Limiting Factors and Make-or-Buy Decisions

ICAN Foundation, Management Accounting. Syllabus area F: Decision making techniques.

16 min read · Updated 8 November 2026

Download this topic

In this part

In the budget, sales demand is normally what limits a business. In the real world, something else often gets in the way first: not enough skilled workers, a machine that runs only so many hours, a material that cannot be imported in full, or simply not enough cash. When that happens, making more of everything is impossible and the question becomes which products deserve the scarce resource.

The answer is not the product with the biggest profit, or even the biggest contribution per unit. It is the product with the biggest contribution for each unit of the scarce resource.

This topic covers the types of limiting factor, how to identify the factor that binds, how to build the profit-maximising production plan for a single limiting factor (including cases with minimum and maximum output levels, and where the scarce resource is money), and make-or-buy decisions, including those where in-house capacity is scarce and some work must be outsourced.

These are very frequently examined: both of the newest diets set a 20-mark limiting factor question.

In 30 seconds

A limiting factor is any resource or condition that restricts activity: labour hours, materials, machine time, finance or sales demand. With one limiting factor other than demand, maximise total contribution by ranking products on contribution per unit of the scarce resource and making them in that order, up to demand, until the resource runs out.

To identify the factor, compare the resource needed to meet full demand with what is available. For make-or-buy, compare relevant costs: buy if the supplier’s price is below the avoidable cost of making. When capacity is scarce, outsource first the products with the lowest extra cost of outsourcing per unit of scarce resource saved. Always ignore apportioned fixed costs and sunk costs.

What a limiting factor is

A limiting factor (also called a scarce or key factor) is any resource or condition that restricts an organisation’s ability to meet its objectives or maximise profit. Budgets usually assume that the company can produce as much as demand requires, so sales demand is the normal limit.

But sometimes a key resource is in short supply, and then the availability of that resource sets the limit on output, sales and profit. If a company makes one product, profit is maximised by making as many as the resource allows. If it makes several using the same scarce resource, it must decide how many of each to make.

Types of limiting factor

TypeHow it limits
Labour hoursA shortage of skilled labour or of available working hours limits capacity
Raw materialsLimited supply stops or delays production, especially when suppliers cannot meet demand
Machine capacityNot enough machine hours because of breakdowns, maintenance or outdated equipment
Financial resourcesA lack of funds or a restricted budget prevents investment in stock, marketing or capacity
Sales demandIf the market buys less than the factory can make, sales are the limit and excess output causes inefficiency

Effects on decisions

When resources are constrained, management must decide how to use them. It may concentrate on the most profitable products, postpone or reject less profitable work, outsource, raise prices to reflect scarcity, or invest to relieve the constraint (more machines, more staff). Recognising the limiting factor and responding to it helps the business optimise profit and manage risk.

Identifying the limiting factor

A question may say that a resource is restricted without saying which. Work it out: calculate the amount of each resource needed to meet the full sales demand and compare with the amount available. The resource for which the need exceeds the availability is the limiting factor.

Example. A company makes products X and Y on two machines. Demand is 14,000 units of X and 12,000 of Y.

Machine time per unitProduct XProduct YHours available
Machine 112 minutes8 minutes2,800
Machine 26 minutes15 minutes4,500
Hours needed for full demandMachine 1Machine 2
X: 14,000 units14,000 × 12 ÷ 60 = 2,80014,000 × 6 ÷ 60 = 1,400
Y: 12,000 units12,000 × 8 ÷ 60 = 1,60012,000 × 15 ÷ 60 = 3,000
Total needed4,4004,400
Available2,8004,500
ResultShort by 1,600: limiting factorSufficient

Machine 1 is the limiting factor. Machine 2 has enough time and does not restrict the plan.

Maximising profit with one limiting factor

When there is one limiting factor (other than sales demand), total profit is maximised by maximising total contribution from the scarce resource. Select products by the contribution per unit of scarce resource, not by contribution per unit of product.

