Project appraisal, flexing the numbers and sensitivity analysis

ICAN Professional, Case Study. Financial data analysis (30%).

7 min read · Updated 8 November 2026

Download this topic

In this part

Project appraisal is where well-prepared candidates most often go wrong, because they know too much. They rush to build their own net present value from invented assumptions, when the case already gave the data and the requirement asked for something specific. This topic shows how to appraise within the information given, how to choose a technique, and how to flex the numbers and test sensitivity.

In 30 seconds

Use the information and the tool the requirement asks for. Do not invent new discount rates or cash flows to justify a favourite calculation. Appraisal techniques are payback and accounting rate of return (not discounted), and net present value, internal rate of return and profitability index (discounted).

Then test the result: identify the critical factors, change them, measure how far each can move before the decision changes, and comment on direction and size even if you cannot calculate everything. Recommending that sensitivity analysis should be done earns nothing.

Appraisal in the Case Study

Many cases need some form of project appraisal as part or all of a financial data requirement. There are many well-known techniques, but you must use the information presented and the requirement as written. Often the request is plain: analyse a project with a simple tool such as payback. If no tool is named, the information given will usually allow only one sensible tool.

Project appraisal is an area where candidates have a lot of prior knowledge and wrongly rush to add their own assumptions. They produce a fully worked net present value from invented figures, with no supporting information in the case and no such calculation requested.

Questioning assumptions is a key skill, but creating a new set of assumptions and criteria, such as discount rates, to permit a favoured calculation is not that skill. It shows only that the candidate is answering a question they prepared in advance. Such work will almost certainly earn no reward, however accurate the arithmetic.

The opposite failure also costs marks. In the Sadeco case the examiner reported that most candidates did not answer the appraisal requirement, apparently because they did not know how to find the net contribution used in the net present value. The data was in the case. Your task is to build the calculation from what is given.

GroupTechniques
Non-discounted cash flowPayback period; accounting rate of return (ARR)
Discounted cash flowNet present value (NPV); internal rate of return (IRR); profitability index (PI)

The detailed calculations are assumed from earlier subjects. Use the tool that is requested or suggested by the information.

Sensitivity analysis

Every decision has variables that affect the outcome, and each is uncertain. Sensitivity analysis tests how the expected outcome changes when the values of key decision variables change. For example, a budget can be tested for changes in sales volume, inflation, materials cost or minimum wages.

It can be used to find how far an item of cost or revenue must differ from its estimate before the decision changes. It can also answer a what-if question, such as what happens if sales are 5% below expectation. If a manager thinks sales volume might be wrong by up to 20%, the analysis shows the profit or loss at that level.

The steps are:

  1. Set the original plan or estimate, such as expected profit or NPV.
  2. Identify the key variables, such as price, volume, material cost, labour cost or completion time. Change each by a percentage that is a reasonable estimate of its possible variation and recalculate.
  3. Measure how sensitive the decision is to each change.

Applied to each variable in turn, the method shows which ones are most critical, where an error would have the largest effect. Management can then decide whether it has enough confidence in the estimates to go ahead, or whether the uncertainty makes the project too risky.

Flexing the numbers

After you assess the assumptions given, you must be able to flex the numbers given or calculated and comment on the adjusted effect. In the Case Study this may mean correcting a series of erroneous transactions or proposed adjustments, flexing a forecast for changed assumptions or circumstances, or changing assumptions in a calculation such as breakeven or a tender price.

Sometimes errors in the information make the need obvious. Often you must decide whether flexing is worthwhile. You are not expected to produce endless similar speculative calculations, so identify your critical factors with care. If you find numbers that should be flexed but have no time to do every calculation, you must still comment on the likely direction and size of the change.

Whatever the time pressure, you earn no marks for recommending that sensitivity analysis should be performed or that all figures should be checked and flexed. That only shows that you have not done what the task needed.

The flexing cycleFour boxes in a row: base case from the data given, change one critical factor, recalculate, then compare with the decision point and comment.Base case fromthe data givenChange onecritical factorRecalculateCompare andcomment
Each cycle answers one question: how far can this figure move before the decision changes?

Worked example: the Sadeco food processing project

The Sadeco case asked for an appraisal of a proposed food processing project using net present value, in Appendix 2 of the report. The solution table used these cash flows and factors, which correspond to a discount rate of 18%. Figures are in naira.

YearCash flowFactorPresent value
0(1,150,000,000)1.0000(1,150,000,000)
1389,694,0000.8475330,265,665
2389,694,0000.7182279,878,231
3389,694,0000.6086237,167,768
4389,694,0000.5158201,004,165
5389,694,0000.4371170,335,247
5300,000,0000.4371131,130,000
NPV199,781,076

The NPV is about ₦199.8 million, and the solution concluded that the project meets the foreign partner’s expectation. Now flex the result.

  1. Annual cash flow. The five annual factors add up to 3.1272. The present value of the annual flows is about ₦1,218.7 million. Without the ₦300 million final item, NPV would still be about ₦68.7 million.
  2. How far can cash flow fall?
    For NPV to be zero, the present value of annual flows must be 1,150.0 − 131.1 = ₦1,018.9 million.
    That is an annual flow of about ₦325.8 million, a fall of about 16% from ₦389.7 million.
  3. Judgement. The project is attractive, but a fall of around one-sixth in annual net contribution would remove the whole gain. The contribution depends on demand, prices and input costs, so management should test those before it commits.

Common mistakes

  • Building a new NPV with invented discount rates when the requirement asked for another tool.
  • Failing to find the contribution or cash flow from data that the case supplied.
  • Writing that sensitivity analysis should be done, instead of doing it.
  • Flexing many variables with no explanation and no view on which matters most.
  • Presenting the result with no decision, or a decision that ignores the sensitivity result.

