A budget normally assumes that the company can make as much as it can sell. Sometimes it cannot. A brewery in Ibadan finds that malt barley is rationed, a clothing factory in Aba has only so many skilled machinists. A printing press can run only so many hours a week.

When one resource limits output, the question is no longer how much the customers want, but which products deserve the scarce resource. The wrong answer is to favour the product with the highest contribution per unit, because it may eat most of the scarce resource. The right answer is to favour the product that earns the most contribution from each unit of the scarce resource.

This topic explains the idea of a limiting factor, how to identify it, how to rank products and build a production plan that maximises contribution, how to deal with a resource given as a naira value, and what to do when more than one resource is limited. It builds on the multi-product CVP topic. The next topic covers linear programming: formulation and graphical solution.

In 30 seconds

A limiting factor (or scarce resource) is the item that restricts the production or sale of a product or service. Normally it is sales demand; sometimes it is a shortage of materials, skilled labour or machine time.

With one limiting factor other than demand, profit is maximised by maximising total contribution: (1) calculate the contribution per unit, (2) identify the scarce resource, (3) calculate the resource used per unit, (4) divide the contribution by the resource used to get contribution per unit of scarce resource, (5) rank the products, (6) build the plan down the ranking up to each product’s demand until the resource is used up.

If the resource is given as a naira value, rank by contribution per ₦1 of the resource. With two or more limiting factors, ranking is not enough and linear programming is used. Full marks come from the ranking and a plan whose resource use adds up to the limit.

The limiting factor

Budgeting often assumes that a company can produce as many units as it needs to meet demand, so sales demand sets the limit. Sometimes a key resource, such as an item of direct materials, skilled labour or machine capacity, is in short supply. Then the limit on sales and profit is the amount of the resource, because sales cannot exceed what can be made.

A limiting factor is the item that restricts or constrains the production or sale of a product or service.

If the company makes one product, profit is maximised by making as many units as the scarce resource allows. If it makes several products that use the same scarce resource, the problem is to decide how many of each to make so as to maximise profit.

Identifying the limiting factor

A question may say that a resource is in short supply without saying which one. Find it by comparing, for each resource, the amount needed to meet the full sales demand with the amount available. A resource for which the need is greater than the supply is limiting. If two are short, there is more than one limiting factor and the problem needs linear programming.

The method for one limiting factor

  1. Contribution per unit of each product (selling price less variable costs).
  2. Identify the scarce resource.
  3. Resource used per unit of each product.
  4. Contribution per unit of scarce resource = contribution per unit ÷ resource per unit.
  5. Rank the products, highest first.
  6. Build the production plan. Work down the ranking, making each product up to its sales demand, until the scarce resource is used up. The last product made may be made in a smaller quantity than its demand.
  7. Total contribution = Σ units × contribution per unit. Subtract fixed costs for profit.

Fixed costs are assumed to be the same whatever the plan, so only contribution matters. Ranking by contribution per unit of product, or by profit per unit, is wrong, because it ignores how much of the scarce resource each unit uses.

Ranking products for one scarce resourceTwo products. Product X earns 12 contribution a unit using 8 minutes, which is 90 an hour. Product Y earns 9 a unit using 5 minutes, which is 108 an hour. Y ranks first. The scarce hours go to Y up to demand, then to X.Product Xcontribution 12, 8 minutes12 ÷ (8 ÷ 60) = 90 an hour: ranks 2ndProduct Ycontribution 9, 5 minutes9 ÷ (5 ÷ 60) = 108 an hour: ranks 1stGive the scarce hours to Y first, up to its demand,then to X with whatever hours remainY has the lower contribution per unit but the higher per scarce hour

Materials by value, and more than one limit

A resource given as a naira value

A question may give the available quantity of a material as a naira amount, not as kilograms. The analysis is the same, using the cost of the material in each unit as the amount of the resource used: contribution per ₦1 of material = contribution per unit ÷ material cost per unit.

Other points

  • Labour. If labour is the scarce resource, find the hours per unit as labour cost ÷ pay rate, and treat labour cost as a variable cost in the contribution as usual.
  • Final answer. The plan should use exactly the available resource, unless demand is met before the resource runs out.
  • Value of extra resource. The contribution per unit of the scarce resource of the last product made is the most the company should pay, over the normal price, for one more unit of the resource.
  • Beyond the numbers. Dropping a product altogether may lose customers, and some customers may need a minimum supply. Management may keep a small output of low-ranked products for strategic reasons.
  • More than one limit. If two or more resources are scarce, the ranking can differ for each, and no single ranking gives the best plan. Linear programming is then used, as the next topic explains.

