A company lists forty risks. If it treats them all alike, it spends the same effort on a paper-clip theft and a fire that could close the factory. Good risk management first finds the risks, then judges how likely each is and how much it would cost, then measures what can be measured and ranks the rest by judgement. Only then does it decide where to spend money on control.
This topic covers how risks are identified, how a company’s risks affect its stakeholders, how risks are assessed by probability and impact on a risk map, how they are measured (including value at risk), how they are prioritised with a risk dashboard, the board’s role, the ALARP principle, objective and subjective assessment, and related and correlated risks. The previous topic covered the nature and categories of risk.
The next covers monitoring, control and enterprise risk management. Neither the May 2014 nor the November 2014 Pathfinder sets a stand-alone question on this topic.
In 30 seconds
Identify risks at group, division and department level, with committees and auditors. Consider the impact on stakeholders: employees, investors, creditors, communities, governments, customers and partners. Assess each risk by probability and impact on a risk map: high-high needs immediate action, high impact with low probability needs consideration (such as insurance), low impact with high probability needs a control review, and low-low is reviewed periodically.
Measure risks where possible, for example with value at risk (VaR). Prioritise with a risk dashboard of red, amber and green lights, comparing residual risk with risk appetite. ALARP means as low as reasonably practicable. Assessments may be objective (hard data) or subjective (judgement). Correlated risks move together, but correlation is not causation.
Key terms in plain English
| Term | What it means |
|---|---|
| Risk map | A grid that places each risk by probability and impact |
| Value at risk (VaR) | The most that is expected to be lost over a period at a stated confidence level |
| Risk dashboard | A traffic-light display of each risk’s level, residual risk and appetite |
| ALARP | As low as reasonably practicable: further cutting risk would cost grossly more than the benefit |
| Objective assessment | An assessment based on hard data |
| Subjective assessment | An assessment based on judgement |
| Correlation | Two risks that move together or in opposite directions |
| Spurious correlation | An apparent link with no real connection |
Syllabus check
This topic is in syllabus area C (risk management, 5% of the marks). It covers:
- identifying, assessing, measuring and prioritising risk;
- the impact of a company’s risks on its stakeholders;
- the ALARP principle and the difference between objective and subjective assessment.
CAMA 2020 and risk assessment
The Companies and Allied Matters Act 2020 (CAMA 2020) is the company law of Nigeria.
| Section | What it says | Link to this topic |
|---|---|---|
| s. 305 | A director must act in good faith in the best interests of the company and have regard to employees | Risks to employees and other stakeholders must be considered |
| s. 308 | A director must use the care, diligence and skill of a reasonably prudent director | Directors must assess risks with care |
| s. 385 | The directors’ report covers performance and risk | Principal risks are disclosed to shareholders |
| s. 404(7) | The audit committee reviews policies and internal control | It reviews how risks are assessed and controlled |
Risk identification
Identification is the first stage of a risk management system. The company must understand the risks in its environment and markets (strategic risks) and inside the business (operational risks). There are no standard rules. In a large company, risks may be identified at group, division and department level. Management usually identifies strategic risks, while internal or external auditors may be better at finding operational risks and suggesting controls.
Many large companies set up risk committees of managers from several departments, each covering one category of risk or one region, which meet regularly to review risks and changes in them.
Risks differ in importance, so they must then be assessed to rank them, to find the most significant and to find those needing urgent control. Control is justified only if its cost is less than the benefit from reducing the risk.
The impact of risk on stakeholders
A company’s risks create risks for its stakeholders, and their reactions can affect the company.
- Employees: loss of job if strategy fails, threats to health and safety (measured, for example, as serious injuries per 1,000 employees a year) and to benefits. Their appetite may differ from the board’s: a rogue trader may take high risks for a bonus.
- Investors: they buy expecting a certain risk profile, high-growth or stable dividends. The board should keep the company’s risk appetite consistent with its shareholders’. When risk rises, some sell and others buy. The board should disclose significant risks. Listed companies disclose their principal risks in the annual report.
- Creditors: a high-risk company is a high credit risk. They risk non-payment and the loss of the customer.
- Communities and the public: recession and closures in places where the company is a major employer, unsafe goods and pollution. Pressure groups arise when people feel threatened.
