st 4th 2nd 5th 3rd Therefore, the state government should embark on projects A, C, and E respectively based on estimated cost of investment. Project Budgeted sum (₦) million Cumulative of money for investment (₦) million A 1st 100 million 1000 million C 2nd 120 million 220 million E 3rd 300 million 520 million

Examiner’s report The question is in two parts. Part (a) of the question requires the candidates to identify and explain the principles that should guide grant design of fiscal transfers. Part (b) of the question require the candidates to calculate cost benefit ratios of given projects, rank the projects and advice the state government on the project that should be undertaken. Majority of the candidates attempted the question and their performance was average. The common pitfalls were the inability of the candidates to explain the principles that should guide grant design of fiscal transfers, while in part (b)many of the candidates could not calculate cost benefit ratios of the projects using other appropriate techniques. Candidates are advised to make use of Pathfinders and the Study Text of the Institute for better performance in the Institute’s future examinations. 123

Marking guide Marks Marks a. Guidelines for grant design Identification of five guidelines 2½ Explanation of guidelines identified 5 7½

b. Calculation of the cost benefit ratio of each project Title ½ Calculation of cost benefit ratio 2½ Ranking 2½ Advising the state government on the project that should be undertaken 2 7½ Total 15

Source: ICAN Pathfinder, Skills Level Examination, Public Sector Accounting and Finance, May 2025, Question 5
6
Theory question 6Section C
15 marks
a 2b 5c 5

Debt Management, a key component of Public Finance Management (PFM), enables the government meet its financing needs at minimum costs and within acceptable levels of risk. One method government use in managing its debt portfolio is to annually conduct a Debt Sustainability Analysis (DSA). Required:

a

Explain what constitutes “Total Public Debt”.

2 marks
b

Define the term “Debt Sustainability” and state the main objective of conducting a “Debt Sustainability” exercise.

5 marks
c

Explain the benefits of conducting an annual DSA.

5 marks
d

Explain the actions which can be taken to reduce accumulation of public debt. (3 Marks) B ₦’m C ₦’m D ₦’m E ₦’m Estimated cost of investment 100 200 120 240 300 Estimated benefit 250 220 200 260 360 103

Suggested answer

a. Total public debt: Total public debt can be described as the aggregate of external debt, domestic debt, guarantees, and contingent liabilities - including debt owed by central and local government and by public (state-owned) corporations.For instance, external debt is debt owed to lenders outside the country, e.g., Euro bond while internal debt is the government’s obligations to domestic lenders.

b. Debt sustainability: When government is able to service all its debts without undue stress or adjustments to its income and expenditure balance in the medium to long term. Debt is sustainable when government’s current and future streams of income cover expenditure. To evaluate countries’ debt sustainability, it is necessary to monitor debt trends along with emerging domestic and external vulnerabilities and systemic risks that threaten debt sustainability. The objectives of DSA: i Assessing debt carrying capacity:To evaluate government’s ability to finance its programs and at the same time service the ensuing debt without undue pressure on its income stream compromising the macroeconomic stability of the country. ii Guiding borrowing decisions: To reduce chances of excessive build-up of debt by providing insight for the government on responsible borrowing. iii Ensuring fiscal stability: Ensuring that government mains a balance between debt levels and economic growth to avoid excessive debt accumulation and limit risk of debt distress. 124 iv Compliance with international standards: To help guide countries and donors in mobilising critical financing for low-income countries and most especially, align Nigeria’s debt management practices with global frameworks set by institutions like World Bank and IMF. v Monitoring debt to GDP ratio: Ensuring that Nigeria’s debt remains within acceptable limit such as the self-imposed 40% threshold and the 55% limit recommended by the World Bank and IMF.

c. Benefits DSA include: i To guide the government on optimal funding options for its projects and programs; ii To examine the impact of on-going fiscal policy reforms of the government and monetary policy objectives on public debt management strategies and provide policy advice. iii To evaluate the solvency and liquidity status of the country’s total public debt portfolio, taking into account current and future debt obligations; iv To determine the fiscal space available to the government with a view to determining the borrowing limit, given the current debt level; v To detect current and potential future fiscal stress that might be caused by external shocks with a view to preventing and resolving the crises; and vi To evaluate the risks inherent with the current total debt portfolio and proffer mitigating measures. vii To ensure compliance with global standards set by international organisations like World Bank and IMF. viii Enhances transparency and credibility reassuring foreign investors confidence in the country’s debt management.