Quick revision

  • Use the data and the tool the requirement gives. Do not invent assumptions or rates.
  • Payback and ARR are not discounted. NPV, IRR and PI are discounted.
  • Sensitivity: original estimate, change key variables, measure effect, find the critical ones.
  • Flex even if you cannot do every calculation, and comment on direction and size.
  • Never write that sensitivity analysis should be done. Do it.

Practice questions

These are original questions in the style of the Institute of Chartered Accountants of Nigeria exam. Try each one before you open the answer.

Question 1. Which technique is a discounted cash flow technique?

  1. Payback
  2. Accounting rate of return
  3. Internal rate of return
  4. Margin of safety
Show the answer

C. NPV, IRR and the profitability index are discounted. Payback and ARR are not.

Question 2. The requirement asks for a payback appraisal. A candidate instead builds an NPV with a self-chosen discount rate. The likely result is:

  1. Full credit for extra work
  2. No reward for the unrequested calculation
  3. Double credit
  4. A higher grade for judgement
Show the answer

B. Invented assumptions and an unrequested tool are unlikely to be rewarded.

Question 3. A project has NPV of ₦200 million. The present value of its annual cash flows is ₦1,200 million. By what percentage can the annual flows fall before NPV is zero?

  1. Nearly 10%
  2. About 17%
  3. About 30%
  4. About 50%
Show the answer

B. 200 ÷ 1,200 = 16.7%.

Question 4. Which statement earns marks?

  1. Sensitivity analysis should be performed
  2. If sales fall 10%, NPV falls from ₦150 million to ₦40 million, so volume is a critical factor
  3. All figures should be checked
  4. More data is needed
Show the answer

B. It quantifies the effect and draws a conclusion.

Question 5 (6 marks). Explain the steps of sensitivity analysis and how management uses the result.

Model answer

Show the model answer to Question 5

Steps (3 marks). Set the original estimate, such as expected profit or NPV. (1) Identify the key variables, change each by a reasonable percentage and recalculate. (1) Measure how sensitive the outcome is to each change. (1)

Use (3 marks). It shows by how much a variable must move before the decision changes. (1) Applying it to each variable shows which are most critical. (1) Management can then decide whether it has enough confidence to proceed or whether the uncertainty makes the project too risky. (1)

The next topic covers risk and uncertainty in decision making.

Pathfinder on Project appraisal, flexing the numbers and sensitivity analysis

These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.

Sadeco Cocoa Processing Limited case: requirement 2

The solution appraises the food processing project by net present value and the examiner records that many candidates could not find the net contribution. Rebuild the table from the data and flex the cash flow.

Revise first: Worked example: the Sadeco food processing project

May 2016 and May 2018: lease or buy, and network expansion

Both ask for an appraisal that depends on stated cash flows and rates. Use only the data given and test the figure that drives the decision.

Revise first: Appraisal in the Case Study

Source: ICAN Pathfinder, Case Study. Diets covered: May 2016, May 2018 and the Sadeco Cocoa Processing Limited case.

Spotted a mistake? Tell us and we will check it.

Where this fits

See every past question on Case Study and the topic each one tests in the Pathfinder question finder.

This course builds on Strategic Business Reporting, Strategic Financial Management, Advanced Taxation and Advanced Audit, Assurance and Forensics.

All Case Study topics

You are reading topic 18 of 26.

  1. What the Case Study paper tests and how it differs from other papers01
  2. The four-hour Case Study paper: the case pack, a reading method and a time plan02
  3. Preparing for the Case Study paper: knowledge, analysis, writing and the ten differentiators03
  4. Reading a case and spotting issues: a method you can repeat on any case04
  5. How the Case Study marking key works: boxes, grades and marks05
  6. Reading a marking key: a worked example, box by box06
  7. How numerical work is rewarded, the grade profile and quality versus quantity07
  8. Writing the report: type, structure, headings and the report format08
  9. The executive summary: what it contains, how to write it and mistakes to avoid09
  10. Language, style and the disclaimer in a Case Study report10
  11. Financial statements analysis: meaning, types and techniques11
  12. The ratio analysis toolkit for the Case Study12
  13. Financial statements analysis in the Case Study: method, report and worked cases13
  14. Analysing and interpreting a sustainability report14
  15. Financial data analysis: forecasting, budgeting and financial appraisal15
  16. Breakeven, cost-volume-profit analysis and pricing decisions16
  17. Product mix, profitability and short-term and long-term decisions17
  18. Project appraisal, flexing the numbers and sensitivity analysis18 here
  19. Risk and uncertainty in decision making: expected values, decision trees and perfect information19
  20. Business valuation: purpose, approaches and asset-based methods20
  21. Valuing shares: P/E, earnings yield, dividend yield and dividend growth models21
  22. Accuracy, assumptions and professional scepticism in financial data analysis22
  23. Plausibility, interpretation and using financial data analysis in the exam23
  24. Corporate restructuring, capital reorganisation and capital reduction under CAMA 202024
  25. Capital reconstruction and schemes of arrangement25
  26. Operational and strategic analysis in the Case Study, including business trust and ethics26
See the whole course

Get the complete Case Study notes

Download as PDF or Word

  • Every topic as PDF and Word, ready to print
  • Edit it in Word or print the PDF. No retyping.
Get this course

Reading stays free. Access lasts 12 months. Pay by card, bank transfer, USSD or QR through Paystack. Your name and email appear on every page of your files. Read our Refund Policy.

PracticeNext topic