  1. Calculate the contribution per unit for each product.
  2. Identify the scarce resource.
  3. Calculate how much of the scarce resource each product uses.
  4. Divide the contribution per unit by the resource used per unit.
  5. Rank the products: highest contribution per unit of resource first.
  6. Build the plan: make each product in rank order up to its maximum demand until the resource is used up.

Example (continued). Contribution per unit: X ₦90, Y ₦70. Machine 1 hours per unit: X = 12 minutes = 0.2 hours; Y = 8 minutes = 0.1333 hours.

Product XProduct Y
Contribution per unit₦90₦70
Machine 1 time per unit12 min (5 units per hour)8 min (7.5 units per hour)
Contribution per machine hour₦450 (90 × 5)₦525 (70 × 7.5)
Rank2nd1st
Production planUnitsMachine 1 hoursContribution per unitTotal (₦)
Y (1st, full demand)12,0001,60070840,000
X (2nd, balance of hours)6,0001,200 (6,000 ÷ 5)90540,000
Total2,8001,380,000

Y has the lower contribution per unit but earns more per scarce hour. Only 6,000 of the 14,000 units of X can be made. Check: making only X (all 2,800 hours) gives 14,000 units × ₦90 = ₦1,260,000, which is less than ₦1,380,000. ✓

Why not rank on profit per unit?

Full cost and profit per unit include fixed overhead apportioned to units. Fixed costs do not change with the plan, so profit per unit can point to the wrong product. Example. A company makes four products using labour at ₦12 an hour. Demand and unit data:

₦ per unitABCD
Selling price8013060100
Direct materials20301525
Direct labour (at ₦12 an hour)24361224
Variable overhead6936
Variable cost50753055
Contribution per unit30553045
Fixed overhead (absorbed)1015512
Profit per unit20402533
Labour hours per unit2312
Contribution per labour hour1518.333022.5
Rank on contribution per hour4th3rd1st2nd
Annual demand (units)3,0002,0004,0002,500

Labour is limited to 14,000 hours, while full demand needs 21,000 hours (6,000 + 6,000 + 4,000 + 5,000). Ranking on profit per unit would put B first. Ranking on contribution per hour puts C first and B third.

PlanUnitsHoursContribution per unitTotal (₦)
C (1st)4,0004,00030120,000
D (2nd)2,5005,00045112,500
B (3rd, balance 5,000 hours ÷ 3)1,6664,9985591,630
A (4th)nilnilnil
Total13,998324,130

(Two hours are left over because only whole units are made. If part units were allowed, B would be 1,666.67 units and total contribution ₦324,166.67.)

Variations that appear in examinations

Minimum and maximum output levels

Recent papers add limits: a minimum quantity of each product that must be made (to keep customers or contracts), or a maximum production capacity. Method: first make the minimum quantities of all products and deduct the resource used. Then allocate the balance in rank order, up to each product’s maximum.

Example. A company makes J, K and L and is able to sell all that it makes. Labour hours available: 19,500. Labour per unit and contribution per unit: J 1.5 hours, ₦90 (₦60 per hour); K 2.0 hours, ₦100 (₦50 per hour); L 3.0 hours, ₦210 (₦70 per hour). Maximum production possible: J 6,000, K 7,000, L 4,500. Current production: J 3,000, K 4,000, L 2,000.

  • Ranking: L (₦70), then J (₦60), then K (₦50).
  • Optimal plan: L at its maximum, 4,500 units, uses 13,500 hours.
    Balance = 6,000 hours.
    J: 6,000 ÷ 1.5 = 4,000 units (below its maximum of 6,000).
    K: nil.
  • Contribution:
    L 4,500 × ₦210 = ₦945,000.
    J 4,000 × ₦90 = ₦360,000.
    Total ₦1,305,000.
  • Current production:
    J 3,000 × ₦90 = ₦270,000
    K 4,000 × ₦100 = ₦400,000
    L 2,000 × ₦210 = ₦420,000.
    Total ₦1,090,000 (using 3,000 × 1.5 + 4,000 × 2 + 2,000 × 3 = 18,500 hours).
  • Improvement.
    ₦1,305,000 − ₦1,090,000 = ₦215,000.