- Governments: companies supply wealth, jobs and tax. The risk is that they move abroad (ICAN mentions some Nigerian businesses relocating to Ghana).
- Customers: errors and delays pass through the supply chain, and product safety risks fall on users of food, drink and medicines.
- Business partners: in a joint venture, a partner that reduces its own risk, for example by dominating decisions, changes the others’ risk. Clear contracts and monitoring help.
Assessing risks: probability and impact
Assessment is also called risk profiling or risk mapping. Each risk is judged on the likelihood that loss will occur and the size of the loss. A simple risk map is a 2 × 2 grid:
| Low probability | High probability | |
|---|---|---|
| High impact | Consider the need for control, such as insurance | Take immediate action to control the risk |
| Low impact | Review periodically | Consider the need for control action |
High-impact, low-probability risks include fire, flood, terrorism and major new legislation. Some, such as fire and theft, can be insured, which reduces residual risk by the amount of cover. Each key risk should be owned by a named manager who takes the control action and reports.
An ongoing process
In dynamic industries (shipping, telecoms, technology), risks must be assessed continuously. ICAN’s example shows how one risk moves on the map. In year 1, a low-geared company in a low-rate environment sees interest rate risk as low impact and low probability. In year 2 it borrows heavily, so it becomes high impact. In year 3 a new government pushes rates up, so it becomes high impact and high probability. The strategy for managing it changes each time.
Measuring risks
Where possible, risks should be quantified, so that maximum tolerance can be set and actual risk tracked against it. Measures may be financial (expected loss) or non-financial (expected injuries). Not every risk can be measured, and qualitative risks rest on judgement.
Value at risk (VaR) is a model banks use for credit and other risks. It estimates, at a given confidence level, the most that will be lost over a period. For example, at 95% confidence, bad debt losses from current borrowers will not exceed ₦5m next month. Banks set VaR limits and compare actual VaR with the limit.
Prioritising risks
The company decides which risks are tolerable and which need more control. Sometimes the answer is that controls are excessive and can be cut. Judgement is common, but a risk dashboard helps. Each risk has a traffic light: red means more control is needed, amber means keep it under review and green means it is under control.
A fuller dashboard shows for each risk the total risk with no control, the residual risk and the risk appetite.
- If residual risk and appetite are in the same band, current control is appropriate.
- If residual risk is in a higher-risk band than appetite, more control is needed.
- If appetite is well above residual risk, controls may be excessive and cost can be saved.
A company is unlikely to have an appetite for a very high (red) risk.
The board’s role
Management identifies key risks (the board may do so with advice from management and auditors), assesses them, designs and runs controls, monitors them and reports regularly to the board. The board has overall responsibility, sets the risk policy and appetite and, under the UK Corporate Governance Code, reviews the effectiveness of internal control and risk management at least annually and reports to shareholders.
The code of the Financial Reporting Council of Nigeria is to the same effect.
The ALARP principle
Low risk is more acceptable than high risk, but not all risk should be avoided because return is usually linked to risk. ALARP, from UK health and safety law, means that it is usually impossible, or grossly expensive, to remove all risk, so the residual risk should be as low as reasonably practicable. A risk is ALARP when the cost of reducing it further is grossly disproportionate to the benefit.
It is a matter of judgement and not a simple cost-benefit sum.
Objective and subjective assessment
If likelihood and impact can both be measured accurately from hard data, the assessment is objective. Otherwise judgement is used and the assessment is subjective. Objective likelihood: a quality failure in a batch of components, from past experience. Subjective likelihood: an oil well disaster this year in a given region. Objective impact: the change in interest payments from a 1% rise in rates.
Subjective impact: the change in revenue from a change in consumer taste. An assessment based on objective data is more robust.
Related and correlated risks
Related risks often occur together. Risks are correlated if they vary together (positive) or in opposite directions (negative), because of a common cause or because one gives rise to another. Correlation shows association, not causation. Smoking raises the risk of both heart disease and lung cancer, so those two are positively correlated through a common cause, and neither causes the other.
A link with no direct connection is spurious. Missing the relationship between risks can lead to the wrong response. ICAN suggests environmental and reputation risk are correlated, and gives the 2010 Deepwater Horizon accident as an example of a company bearing both clean-up and reputation costs.
The rules in more depth
Why probability and impact are not enough alone
A risk that is rare but could end the company needs attention even though its expected loss is small. The map makes this visible.