d. Actions to take in order to reduce debt burden:

i. Prioritise expenditure ii. Convert debt into equity or assets iii. Stop contraction of new debt iv. Limit debt service payments

v. Consolidate debt and refinance existing debt vi. Reschedule debt payments

Examiner’s report The question is in four parts. Part (a) of the question requires the candidates to explain what constitutes “total public debt” while part (b) require the candidates to define “debt sustainability” and the main objective of conducting a “debt sustainability” exercise. Part (c) requires the candidates to explain the benefits of conducting an annual debt sustainability analysis Part (d) requires the candidates to explain the actions which can be taken to reduce accumulation of public debt. Majority of the candidates attempted the question and their performance was average. The common pitfalls were the inability of many candidates to define “debt sustainability” and the main objective of conducting a “debt sustainability” exercise. Also, many candidates could not explain the actions which can be taken to reduce accumulation of public debt. Candidates are advised to make use of Pathfinders and the Study Text of the Institute for better performance in the future examinations.

Marking guide Marks Marks a. Explanation of total public debt Brief discussion of the concept 2

b. Definition and objectives of debt sustainability Definition of the debt sustainability 2 Identification of three objectives of debt sustainability exercise 3 5

c. Benefits of debt sustainability analysis Identification of five benefits 5

d. Actions to reduce accumulation of debt Identification of three actions 3 Total 15

Source: ICAN Pathfinder, Skills Level Examination, Public Sector Accounting and Finance, May 2025, Question 6
7
Theory question 7Section C
15 marks
a

The total amount of money raised by government directly or through any of the authorised agencies is known as public debt. The money could be raised within the domestic economy or externally from citizens and or foreigners. You are required to identify and explain FIVE general reasons for borrowing.

5 marks
b

In order to improve the road network for the citizens of the state government, Arewa State Government is planning to construct a road network that will cover twenty-three villages within the state using two methods of constructions as follows: Method A: Initial cost of capital = N1,500,000,000 Cost of maintenance for every 4 years = N300,000,000 Method B: Initial Cost of capital = N1,250,000,000 Cost of maintenance for every 3 years = N150,000,000 Additional information: It is expected that the road would have maximum life span of 28 years if properly maintained.

RequiredDetermine the cost effectiveness on each method given that the rate of interest is 10%. (10 Marks) 104
Suggested answer

a. General reasons for borrowing The following are some of the reasons that have been advanced to justify the need for a country to borrow: i Huge and persistent budget deficit: The government borrows when its expenditure is greater than its revenue (budget deficit), especially after its taxing capacity has been stretched to the limit. ii Balance of payments disequilibrium: Excessive reliance on foreign resources to sustain domestic production processes, and on foreign goods and services beyond the nation’s foreign exchange earning capacity may lead government into contracting debt obligations. iii Rapidly increasing population: In most developing countries, population is growing faster than the level of national output. The need arises for government borrowing to expand public enterprises and public utilities to cater for the welfare of the people. iv Implementation of development programmes: To promote economic development usually requires provision of new and upgrading of existing social and economic infrastructural facilities like roads, railways, electricity, schools and hospitals. The tax revenue of government may be insufficient to execute such projects, hence the resort to government borrowing. v Economic instability: A stable economy naturally provides an enabling environment for economic growth and development. Public debt of the internal type may be contracted to control inflation, while both internal and external borrowings may be used to stimulate economic activities during economic depression. vi Natural disasters: Government has the responsibility to provide relief to victims of earthquakes, floods and fire disasters, famines, sectarian violence and other natural calamities. Government borrowing may be justified because such occurrences are never expected nor budgeted for. vii Fluctuations in government revenue: Most countries operate mono cultural economies depending on only one (or very few) export product for foreign exchange earnings. A sudden poor performance of such product in the international market would reduce income considerably and adversely affect budget implementation. Any country that finds itself in such a situation may have no option than to borrow to bridge the financial resource gap. viii War-time borrowing: Financial resources needed to prosecute wars are usually beyond the capacity of government. Hence, the need to borrow arises to avoid devastating consequences of defeat ix Debt servicing: New debt with favourable terms and conditions may be undertaken to service old debts thereby reducing the burden of debt on the economy.