Layouts

  1. Resource needed for full demand = Σ (demand × resource per unit), compared with the amount available.
  2. Contribution per unit of resource = contribution per unit ÷ resource per unit (for minutes, convert to hours).
  3. Plan table: product, rank, units, resource used, contribution per unit, total contribution; running total of resource used = limit.
  4. Last product = remaining resource ÷ resource per unit.

Money is in naira and answers are exact.

Worked examples

Example 1: identify the limit and make the plan. A company makes X and Y. X uses 8 minutes on machine 1 and 4 minutes on machine 2; Y uses 5 minutes on machine 1 and 10 minutes on machine 2. Demand is 18,000 units of X and 12,000 of Y. Machine 1 has 2,400 hours available and machine 2 has 3,400. Contribution is ₦12 for X and ₦9 for Y. Required: the limiting factor, and the plan that maximises contribution.

  1. Machine 1 for full demand.
    X 18,000 × 8 ÷ 60 = 2,400 hours
    Y 12,000 × 5 ÷ 60 = 1,000 hours.
    Total 3,400 hours against 2,400 available: short.
  2. Machine 2. X 1,200 hours; Y 2,000 hours; total 3,200 against 3,400: enough. Machine 1 is the limiting factor.
  3. Per machine 1 hour.
    X 12 ÷ (8 ÷ 60) = ₦90
    Y 9 ÷ (5 ÷ 60) = ₦108.
    Rank Y first, X second.
  4. Plan. Y: 12,000 units use 1,000 hours.
    Remaining 1,400 hours for X: 1,400 ÷ (8 ÷ 60) = 10,500 units, less than demand.
  5. Contribution.
    Y 12,000 × 9 = ₦108,000
    X 10,500 × 12 = ₦126,000.
    Total ₦234,000.
  6. Comment. X has the higher contribution per unit but Y earns more per scarce hour, so Y is made in full and X fills the rest.

Example 2: a material given as a value. A company makes W, X, Y and Z. Contribution per unit: W ₦3,200, X ₦1,500, Y ₦2,800, Z ₦2,100. Material cost per unit: W ₦400, X ₦300, Y ₦700, Z ₦350. Demand: W 400, X 300, Y 200, Z 500. Only ₦519,500 of material is available. Required: the best plan.

  1. Contribution per ₦1 of material.
    W 3,200 ÷ 400 = 8.0
    Z 2,100 ÷ 350 = 6.0
    X 1,500 ÷ 300 = 5.0
    Y 2,800 ÷ 700 = 4.0.
    Rank W, Z, X, Y.
  2. W.
    Demand 400 units × ₦400 = ₦160,000 of material.
  3. Z.
    500 × 350 = ₦175,000.
    Cumulative ₦335,000.
  4. X.
    300 × 300 = ₦90,000.
    Cumulative ₦425,000.
  5. Y.
    Remaining 519,500 − 425,000 = ₦94,500
    ÷ 700 = 135 units, less than the demand of 200.
  6. Contribution.
    W 400 × 3,200 = ₦1,280,000
    Z 500 × 2,100 = ₦1,050,000
    X 300 × 1,500 = ₦450,000
    Y 135 × 2,800 = ₦378,000.
    Total ₦3,158,000.
  7. Comment. The product with the lowest ratio, Y, is cut back; the highest, W, is made in full. The material used adds up to the amount available.

Expect variants: labour hours as the scarce resource, minutes to convert to hours, a minimum output for one product, and a question that asks for the most that should be paid for an extra unit of the resource.

Choosing one product under several limits, and overcoming constraints

Sometimes only one of two products can be made, and there are several limits (two machine lines, a scarce material, market demand). This is not a linear programming problem: work out the maximum output of each product under each limit separately, take the lowest figure, find the contribution at that output, and compare the products. Example. Machine A has 10,000 hours, machine B 12,000 hours, material 90,000 kg.

Product P: 0.20 and 0.30 hours, 2 kg, demand 50,000, contribution ₦260. Product Q: 0.25 and 0.25 hours, 2.5 kg, demand 40,000, contribution ₦300. P: A 50,000; B 40,000; material 45,000; demand 50,000, so 40,000 units, contribution ₦10.4m. Q: A 40,000; B 48,000; material 36,000; demand 40,000, so 36,000 units, contribution ₦10.8m. Make Q.

Surplus hours. If spare machine hours can be sold at ₦400 an hour (A) and ₦350 an hour (B): Q leaves 1,000 hours of A and 3,000 of B, worth 400,000 + 1,050,000 = ₦1.45m, giving ₦12.25m; P leaves 2,000 hours of A and none of B, worth ₦0.8m, giving ₦11.2m. Q is still better.