Why VaR has limits
It says nothing about the loss in the worst 5% of cases, and it relies on past data. It is a limit and a measure, not a guarantee.
Why a dashboard compares residual risk with appetite
Both too little and too much control are costly. The comparison shows where to add control and where to save.
Why correlated risks matter for hedging
If two exposures move together, one hedge may cover both. If they move in opposite directions, they may already offset.
Effect on analysis
In a scenario, list the risks, place them on the map, size the main ones, compare residual risk with appetite and recommend the controls that pass the cost test.
Worked examples
Example 1: placing risks on the map. (a) Fire at the only warehouse. (b) A fall in the naira that raises import costs every quarter. (c) Small errors in stock counts each month. (d) Occasional loss of stationery.
- (a) High impact, low probability: consider insurance.
- (b) High impact, high probability: immediate action, such as hedging.
- (c) Low impact, high probability: consider tighter procedures.
- (d) Low impact, low probability: review periodically.
Example 2: the cost test for control. The chance of a fire is 2% a year and the loss would be ₦500m. Insurance covering 90% of any loss costs ₦6m a year.
- Expected loss.
2% × 500 = ₦10m. - Insurance removes 90% of that, which is ₦9m of expected loss.
- Benefit ₦9m exceeds cost ₦6m, so the insurance is justified on cost.
- Residual expected loss = ₦1m. Because the loss is high, the company may buy it anyway to protect against the worst case.
Example 3: reading a VaR limit. A bank’s limit is ₦5m at 95% confidence for the month. The model now shows ₦6.2m.
- The bank is ₦1.2m over its limit.
- It should cut the exposure, add collateral or change the loan book to return within the limit.
- The breach should be reported to the risk committee.
Example 4: dashboard reading. For credit risk, appetite is amber and residual risk is red.
- Residual risk is in a higher-risk band than the appetite.
- More control is needed, for example tighter credit limits or insurance.
- For a risk where appetite is amber and residual risk is green, controls may be excessive and some cost might be saved.
How to score full marks
- List the risks before assessing them.
- Place each on the map and state the action that follows.
- Quantify the main ones, and say which cannot be measured.
- Compare residual risk with appetite.
- Test the cost of each control against its benefit.
- Name an owner for each key risk.
Common mistakes in the exam
- Listing risks without ranking them.
- Placing a high-probability, low-impact risk in the top-priority box.
- Treating VaR as a guarantee.
- Treating correlation as proof of cause.
- Ignoring the effect of company risk on stakeholders.
- Recommending controls that cost more than the risk is worth.
Quick revision
- Identify at all levels; committees and auditors help.
- Stakeholders: employees, investors, creditors, public, government, customers, partners.
- Risk map: probability against impact.
- VaR: maximum loss at a confidence level.
- Dashboard: red, amber, green; residual risk against appetite.
- ALARP, objective and subjective, correlation.
- CAMA 2020: ss. 305, 308, 385, 404(7).
Practice questions
These are original questions written in the style of the Institute of Chartered Accountants of Nigeria (ICAN) exam. Try each one before you open the answer. Full model answers follow the written questions.
Recall check: multiple choice
The real ICAN paper has no multiple-choice section. These questions are for quick recall. The written questions that follow are closer to the exam.
Question 1. A high-impact, high-probability risk needs:
- Periodic review
- Immediate action
- No action
- Only insurance
Show the answer
B. Top-left of the usual map.
Question 2. A high-impact, low-probability risk such as fire is often:
- Ignored
- Insured
- Hedged with options
- Sold
Show the answer
B. Insurance cuts residual risk.
Question 3. Value at risk gives:
- A guaranteed maximum loss
- A maximum expected loss at a confidence level
- The tax due
- The price of a share
Show the answer
B. For example 95%.
Question 4. On a dashboard, a red light means:
- Risk under control
- More control is needed
- No risk
- Review annually
Show the answer
B. Green means under control.
Question 5. If residual risk is in a higher band than appetite:
- Controls are excessive
- More control is needed
- Do nothing
- Increase appetite
Show the answer
B. The gap must be closed.
Question 6. ALARP stands for:
- As low as reasonably practicable
- Always low and reasonably priced
- As long as risk persists
- Annual loss and risk plan
Show the answer
A. From health and safety law.
Question 7. Two risks that move together are:
- Correlated
- Spurious always
- Independent
- Residual
Show the answer
A. Correlation is not causation.
Question 8. An assessment based on hard data is:
- Subjective
- Objective
- Qualitative only
- Invalid
Show the answer
B. It is more robust.
Question 9. Control measures are justified when:
- The cost is less than the benefit
- Always
- Never
- The risk is zero
Show the answer
A. The cost test.
Question 10. Which section of CAMA 2020 sets the director’s duty of care and skill?