b. Arewa State Government Cost effectiveness of method A Year Cash flow Discounting factor (1 +

r) – t PV N’000 N’000 0 1,500,000 1 1,500,000 4 300,000 0.6830 204,900 8 300,000 0.4665 139,950 12 300,000 0.3186 95,580 16 300,000 0.2176 65,280 20 300,000 0.1486 44,580 24 300,000 0.1015 30,450 28 300,000 0.0693 20,790 Total 2,101,530 Total = ₦2,101,530,000 in the next 28 years. Cost effectiveness of method B Year Cash flow Discounting factor (1 + r) - t PV N’000 N’000 0 1,250,000 1 1,250,000 3 150,000 0.7513 112,695 6 150,000 0.5645 84,675 9 150,000 0.4241 63,615 12 150,000 0.3186 47,790 15 150,000 0.2394 35,910 18 150,000 0.1798 26,970 21 150,000 0.1351 20,265 24 150,000 0.1015 15,225 27 150,000 0.0763 11,445 Total 1,668,590 Total = ₦1,668,590,000 in the next 28 years. Decision: Based on the outcomes of these methods, Method B is cost effective and it is preferable because it has the lowest cost and shorter life span.

Examiner’s report The question is in two parts, part (a) of the question requires candidates to identify and explain general reasons for borrowing. Part (b) of the question requires the candidates to carry out investment appraisal using cost effectiveness approach. Most of the candidates attempted the question and their performance was below average. The commonest pitfall was the inability of many candidates to use the cost effectiveness approach of investment appraisal, while considering a given life span and maintenance cost of the projects. Also, few candidates were able to identify and explain reasons for borrowing. Candidates are advised to make use of Pathfinders and the Study Text of the Institute for better performance in the Institute’s future examination.

Marking guide Marks Marks a. General reasons for borrowing Identification of five general reasons for borrowing at ½ mark each 2½ Explanation of five general reasons identified at ½ mark each 2½ 5

b. Determination the cost effectiveness on each method Determination the cost effectiveness on method A (16 ticks @ ¼ each) 4 Determination the cost effectiveness on method B (20 ticks @ ¼ each) 5 Decision 1 10 Total 15 ICAN/251/Q/B6 Examination No......................... THE INSTITUTE OF CHARTERED ACCOUNTANTS OF NIGERIA SKILLS LEVEL EXAMINATION – MAY 2025 CORPORATE STRATEGIC MANAGEMENT & ETHICS EXAMINATION INSTRUCTIONS PLEASE READ THESE INSTRUCTIONS BEFORE THE COMMENCEMENT OF THE PAPER

1. Check your pockets, purse, mathematical set, etc. to ensure that you do not have prohibited items such as telephone handset, electronic storage device, programmable devices, wristwatches or any form of written material on you in the examination hall. You will be stopped from continuing with the examination and liable to further disciplinary actions including cancellation of examination result if caught.

2. Write your EXAMINATION NUMBER in the space provided above.

3. Do NOT write anything on your question paper EXCEPT your examination number.

4. Do NOT write anything on your docket.

5. Read all instructions in each section of the question paper carefully before answering the questions.

6. Do NOT answer more than the number of questions required in each section, otherwise, you will be penalised. 7. All solutions should be written in BLUE or BLACK INK. Any solution written in PENCIL or any other COLOUR OF INK will not be marked.

8. You are required to attempt Question ONE (compulsory), any TWO Questions in Section B and any TWO Questions in Section C.