Ways to overcome a capacity constraint, with the costs. Hire or buy more machines (hire or financing cost); raise output per hour by faster running (breakdowns, lost output); add shifts or overtime (premium pay, wear and breakdowns); sub-contract or outsource (higher unit cost, risk to quality and delivery); find another source of the scarce material (higher price, delivery cost); and for a demand limit, spend on marketing or cut price (advertising cost, lower margin).

Each is worth doing only if the extra contribution exceeds the extra cost.

The minimum penalty that makes meeting a contract worthwhile

A major customer’s order is at a discount, and the scarce material means that it may not be possible to supply everything. Treat the discount as a variable cost of the special order only.

Compare the best plan without a penalty (which may supply only part of the order) with the best plan that meets the contract in full. The lowest penalty that would make the customer’s order be met in full is the difference. Example. Material 9,000 kg. Product F: contribution ₦700, 5 kg; product G: ₦540, 4 kg. Normal demand F 1,000 and G 500 (7,000 kg). Special order: 400 units of each at a discount of ₦50 a unit (3,600 kg).

Without a penalty: make the normal demand (₦970,000) and use the 2,000 kg left on the special order, ranked per kg after discount (F 650 ÷ 5 = 130; G 490 ÷ 4 = 122.5): 400 units of F, ₦260,000; total ₦1,230,000. Meeting the order in full: special order 400 × 650 + 400 × 490 = ₦456,000 uses 3,600 kg; the remaining 5,400 kg make 1,000 F (5,000 kg) and 100 G: ₦754,000; total ₦1,210,000. The penalty must be at least 1,230,000 − 1,210,000 = ₦20,000.

Constraints given as maximum revenue, and several machine types

If demand is given as maximum revenue, divide by the selling price to get maximum units. Calculate the hours needed for maximum demand on each machine type and compare with the hours available: only a type that is short is a limiting factor (a type with spare hours is not).

Rank products by contribution per hour of the short machine, make the best-ranked up to demand and the last with the hours that remain. Fixed costs of each machine block are deducted at the end; a fixed cost attributable to a product is relevant only if the product could be dropped.

Common mistakes

  • Ranking by contribution per unit of product. Rank by contribution per unit of the scarce resource.
  • Ranking by profit per unit. Fixed costs are the same in every plan.
  • Not identifying the limiting factor first. Compare need with supply for each resource.
  • Not converting minutes to hours.
  • Exceeding demand. Stop each product at its demand.
  • A plan that does not use exactly the resource available. Check the total.

Quick revision

  • Limiting factor: resource that restricts output. Compare need for full demand with supply.
  • One limit: contribution per unit of scarce resource; rank; plan to demand until resource is gone.
  • Materials as a value: contribution per ₦1 of material.
  • Two or more limits: linear programming.

How the marks are earned

  • Identify: a mark for each resource compared and the limiting one named.
  • Rank: contribution per unit of resource for each product.
  • Plan: units, resource used, contribution, and a total that ties to the limit.

Practice questions

These are original questions, written in the style of the Skills examination. Work each one before you open the answer.

Recall check: multiple choice

Question 1. A limiting factor is:

  1. A fixed cost
  2. A type of tax
  3. A resource that restricts production or sales
  4. A selling price
Show the answer

C. Normally it is demand; sometimes it is a scarce resource.

Question 2. With one limiting factor, profit is maximised by ranking products by:

  1. Contribution per unit of the scarce resource
  2. Contribution per unit of product
  3. Selling price
  4. Profit per unit
Show the answer

A. The scarce resource is what is rationed.

Question 3. Contribution per unit of scarce resource equals:

  1. Resource used ÷ contribution
  2. Contribution × resource used
  3. Price ÷ resource used
  4. Contribution per unit ÷ resource used per unit
Show the answer

D. For example ₦ per machine hour.

Question 4. Ranking by contribution per unit of product, when there is a scarce resource, is:

  1. Always correct
  2. Wrong, because products use different amounts of the resource
  3. Required by law
  4. Equal to ranking by price
Show the answer

B. It ignores the resource use of each unit.

Question 5. Normally the limiting factor in a budget is:

  1. Sales demand
  2. Machine time
  3. Skilled labour
  4. Materials
Show the answer

A. Sometimes a resource is scarcer.

Question 6. To identify the limiting factor you compare:

  1. Prices
  2. Fixed costs
  3. The amount of each resource needed for full demand with the amount available
  4. Profits
Show the answer

C. The resource that is short is limiting.

Question 7. When a material is given as a naira value, products are ranked by:

  1. Selling price
  2. Contribution per ₦1 of material
  3. Demand
  4. Profit
Show the answer

B. Use the material cost in each unit.

Question 8. The production plan is built by:

