Sign inSign upSign in
Menu

Risk: sensitivity analysis and expected values

ICAN Professional, Strategic Financial Management. Syllabus area B, advanced investment appraisal

9 min read · Updated 8 November 2026

Download this topic

In this part

A forecast of ₦5m a year is a guess dressed as a number. Sales may fall short, costs may overrun, the machine may be needed for fewer years. A manager who reports only the single NPV is hiding the part that matters most: how wrong can the forecast be before the decision flips? This topic shows the tools for answering that.

This topic covers risk and uncertainty, sensitivity analysis (how far each input can move before NPV reaches zero), discounted payback as a measure of life sensitivity, expected values of NPV with probabilities, the standard deviation of NPV and the strengths and weaknesses of each. The previous topic covered inflation. The next covers decision trees, risk-adjusted discount rates and simulation.

Neither the May 2014 nor the November 2014 Pathfinder sets a stand-alone question on this topic.

In 30 seconds

Risk means several possible outcomes with probabilities that can be estimated. Uncertainty means too little information to assign probabilities. Sensitivity analysis asks: by how much can each input change before NPV falls to zero? Sensitivity % = NPV ÷ PV of the item × 100. The smaller the percentage, the more critical the input. For project life, use the discounted payback period.

Expected value (EV) = Σpx. Accept if the EV of NPV is positive, but look at the spread too: the standard deviation measures it, and the chance of a negative NPV shows the downside. An EV is an average that may never happen, and probabilities are often subjective.

Key terms in plain English

TermWhat it means
RiskSeveral possible outcomes whose probabilities can be estimated
UncertaintyToo little information to know the outcomes or their probabilities
Sensitivity analysisFinding how much each input can change before NPV reaches zero
Discounted paybackThe time taken for discounted cash flows to repay the investment
Expected value (EV)A probability-weighted average of possible outcomes
Standard deviationA measure of how widely outcomes are spread around the EV
Probability distributionThe list of outcomes and their probabilities

Syllabus check

This topic is in syllabus area B (advanced investment appraisal, 30% of the marks). It covers:

  • sensitivity analysis and comments on its results;
  • expected values as a way to take account of risk and uncertainty;
  • the strengths and limits of each technique.

CAMA 2020 and risk in appraisal

The Companies and Allied Matters Act 2020 (CAMA 2020) is the company law of Nigeria.

SectionWhat it saysLink to this topic
s. 305A director must act in good faith in the best interests of the companyRisk should be weighed against return for the benefit of the company
s. 308A director must use the care, diligence and skill of a reasonably prudent directorDirectors should test the risk and the assumptions in a proposal
s. 377(1) and s. 378Directors prepare statements that follow IFRS and give a true and fair viewDecisions later affect reported assets, profit and cash
s. 385The directors’ report covers performance and riskMajor plans and risks are reported to shareholders

Risk and uncertainty

Cash flow estimates may be wrong because of risk and uncertainty. In a dice roll, the outcomes are 1 to 6, each with probability one-sixth: that is risk, and it can be measured with probabilities. When a business predicts sales in three years’ time of ₦500,000 on little information, that is uncertainty, which can still be assessed but with less precision. Management should consider both, as well as the expected return.

Methods include sensitivity analysis and probability analysis, and also simulation, risk-adjusted discount rates and discounted payback, which the next topic covers.

Sensitivity analysis

Sensitivity analysis takes each uncertain input in turn and finds the change needed to bring NPV to zero. It is break-even analysis in NPV terms. To do it, find the PV of each element of cost and revenue separately.

Sensitivity (%) = NPV ÷ PV of the item × 100, where the item is the one being tested.

  • Initial investment: NPV ÷ investment.
  • Selling price: NPV ÷ PV of sales revenue.
  • Sales volume: NPV ÷ PV of contribution (sales less variable costs).
  • Variable cost per unit: NPV ÷ PV of variable costs.
  • Fixed costs: NPV ÷ PV of fixed costs.
  • Cost of capital: the IRR is the break-even rate. Sensitivity = (IRR − cost of capital) ÷ cost of capital.
  • Project life: use the discounted payback. If it is 3.2 years on a 4-year project, the life can fall by about 20% before NPV is zero.