If management insisted on a minimum of 2,000 units of K, K would be made first (2,000 × 2 = 4,000 hours), leaving 15,500 hours: L 4,500 units (13,500 hours), then J 2,000/1.5 = 1,333 units. The minimum lowers contribution by the amount K’s hours would have earned in J and L: that is the cost of the commitment.

When the scarce resource is money

If the limit is a sum of money available to buy a material (for example, imports limited to a naira amount), rank on contribution per ₦1 of the material. Example. Only ₦600,000 can be spent on a material. Product P: contribution ₦40, material cost ₦10 per unit, giving ₦4 per ₦1 of material. Q: contribution ₦60, material ₦20, giving ₦3. R: contribution ₦30, material ₦5, giving ₦6.

Rank: R, P, Q. If demand is R 40,000, P 30,000 and Q 20,000 units, R uses ₦200,000 (40,000 × ₦5), P uses ₦300,000 (30,000 × ₦10), leaving ₦100,000 for Q: 5,000 units (₦100,000 ÷ ₦20). The same method applies when a question gives the value of the material and not the quantity.

When there is more than one limiting factor

If two or more resources are scarce, the ranking method does not work in general. Specialised methods (such as linear programming) are needed. At Foundation level, questions have one limiting factor, so check the identification step first.

Make-or-buy decisions

A make-or-buy decision asks whether to make an item or do work internally, or to buy it from or contract it to an outsider. It is a short-term relevant costing decision: the financially preferred option has the lower relevant cost. Compare the costs saved by outsourcing with the incremental costs of buying.

Example. A company makes 5,000 components a year with a variable cost of ₦240 each. A supplier offers to sell at ₦270. If the company stops making the component, it will save ₦200,000 a year in avoidable fixed overhead.

Relevant costs and savings of buying (₦)₦
Extra cost of buying: 5,000 × (₦270 − ₦240)(150,000)
Fixed overhead saved200,000
Net benefit of buying50,000

On financial grounds, buy. If the fixed overhead saving were only ₦100,000, buying would lose ₦50,000 and the company should make. Only avoidable fixed costs matter; absorbed fixed overhead that continues is irrelevant.

Make or buy with scarce capacity

When in-house capacity is limited, the company may outsource some work to use the capacity more profitably. The profit-maximising choice is to outsource the items where the extra cost of outsourcing per unit of scarce resource saved is lowest. Steps:

  1. For each item, calculate the extra cost of buying = external price − in-house variable cost.
  2. Divide by the scarce resource used per unit in-house, to give the extra cost per hour saved.
  3. Rank: outsource first the item with the lowest extra cost per hour; make in-house the items with the highest.
  4. Fill the in-house capacity in order of priority and outsource the rest.

Example. Three components, with 3,000 machine hours available in-house.

PQR
Annual demand (units)2,0003,0001,500
Machine hours per unit0.50.81.2
In-house variable cost per unit (₦)407090
Outsourcing price per unit (₦)55100150
Extra cost of outsourcing per unit (₦)153060
Extra cost per hour saved (₦)3037.5050
Priority for outsourcing1st2nd3rd
Priority for in-house production3rd2nd1st

Full demand would need 1,000 + 2,400 + 1,800 = 5,200 hours. Only 3,000 are available, so 2,200 hours of work must be outsourced.

PlanUnitsHoursCost (₦)
In-house R1,5001,800135,000
In-house Q (balance 1,200 hours ÷ 0.8)1,5001,200105,000
Outsource Q1,500150,000
Outsource P2,000110,000
Total variable cost3,000500,000

Check that every item is cheaper to buy than to leave unmade, that is, that the selling price exceeds the outsourcing cost per unit. If it does not, a product should be dropped rather than bought.

Non-financial factors in make-or-buy

  • Quality and reliability of the supplier, and the risk of late delivery.
  • Control over specification, design secrecy and intellectual property.
  • Capacity use. Idle capacity after outsourcing may have no alternative use, and skilled staff may leave.
  • Dependence on one supplier, and the cost of switching back.
  • Long-term strategy, since short-term relevant costing ignores the time value of money and long-term investment effects.

The ideas in more depth

Why contribution per unit of resource?