- Section 308
- Section 400
- Section 405
- Section 409
Show the answer
A. Directors must assess risks with care.
Written questions
Question 11 (10 marks). (a) Describe a risk map and the action suggested for each of its four areas. (6 marks) (b) State why a named manager should own each key risk. (4 marks)
Question 12 (20 marks). Sahel Pharma Plc is assessing risks. A fire at its only warehouse has a 2% annual chance and a ₦500m loss. Insurance covering 90% of any loss costs ₦6m a year. The company’s credit risk has an appetite in the amber band but a residual risk in the red band.
A bank that lends to the company applies a value at risk limit of ₦5m to those loans. Its model now shows ₦6.2m. (a) Calculate the expected loss from the fire and decide whether the insurance is justified on cost. (6 marks) (b) Explain what the dashboard position shows for the credit risk and what to do. (5 marks) (c) Explain the position on the VaR limit.
(4 marks) (d) Explain how the company’s risks may affect its employees and creditors. (5 marks)
Question 13 (10 marks). (a) Explain the ALARP principle. (4 marks) (b) Distinguish objective from subjective risk assessment with an example of each. (3 marks) (c) Explain what is meant by correlated risks and the warning that goes with it. (3 marks)
Model answers
Show the model answer to Question 11
(a) Risk map (6 marks). A 2 × 2 grid of probability against impact. (2) High impact, high probability: take immediate action. (1) High impact, low probability: consider control such as insurance. (1) Low impact, high probability: consider the need for control action. (1) Low impact, low probability: review periodically. (1)
(b) Ownership (4 marks). An owner is responsible for taking the control measures. (2) The owner reports to a senior manager on what has been done, so accountability is clear. (2)
Show the model answer to Question 12
(a) Fire (6 marks).
- Expected loss.
2% × 500 = ₦10m. (2) - Insurance removes 90%, which is ₦9m of expected loss. (2)
- The benefit ₦9m exceeds the cost ₦6m, so it is justified on cost, and the high impact is a further reason. (2)
(b) Dashboard (5 marks). Residual risk is in a higher-risk band (red) than the appetite (amber). (2) More control is needed to bring residual risk down to the appetite, such as tighter credit limits, credit insurance or better screening of customers. (3)
(c) VaR (4 marks). The VaR of ₦6.2m is ₦1.2m above the ₦5m limit. (2) The bank should cut exposure or add security and report the breach to the risk committee. (2)
(d) Stakeholders (5 marks). Employees: jobs and safety are at risk if strategy fails or controls are poor. (2.5) Creditors: a high-risk company is a high credit risk, so they may not be paid or may lose a customer. (2.5)
Show the model answer to Question 13
(a) ALARP (4 marks). It is usually impossible, or grossly expensive, to remove all risk. (1) Residual risk should therefore be as low as reasonably practicable. (1) A risk is ALARP when the cost of reducing it further is grossly disproportionate to the benefit. (1) It is a matter of judgement. (1)
(b) Objective and subjective (3 marks). Objective uses hard data, for example the change in interest payments from a 1% rate rise. (1.5) Subjective relies on judgement, for example the change in revenue from a shift in consumer taste. (1.5)
(c) Correlation (3 marks). Risks that vary together or in opposite directions. (1.5) Correlation is not causation, because there may be a common cause or the link may be spurious. (1.5)
Pathfinder on Risk maps, VaR, dashboards and ALARP
These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.
Neither the May 2014 nor the November 2014 Pathfinder sets a stand-alone question on this topic. Risk mapping and measurement appear inside scenario questions on governance and treasury. Worked examples 1 to 4 show how to apply them.
Revise first: Worked examples
Questions ask you to place risks by probability and impact and recommend action. See the section on assessing risks.