ICAN’s example (Kola Ltd): NPV ₦785,000; investment ₦3,750,000, so it can rise by 20.9%. Sales revenue PV is ₦16,195,000, so price can fall by 4.8%. Volume can fall by 12.1%, variable costs rise by 8.1% and fixed costs rise by 40.4%. The discounted payback is 3.21 years.

Strengths and weaknesses

Strengths: it shows which inputs are critical, so management can monitor them or reduce the risk (more market research on price or volume, fixed-price contracts or hedging on materials, noting that these cost money). It is simple. It gives information in a form that supports judgement.

Weaknesses: it treats inputs as independent when they often move together (higher materials cost may be passed into price). It ignores probability: it says how far a variable must move but not how likely that is. It does not give a decision, only information.

Expected values

An expected value is a weighted average: EV = Σpx, where p is the probability and x the outcome. Applied to a project, x is the NPV for each outcome, and the EV of the NPV is the basic measure. Accept if the EV of the NPV is positive, but a project may still be refused if the risk seems too large for the return.

ICAN’s example. A five-year project costs ₦200,000. NPVs and probabilities: (₦8,000) at 0.10; ₦4,000 at 0.30; ₦12,000 at 0.40; ₦20,000 at 0.20.

  1. EV = (0.10 × −8,000) + (0.30 × 4,000) + (0.40 × 12,000) + (0.20 × 20,000) = −800 + 1,200 + 4,800 + 4,000 = ₦9,200.
  2. The EV is positive, so undertake it provided the risk is acceptable.
  3. There is a 10% chance of a negative NPV of ₦8,000.

The spread of outcomes

To measure risk, compute the standard deviation: take each outcome’s difference from the EV, square it, weight it by its probability, add the results (the variance) and take the square root. A larger standard deviation means more spread, so more risk. The probability of a negative NPV is simply the sum of probabilities of the outcomes below zero.

The coefficient of variation (standard deviation ÷ EV) compares risk per unit of return across projects.

Advantages and disadvantages of EV

Advantages: it uses all the outcomes and gives one figure for the decision.

Disadvantages: probabilities are subjective; the EV may never actually happen; it suits repeated events better than a one-off project; and by itself it does not show the risk.

The rules in more depth

Why the smallest percentage matters most

A small percentage means a small error in that input wipes out the NPV. That is the input to check and control.

Why independence is a problem

If price and volume move together, testing each alone gives a misleading picture of the combined effect.

Why EV alone can mislead

A project with an EV of ₦20m could come from a safe ₦20m or from a gamble between ₦100m and a loss of ₦60m. The spread tells the two apart.

Why discounted payback measures life risk

If cash flows stop early, the project must still repay the investment in PV terms. The payback shows how much life is needed.

Effect on analysis

Give the NPV, rank the inputs by sensitivity, state the EV and the spread, and recommend with reasons.

Worked examples

Example 1: sensitivity. A project has an NPV of ₦500,000, an investment of ₦2,000,000, PV of sales ₦6,000,000, PV of variable costs ₦3,200,000 and PV of fixed costs ₦800,000.

  1. Investment.
    500 ÷ 2,000 = 25.0%.
  2. Price.
    500 ÷ 6,000 = 8.3%.
    Volume: 500 ÷ (6,000 − 3,200) = 17.9%.
  3. Variable cost.
    500 ÷ 3,200 = 15.6%.
    Fixed cost: 500 ÷ 800 = 62.5%.
    Price is the most critical input.

Example 2: expected value and spread. NPV of ₦80m with probability 0.3, ₦30m with 0.5 and −₦40m with 0.2.

  1. EV = 24 + 15 − 8 = ₦31m.
  2. Variance = 0.3(80−31)2 + 0.5(30−31)2 + 0.2(−40−31)2 = 720.3 + 0.5 + 1,008.2 = 1,729.
    Standard deviation = ₦41.6m.
  3. The chance of a loss is 20%.

Example 3: ICAN’s two-state case. An investment of ₦1m has a 75% chance of a strong economy (NPV ₦364,500) and 25% of a weak one (NPV −₦476,950).