A product with a high contribution per unit may use up so much of the scarce resource that the resource earns less per hour than on a lower-contribution product. The scarce resource is the money-maker. Each hour or kilogram should go where it earns the most.

Short-term versus long-term

Limiting factor analysis is a short-term tool. If a resource is permanently scarce, the better question is whether to relieve the constraint: hire and train staff, buy another machine, or find new suppliers. The value of one extra hour of the scarce resource is the contribution per hour of the lowest-ranked product being made, the “shadow price”.

If an extra machine hour would earn ₦450 (the marginal product’s rate) and a machine hour costs ₦200 to hire, hiring pays.

Checking the plan

After building the plan, check:

  • (1) total resource used does not exceed the amount available
  • (2) no product exceeds its demand or maximum production
  • (3) any left-over resource is explained (usually rounding to whole units)

Then calculate total contribution and, if fixed costs are given, profit.

Presenting advice

An examiner wants a recommendation, not just numbers. State the limiting factor, the ranking, the plan, the total contribution, and any risk (for example, that the plan stops production of a product some customers need).

Worked example: a full limiting factor question

Scenario. Warri Paints Ltd makes gloss (G), emulsion (E) and primer (P). Selling price per tin: G ₦1,200, E ₦900, P ₦700. Variable cost: G ₦800, E ₦600, P ₦500. Machine hours per tin: G 0.8, E 0.5, P 0.25. Demand: G 5,000, E 8,000, P 12,000 tins. Machine hours available: 9,000. Fixed costs are ₦3,000,000. Find the best production plan and the profit.

  1. Hours needed for full demand:
    G 4,000 + E 4,000 + P 3,000 = 11,000.
    Available 9,000.
    Machine time is the limiting factor (short by 2,000 hours).
  2. Contribution per tin: G ₦400, E ₦300, P ₦200.
  3. Per machine hour:
    G ₦400 ÷ 0.8 = ₦500.
    E ₦300 ÷ 0.5 = ₦600.
    P ₦200 ÷ 0.25 = ₦800.
    Rank: P, E, G.
  4. Plan: P 12,000 tins (3,000 hours). E 8,000 tins (4,000 hours).
    G with the balance of 2,000 hours: 2,000 ÷ 0.8 = 2,500 tins.
  5. Contribution:
    P 12,000 × ₦200 = ₦2,400,000.
    E 8,000 × ₦300 = ₦2,400,000.
    G 2,500 × ₦400 = ₦1,000,000.
    Total ₦5,800,000.
  6. Profit.
    ₦5,800,000 − ₦3,000,000 = ₦2,800,000.
  7. Advice: gloss has the highest contribution per tin but the lowest per machine hour, so only 2,500 of 5,000 tins are made. Each extra machine hour would earn ₦500 (the rate on the marginal product G), so extra hours costing less than ₦500 each, up to 2,000 hours, would add to profit.

The value of extra capacity

A limiting factor analysis also tells you what extra capacity is worth. The marginal product is the last one in the rank order that is limited by the resource (not by demand). Each extra hour of the scarce resource would be used to make more of that product, so it is worth that product’s contribution per hour. In the Warri example it is ₦500 per machine hour.

If the firm can hire machines at ₦350 an hour, it gains ₦150 an hour on up to 2,000 hours: a gain of ₦300,000. If hiring costs ₦550 an hour, it should not. Once all gloss demand is met (2,500 more tins using 2,000 hours), the constraint is no longer the machines, and sales demand becomes the limit.

Special cases

  • Products with equal contribution per unit of resource. The order does not change total contribution. Use other criteria such as strategic importance or customer commitments.
  • Products that cannot be dropped. If a customer contract requires a product, make the contract quantity first even though it ranks low. The cost of this commitment is the extra contribution that the resource would have earned elsewhere.
  • Resources shared between products. If a product uses two scarce resources, only one can be the single limiting factor at a time. Test each resource and see which is exhausted first.
  • Fractional units. If the balance of the resource does not make a whole unit, state whether you round down (whole units only) or allow part units. Say what you assumed.