9. Check that you have collected the correct question paper for the examination you are writing. THE INSTITUTE OF CHARTERED ACCOUNTANTS OF NIGERIA SKILLS LEVEL EXAMINATION – MAY 2025 CORPORATE STRATEGIC MANAGEMENT & ETHICS Time Allowed: 31/4 hours (including 15 minutes reading time) INSTRUCTION: YOU ARE REQUIRED TO ATTEMPT FIVE OUT OF THE SEVEN QUESTIONS IN THIS PAPER

SECTION A: COMPULSORY QUESTION (30 MARKS) QUESTION 1 ZetaTech Solutions, a mid-sized technology company based in Nigeria, specialises in providing innovative software solutions for small and medium-sized enterprises (SMEs). The company has seen steady growth over the past decade. This is driven by its ability to create affordable and scalable solutions. However, the industry landscape has changed dramatically in recent years, influenced by external forces and internal challenges. Firstly, the Nigerian government has recently introduced new regulations to improve data privacy and cyber-security. Compliance with these regulations and heightened insecurity in many parts of the country have increased operational costs for tech companies. Also, the inflation rate has risen to 18%, and the naira has depreciated significantly against major foreign currencies. The SMEs, ZetaTech’s primary clientele, are struggling, which has led to delays in payments and a reduced number of new contracts. However, there is a growing adoption of digital tools among young entrepreneurs, creating opportunities for ZetaTech. Despite this fact, traditional SMEs remain hesitant to transition to digital solutions. Furthermore, the rapid advancement of Artificial Intelligence (AI) and machine learning is reshaping the industry. Competitors have started to integrate these technologies into their offerings, while ZetaTech is still playing catch-up. There is increasing pressure from stakeholders for companies to adopt sustainable practices, including energy-efficient software development. A recent lawsuit against a rival firm for intellectual property infringement has raised awareness of the need for stronger legal framework in the industry. The tech industry has low entry barriers, leading to an influx of startups offering cheaper alternatives. However, ZetaTech’s established reputation provides some insulation. SMEs have significant bargaining power due to the availability of multiple alternatives in the market. ZetaTech relies heavily on cloud service providers and software development tools, giving suppliers of these services considerable leverage. Open-source software and do-it-yourself platforms are gaining popularity, posing a threat to ZetaTech’s offerings. Competition is intense, with both local startups and international firms vying for market share. ZetaTech’s Chief Executive Officer, Adebanjo Oke, has emphasised the importance of agility in responding to industry changes. The leadership team has outlined a strategic plan focused on three key areas: (1) Investing in AI and machine learning capabilities to enhance product offerings. (2) Strengthening relationships with SMEs through tailored customer support. (3) Expanding into West African markets to diversify revenue streams. Despite the ambitious plan, execution has been slow due to resistance from middle management and inadequate resource allocation. Employees have voiced concerns about unclear communication from leadership, resulting in low morale and a high labour turnover.

Required: a. From the above scenario,

i. Use the PESTEL framework to identify and explain key elements of the environment that could shape the success of ZetaTech’s strategies (6 Marks) ii. Identify and justify from the external environment, the TWO top factors that could significantly impact ZetaTech’s strategy (4 Marks)

b. Using the Porter’s 5-force model,

i. Identify and explain the key elements, from the given scenario, that shape ZetaTech’s competitive environment (5 Marks) ii. Suggest ways that ZetaTech can mitigate the threats posed by each of the forces to maintain its competitive position (5 Marks)

c. Using the transformational leadership style, suggest to Adebanjo Oke, ways of mitigating challenges posed by middle management and thereby, ensuring success in the company’s strategy implementation (10 Marks) (Total 30 Marks)

SECTION B: YOU ARE REQUIRED TO ATTEMPT TWO OUT OF THE THREE QUESTIONS IN THIS SECTION (40 MARKS) QUESTION 2 Purity Life Beverages, a bottled water company, prides itself in promoting health and wellness. The company’s tagline, “Pure water, pure life,” reflects its commitment to sustainability and social responsibility. Purity Life sources water from a spring located in a rural community. The company has always maintained that its operations support the community by providing jobs and contributing to local development projects. INSTITUTE OF CHARTERED ACCOUNTANTS OF NIGERIA

Source: ICAN Pathfinder, Skills Level Examination, Public Sector Accounting and Finance, May 2025, Question 7
Source and reference. These questions come from the Institute of Chartered Accountants of Nigeria (ICAN) Pathfinder for the Skills Level Examination, Public Sector Accounting and Finance, May 2025. When you use them, please cite the source, for example: ICAN Pathfinder, Skills Level Examination, Public Sector Accounting and Finance, May 2025. Each question carries its own reference and a button to copy it.