  1. EV = 0.75 × 364,500 + 0.25 × (−476,950) = 273,375 − 119,238 = ₦154,138.
  2. The EV is positive, so the project passes.
  3. There is a 25% risk that the NPV is negative.

Example 4: discounted payback. A ₦3,000k project returns ₦1,100k a year for 4 years. The cost of capital is 10%.

  1. Cumulative PV: year 1, 1,000; year 2, 1,909; year 3, 2,735; year 4, 3,487.
  2. Payback = 3 + (3,000 − 2,735) ÷ 752 = 3.35 years.
  3. The life could fall by about 16% (0.65 ÷ 4) before NPV reaches zero.

How to score full marks

  • Calculate the PV of each input before the sensitivities.
  • Present the sensitivities in a table and rank them.
  • Comment on the most critical inputs and how to manage them.
  • For EV, show the table and state the decision.
  • Add the standard deviation or the chance of a loss if risk is asked.
  • Give limits of each method.

Common mistakes in the exam

  • Dividing by the wrong PV (for volume, use contribution).
  • Using undiscounted amounts in sensitivity.
  • Calling an EV the most likely outcome.
  • Not mentioning the downside risk.
  • Saying sensitivity analysis gives the answer.
  • Forgetting that inputs may move together.

Quick revision

  • Sensitivity % = NPV ÷ PV of the item; volume uses contribution; life uses discounted payback.
  • EV = Σpx; accept if positive and the risk is tolerable.
  • Standard deviation and chance of loss show the spread.
  • Sensitivity ignores probability and assumes independence.
  • CAMA 2020: ss. 305, 308, 377(1), 378, 385.

Practice questions

These are original questions written in the style of the Institute of Chartered Accountants of Nigeria (ICAN) exam. Try each one before you open the answer. Full model answers follow the written questions.

Recall check: multiple choice

Recent ICAN papers are written, although older papers such as May 2014 included multiple-choice questions. These questions are for quick recall. The written questions that follow are closer to the exam.

Question 1. Risk differs from uncertainty because with risk:

  1. Probabilities can be estimated
  2. Nothing is known
  3. Outcomes are certain
  4. Tax is ignored
Show the answer

A. Uncertainty lacks them.

Question 2. Sensitivity of selling price is NPV divided by the PV of:

  1. Sales revenue
  2. Fixed costs
  3. The investment
  4. Contribution
Show the answer

A. Then multiplied by 100.

Question 3. Sensitivity of sales volume uses the PV of:

  1. Sales revenue
  2. Contribution
  3. Fixed costs
  4. Tax
Show the answer

B. Sales less variable costs.

Question 4. The inputs with the smallest sensitivity percentages are:

  1. Least critical
  2. Most critical
  3. Irrelevant
  4. Fixed
Show the answer

B. Small changes cancel the NPV.

Question 5. Life sensitivity is found using:

  1. Discounted payback
  2. Accounting rate of return
  3. Tax rate
  4. Inflation
Show the answer

A. Compared with the project life.

Question 6. EV =

  1. Σpx
  2. Σp ÷ x
  3. x ÷ p
  4. Σx only
Show the answer

A. A weighted average.

Question 7. A weakness of sensitivity analysis is that it:

  1. Ignores probability
  2. Is too complex
  3. Needs simulation
  4. Uses profit
Show the answer

A. And treats inputs as independent.

Question 8. A disadvantage of EV is that it:

  1. Shows the risk fully
  2. May describe an outcome that never occurs
  3. Ignores NPV
  4. Is exact
Show the answer

B. It is only an average.

Question 9. A larger standard deviation of NPV means:

  1. Less risk
  2. More spread and more risk
  3. Higher EV
  4. Lower tax
Show the answer

B. Outcomes vary more.

Question 10. Which section of CAMA 2020 sets the director’s duty of care and skill?