Common mistakes in the exam

  • Ranking on contribution per unit, or profit per unit, instead of contribution per unit of the scarce resource.
  • Including fixed overhead (absorbed) in the contribution.
  • Not checking which resource is the limiting factor when more than one is given.
  • Making more than the demand or maximum production for the top-ranked product.
  • Forgetting to deduct minimum production quantities first.
  • Dividing the hours left by the wrong hours per unit.
  • In outsourcing, ranking on the cost of buying instead of the extra cost per hour saved.
  • Ignoring avoidable fixed costs in a make-or-buy decision.

Quick revision

  • Limiting factor: the resource that restricts output. Identify it by comparing hours needed for full demand with hours available.
  • Single limiting factor: rank on contribution per unit of scarce resource. Make in rank order up to demand.
  • Money as the limit: rank on contribution per ₦1 of the material.
  • Minimums first, maximums as caps.
  • Make or buy: buy if price is less than avoidable cost of making. With scarce capacity, outsource first the lowest extra cost per hour saved.
  • Ignore apportioned fixed overhead and sunk costs.

Practice questions

These are original questions written in the style of the Institute of Chartered Accountants of Nigeria (ICAN) exam. Try each one before you open the answer.

Section A style: multiple choice

Question 1. A limiting factor is:

  1. The resource that restricts the volume of output or sales
  2. The largest cost
  3. Always sales demand
  4. The selling price
Show the answer

A. It may be labour, materials, machine time, finance or demand.

Question 2. With one limiting factor, products should be ranked by:

  1. Contribution per unit of the scarce resource
  2. Profit per unit
  3. Selling price
  4. Sales demand
Show the answer

A. It maximises total contribution.

Question 3. A product earns ₦120 contribution and uses 4 labour hours. The contribution per labour hour is:

  1. ₦30
  2. ₦480
  3. ₦124
  4. ₦116
Show the answer

A. ₦120 ÷ 4 = ₦30.

Question 4. Demand needs 6,000 machine hours and 5,000 are available. Machine hours are:

  1. A limiting factor
  2. Not a limiting factor
  3. Surplus
  4. Irrelevant
Show the answer

A. Need exceeds availability.

Question 5. In a limiting factor plan, fixed overhead apportioned to products is:

  1. Ignored
  2. Deducted from contribution
  3. Added to variable cost
  4. Used to rank products
Show the answer

A. It does not change with the plan.

Question 6. A component costs ₦240 to make (variable) and ₦270 to buy. Avoidable fixed costs of making are ₦200,000 on 5,000 units. The net benefit of buying is:

  1. ₦50,000
  2. ₦150,000
  3. ₦200,000
  4. −₦50,000
Show the answer

A. Saving ₦200,000 less extra cost ₦150,000.

Question 7. When capacity is scarce, which item should be outsourced first?

  1. The one with the lowest extra cost of outsourcing per unit of scarce resource saved
  2. The one with the highest selling price
  3. The one with the lowest demand
  4. The cheapest to buy
Show the answer

A. It costs least to free up each hour.

Question 8. The extra cost of outsourcing a unit is ₦30 and in-house production uses 0.8 machine hours. The extra cost per hour saved is:

  1. ₦37.50
  2. ₦24
  3. ₦30
  4. ₦0.027
Show the answer

A. ₦30 ÷ 0.8 = ₦37.50.

Question 9. If money to buy materials is the limit, products are ranked on contribution per:

  1. ₦1 of material cost
  2. Unit sold
  3. Labour hour
  4. Machine hour
Show the answer

A. The scarce resource is naira.

Question 10. A minimum production quantity for a product should be:

  1. Made first, with the balance of resource then allocated by rank
  2. Ignored
  3. Made last
  4. Made only if it is first in rank
Show the answer

A. The commitment must be met before the balance is ranked.

Section B style: written questions

Question 11 (10 marks). Explain what a limiting factor is, with five examples, and describe the steps for finding the production plan that maximises profit when there is one limiting factor.