  1. Section 308
  2. Section 400
  3. Section 405
  4. Section 409
Show the answer

A. Directors should test the assumptions behind a decision.

Written questions

Question 11 (10 marks). (a) Distinguish risk and uncertainty. (3 marks) (b) Explain how sensitivity analysis is carried out and state its weaknesses. (7 marks)

Question 12 (20 marks). Kano Ltd has a 4-year project: outlay ₦3,000k; 8,000 units a year at ₦500 with variable cost ₦300 and fixed cash costs ₦500,000. The cost of capital is 10% (annuity factor 3.170; discount factors 0.909, 0.826, 0.751, 0.683). Ignore tax. (a) Calculate the NPV. (5 marks) (b) Calculate the sensitivity of the NPV to the outlay, price, volume, variable cost and fixed cost. (8 marks) (c) Calculate the discounted payback and comment. (4 marks) (d) Advise on the key risks. (3 marks)

Question 13 (10 marks). NPV outcomes are ₦80m (probability 0.3), ₦30m (0.5) and −₦40m (0.2). (a) Calculate the EV. (3 marks) (b) Calculate the standard deviation. (4 marks) (c) State the probability of a loss and two limits of EV. (3 marks)

Model answers

Show the model answer to Question 11

(a) Terms (3 marks). Risk: several possible outcomes whose probabilities can be estimated. (1.5) Uncertainty: too little information to know the outcomes or their probabilities. (1.5)

(b) Sensitivity (7 marks). Take each uncertain input in turn and find the percentage change needed to bring NPV to zero: NPV ÷ PV of the item. (3) Weaknesses: inputs are treated as independent; it ignores probability; it gives information, not a decision. (4)

Show the model answer to Question 12

(a) NPV (5 marks).

  1. Contribution = 8,000 × 200 = ₦1,600k
  2. less fixed 500 = ₦1,100k.
  3. PV = 1,100 × 3.170 = ₦3,487k.
  4. NPV = 3,487 − 3,000 = ₦487k. (5)

(b) Sensitivities (8 marks).

  1. PV of sales.
    4,000 × 3.170 = 12,680
  2. PV of variable costs.
    2,400 × 3.170 = 7,608
  3. PV of fixed.
    500 × 3.170 = 1,585.
  4. Outlay.
    487 ÷ 3,000 = 16.2%.
  5. Price.
    487 ÷ 12,680 = 3.8%.
  6. Volume.
    487 ÷ (12,680 − 7,608) = 9.6%.
  7. Variable cost.
    487 ÷ 7,608 = 6.4%.
  8. Fixed cost.
    487 ÷ 1,585 = 30.7%.
  9. (1.5 each, 0.5 working)

(c) Payback (4 marks).

  1. Cumulative PV.
    year 3 = 2,735
  2. year 4 PV = 752.
  3. Payback = 3 + 265 ÷ 752 = 3.35 years. (2.5)
  4. The life could fall by about 16% before NPV reaches zero. (1.5)

(d) Risks (3 marks). Price is the most critical input, since a 3.8% fall removes the NPV, so confirm the price through market research or contracts. (1.5) Variable cost and volume are next at 6.4% and 9.6%, so consider fixed-price supply contracts. (1.5)

Show the model answer to Question 13

(a) EV (3 marks). 0.3 × 80 + 0.5 × 30 + 0.2 × (−40) = 24 + 15 − 8 = ₦31m. (3)

(b) Standard deviation (4 marks).

  1. Variance = 0.3 × 492 + 0.5 × 12 + 0.2 × 712 = 720.3 + 0.5 + 1,008.2 = 1,729. (3)
  2. Standard deviation = ₦41.6m. (1)

(c) Loss and limits (3 marks). Probability of a loss = 20%. (1) Limits: probabilities are subjective; the EV may never occur and suits repeated events better than a one-off project. (2)

Pathfinder on Sensitivity analysis, expected NPV and standard deviation

These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.

Risk in the Pathfinders

Neither the May 2014 nor the November 2014 Pathfinder sets a stand-alone question on this topic. Sensitivity and expected values appear inside project questions. Worked examples 1 to 4 show how to apply them.

Revise first: Worked examples

Sensitivity analysis

Questions ask for the percentage change in each input that makes NPV zero. See the section on sensitivity analysis.

Revise first: Sensitivity analysis

Source: ICAN Pathfinder, Strategic Financial Management. Diets covered: No stand-alone question in the May 2014 or November 2014 Pathfinder.

Spotted a mistake? Tell us and we will check it.

Where this fits

See every past question on Strategic Financial Management and the topic each one tests in the Pathfinder question finder.

This course builds on Financial Management and Performance Management. After it, move on to Case Study.

All Strategic Financial Management topics

You are reading topic 28 of 71.

  1. Strategic financial management and corporate objectives01
  2. The treasury function02
  3. Stakeholders, corporate social responsibility and ethics in financial management03
  4. Money laundering and the duties of directors04
  5. The economic environment, free trade and international institutions05
  6. Government influence on business and the financial management framework06
  7. Financial markets, money markets and money market instruments07
  8. Dividend policy, dividend capacity and transfer pricing08
  9. Emerging issues: the financial crisis, dark pools and new asset classes09
  10. Technology tools for financial management10
  11. Strategic analysis: PESTEL, SWOT and the five forces11
  12. The Ansoff matrix and methods of strategic development12
  13. Assessment and selection of business strategies13
  14. Business plans and communicating strategy14
  15. Strategic change and managing change15
  16. Risk, risk management and categories of risk16
  17. Identification, assessment and measurement of risk17
  18. Monitoring and controlling risk, and enterprise risk management18
  19. Corporate governance: meaning, concepts and stakeholders19
  20. Agency theory and other governance theories20
  21. Governance codes: rules-based and principles-based approaches21
  22. The board: roles, composition and committees22
  23. Directors and the law, director development and audit23
  24. Discounted cash flow (i): NPV, annuities and perpetuities24
  25. Discounted cash flow (ii): IRR, MIRR and relevant costs25
  26. Discounted cash flow (iii): taxation and capital allowances26
  27. Discounted cash flow (iv): inflation27
  28. Risk and uncertainty (i): sensitivity analysis and expected values28 here
  29. Risk and uncertainty (ii): decision trees, risk-adjusted rates and other methods29
  30. The lease versus buy decision30
  31. Asset replacement decisions31
  32. Capital rationing32
  33. Cost of capital and the weighted average cost of capital33
  34. Risk, return and portfolio theory34
  35. The capital asset pricing model and the cost of capital for appraisal35
  36. Sources of finance: equity and rights issues36
  37. Sources of finance: debt, convertibles and preference shares37
  38. Finance for SMEs and venture capital38
  39. Islamic finance39
  40. Financing projects and capital structure theories40
  41. Gearing, WACC and asset and equity betas41
  42. Adjusted present value42
  43. International Valuation Standards43
  44. Business valuation: asset-based and income-based methods44
  45. Dividend valuation models45
  46. The valuation of debt and preference shares46
  47. The efficient market hypothesis47
  48. Value-based management: EVA and MVA48
  49. Cash flow valuation and free cash flow49
  50. International investment decisions50
  51. Option pricing theory and the Black-Scholes model51
  52. Real options and applications of Black-Scholes52
  53. Mergers and acquisitions: strategic and regulatory issues53
  54. Valuation for mergers and acquisitions54
  55. Financing acquisitions and mergers55
  56. Capital reconstructions56
  57. Business reorganisation and management buyouts (MBO)57
  58. Forecast financial statements58
  59. Evaluating financial performance, position and proposed strategies59
  60. Corporate failure and how to predict it60
  61. Foreign exchange rates and exposure61
  62. Exchange rate relationships: PPP and interest rate parity62
  63. Forward contracts, money market hedges and netting63
  64. Duration and convexity64
  65. Yield curves and credit risk65
  66. Forward rate agreements and interest rate swaps66
  67. Forward rates from yield curves and currency swaps67
  68. Futures and hedging with futures68
  69. Currency futures and short-term interest rate futures69
  70. Hedging with options, caps, floors and collars70
  71. Delta hedging and the Greeks71
See the whole course

Get the complete Strategic Financial Management notes

Download as PDF or Word

  • Every topic as PDF and Word, ready to print
  • Edit it in Word or print the PDF. No retyping.
Get this course

Reading stays free. Access lasts 12 months. Pay by card, bank transfer, USSD or QR through Paystack. Your name and email appear on every page of your files. Read our Refund Policy.

PracticeNext topic