Question 12 (20 marks). Lagos Plastics Ltd makes jugs (J), basins (B) and cups (C). Selling prices: J ₦400, B ₦600, C ₦250. Variable costs: J ₦250, B ₦400, C ₦150. Machine hours per unit: J 0.5, B 1.0, C 0.25. Demand: J 10,000, B 6,000, C 20,000. Machine hours available are 12,000. Fixed costs are ₦2,500,000.

(a) Show that machine time is the limiting factor. (4 marks)

(b) Rank the products and prepare the production plan that maximises profit. (10 marks)

(c) Calculate the total contribution and profit. (3 marks)

(d) State three ways of relieving the constraint. (3 marks)

A further written question

Question 13 (10 marks). A firm makes products A, B and C with demand of 4,000, 3,000 and 2,000 units. Machine hours per unit: A 0.5, B 1.0, C 0.4. In-house variable cost: A ₦30, B ₦60, C ₦45. Outsourcing price: A ₦45, B ₦84, C ₦65. Machine hours available: 4,000. (a) Calculate the extra cost of outsourcing per machine hour saved for each product and rank them. (5 marks) (b) Prepare the plan that minimises total variable cost and calculate the cost. (5 marks)

Model answers

Show the model answer to Question 11

A limiting factor is any resource or condition that restricts an organisation’s activities or its ability to maximise profit. Examples: labour hours (shortage of skilled labour); raw materials (limited supply); machine capacity (breakdowns or too few machines); financial resources (limited funds); sales demand (market smaller than capacity).

Steps when there is one limiting factor. (1) Calculate the contribution per unit of each product. (2) Identify the scarce resource. (3) Calculate how much of it each unit of each product uses. (4) Divide contribution per unit by the resource used, giving contribution per unit of scarce resource. (5) Rank the products, highest first.

(6) Build the plan by making each product in rank order, up to its maximum demand, until the scarce resource is used up. Fixed costs are ignored in the ranking since they do not change with the plan.

Show the model answer to Question 12

(a)

  1. Hours needed for full demand.
    J 10,000 × 0.5 = 5,000
  2. B 6,000 × 1.0 = 6,000
  3. C 20,000 × 0.25 = 5,000.
  4. Total 16,000 hours against 12,000 available, so machine time is the limiting factor (short by 4,000 hours).

(b)

  1. Contribution per unit: J ₦150, B ₦200, C ₦100.
  2. Per machine hour.
    J ₦150 ÷ 0.5 = ₦300
  3. B ₦200 ÷ 1 = ₦200
  4. C ₦100 ÷ 0.25 = ₦400.
  5. Ranking: C 1st, J 2nd, B 3rd.
  6. Plan: C 20,000 units (5,000 hours); J 10,000 units (5,000 hours); B 2,000 units (balance of 2,000 hours).

(c)

  1. Contribution.
    C ₦2,000,000 + J ₦1,500,000 + B ₦400,000 = ₦3,900,000.
  2. Profit = ₦3,900,000 − ₦2,500,000 = ₦1,400,000.

(d) Any three:

  • buy extra machine time or hire machines
  • add a shift or overtime
  • subcontract some production
  • improve machine efficiency and reduce downtime
  • invest in more machines
  • raise prices on the scarcest products
Show the model answer to Question 13

(a)

  1. Extra cost of outsourcing.
    A ₦45 − ₦30 = ₦15
  2. B ₦84 − ₦60 = ₦24
  3. C ₦65 − ₦45 = ₦20.
  4. Per machine hour saved.
    A ₦15 ÷ 0.5 = ₦30
  5. B ₦24 ÷ 1.0 = ₦24
  6. C ₦20 ÷ 0.4 = ₦50.
  7. Priority for outsourcing: B (1st), A (2nd), C (3rd).
  8. Priority for in-house production: C, A, B.

(b)

  1. Hours for full demand.
    A 2,000 + B 3,000 + C 800 = 5,800; available 4,000.
  2. In-house.
    C 2,000 units (800 hours); A 4,000 units (2,000 hours); B with the balance of 1,200 hours = 1,200 units.
  3. Outsource B.
    3,000 − 1,200 = 1,800 units.
  4. Cost.
    C 2,000 × ₦45 = ₦90,000
  5. A 4,000 × ₦30 = ₦120,000
  6. B in-house 1,200 × ₦60 = ₦72,000
  7. B outsourced 1,800 × ₦84 = ₦151,200.
  8. Total variable cost = ₦433,200.

Pathfinder on Limiting factors and make-or-buy

These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.

May Diet, 2026: Question 5 (20 marks)

Rasmo Nigeria Ltd makes three products and labour is short because of unrest. Asks for the most profitable production mix, given current and maximum production (9 marks), and the improvement in profit compared with current production (11 marks).

Revise first: Variations that appear in examinations

November Diet, 2025: Question 4 (20 marks)

Abangam Manufacturing Ltd can import only ₦38,000,000 of a key component. Management requires at least 20,000 units of each product, with the balance to the highest contribution. Asks for the quantity of each product to produce (14 marks) and a further comment (6 marks).

Revise first: Variations that appear in examinations

Section A of each diet (multiple choice)

Multiple-choice items can test the definition of a limiting factor, contribution per unit of the scarce resource and the make-or-buy comparison. Check Section A of every diet you practise.

Revise first: Maximising profit with one limiting factor

Make or buy in earlier papers (previous syllabus)

Questions in earlier papers set make-or-buy comparisons and joint product further processing choices. The same relevant cost approach applies.

Revise first: Make-or-buy decisions

Source: ICAN Pathfinder, Management Accounting. Diets covered: May Diet, 2026 and November Diet, 2025. May Diet, 2025 and November Diet, 2024 are not covered here.

Spotted a mistake? Tell us and we will check it.

Where this fits

See every past question on Management Accounting and the topic each one tests in the Pathfinder question finder.

After it, move on to Performance Management.

All Management Accounting topics

You are reading topic 40 of 41.

  1. Data, information and the qualities of good information01
  2. Nature and purpose of management accounting02
  3. Management information systems03
  4. Spreadsheets in cost and management accounting04
  5. Big data and data analytics05
  6. Cost classification by element, function and behaviour06
  7. Direct and indirect costs, product and period costs, and cost codification07
  8. Cost segregation and the high-low method08
  9. Linear regression and the correlation coefficient09
  10. Inventory procedures, documents and records10
  11. Inventory valuation: FIFO, LIFO and average cost11
  12. Economic order quantity and inventory control levels12
  13. Just-in-time and other inventory management systems13
  14. Labour costs, recording and remuneration methods14
  15. Labour turnover and payroll accounting15
  16. Manufacturing overheads and the stages of absorption costing16
  17. Overhead apportionment and service department costs17
  18. Overhead absorption, under- and over-absorption, fixed and variable overheads18
  19. Job costing and batch costing19
  20. Process costing: normal loss, abnormal loss and abnormal gain20
  21. Process costing: equivalent units and work-in-progress21
  22. Joint products and by-products22
  23. Service costing23
  24. Marginal and absorption costing: preparing profit statements24
  25. Reconciling profits and comparing marginal and absorption costing25
  26. Cost control and cost reduction26
  27. Forecasting: types, process and methods27
  28. Time series analysis and moving averages28
  29. Lines of best fit and seasonal variations29
  30. The budgeting system, principal budget factor and budget process30
  31. Preparing functional budgets31
  32. Cash budgets and the master budget32
  33. Standard costing: purposes, operation and standard cost cards33
  34. Direct material and direct labour variances34
  35. Variable and fixed production overhead variances35
  36. Sales variances and reconciling budgeted and actual profit36
  37. Cost-volume-profit analysis and break-even point37
  38. Margin of safety and break-even charts38
  39. Relevant cost analysis39
  40. Limiting factors and make-or-buy decisions40 here
  41. Other short-term decisions and shutdown decisions41
See the whole course

Get the complete Management Accounting notes

Download as PDF or Word

  • Every topic as PDF and Word, ready to print
  • Edit it in Word or print the PDF. No retyping.
Get this course

Reading stays free. Access lasts 12 months. Pay by card, bank transfer, USSD or QR through Paystack. Your name and email appear on every page of your files. Read our Refund Policy.

PracticeNext topic