  1. Making equal amounts of each product
  2. Dropping the highest-ranked product
  3. Making only the cheapest
  4. Working down the ranking up to demand until the resource is used up
Show the answer

D. The last product may be made in less than its demand.

Question 9. In limiting factor analysis, fixed costs are:

  1. Added to variable costs
  2. Ranked first
  3. Assumed the same in every plan, so only contribution matters
  4. Ignored in the final profit
Show the answer

C. They are deducted from total contribution for profit.

Question 10. If two or more resources are scarce, the method needed is:

  1. Linear programming
  2. Simple ranking
  3. Absorption costing
  4. Break-even analysis
Show the answer

A. Rankings may differ for each resource.

Section B style: written questions

Question 11 (10 marks). (a) Explain what a limiting factor is and how it is identified. (4 marks) (b) State the steps in finding the plan that maximises contribution with one limiting factor. (6 marks)

Question 12 (15 marks). A company makes A, B, C and D using the same labour. Contribution per unit: A ₦18, B ₦30, C ₦12, D ₦40. Labour hours per unit: A 0.5, B 1.0, C 0.25, D 2.0. Annual demand: A 4,000, B 3,000, C 6,000, D 2,000 units. Only 7,000 labour hours are available.

(a) Calculate the hours needed for full demand and identify the limit. (3 marks) (b) Calculate the contribution per labour hour and rank the products. (4 marks) (c) Prepare the plan and calculate the contribution. (6 marks) (d) Calculate the hours not available. (2 marks)

Question 13 (20 marks). A company makes P, Q and R from one material. Contribution per unit: P ₦60, Q ₦45, R ₦70. Material per unit: P 1.5 kg, Q 0.9 kg, R 2.0 kg. Demand: P 2,000, Q 3,000, R 1,500 units. Only 6,000 kg are available.

(a) Show that the material is the limiting factor. (3 marks) (b) Calculate the contribution per kg and rank the products. (4 marks) (c) Prepare the plan and calculate the contribution. (5 marks) (d) State the most the company should pay over the normal price for one more kilogram. (3 marks) (e) Discuss other factors that management should consider before following the plan. (5 marks)

Model answers

Show the model answer to Question 11

(a) A limiting factor is the item that restricts production or sales (1). Normally it is sales demand, but it can be a scarce resource such as materials, labour or machine time (1). To identify it, calculate the amount of each resource needed to meet full demand and compare with the amount available (2).

(b) Calculate the contribution per unit (1); identify the scarce resource (1); calculate its use per unit (1); calculate contribution per unit of the resource (1); rank the products (1); build the plan down the ranking up to demand until the resource is used up (1).

Show the model answer to Question 12

(a)

  1. A 4,000 × 0.5 = 2,000
  2. B 3,000 × 1.0 = 3,000
  3. C 6,000 × 0.25 = 1,500
  4. D 2,000 × 2.0 = 4,000.
  5. Total 10,500 hours against 7,000 available: labour is limiting (3).

(b)

  1. A 18 ÷ 0.5 = ₦36
  2. B 30 ÷ 1.0 = ₦30
  3. C 12 ÷ 0.25 = ₦48
  4. D 40 ÷ 2.0 = ₦20.
  5. Rank C, A, B, D (4).

(c) C 6,000 units, 1,500 hours, contribution ₦72,000. A 4,000 units, 2,000 hours, ₦72,000. B 3,000 units, 3,000 hours, ₦90,000. Hours used 6,500; the remaining 500 hours make D 250 units, ₦10,000. Total ₦244,000 (6).

(d) Hours short of full demand 10,500 − 7,000 = 3,500 hours, all of it from D (1,750 units not made) (2).

Show the model answer to Question 13

(a)

  1. P 2,000 × 1.5 = 3,000 kg
  2. Q 3,000 × 0.9 = 2,700 kg
  3. R 1,500 × 2.0 = 3,000 kg.
  4. Total 8,700 kg against 6,000: material is short (3).

(b)

  1. P 60 ÷ 1.5 = ₦40
  2. Q 45 ÷ 0.9 = ₦50
  3. R 70 ÷ 2.0 = ₦35.
  4. Rank Q, P, R (4).

(c) Q 3,000 units, 2,700 kg, contribution ₦135,000. P 2,000 units, 3,000 kg, ₦120,000. Kg used 5,700; 300 kg remain for R: 150 units, contribution ₦10,500. Total ₦265,500 (5).

(d) The last product made is R, which earns ₦35 per kg, so the company should pay no more than ₦35 a kg above the normal price (3).

(e) Any five:

  • effect on customers if R is cut back
  • minimum supply agreements
  • whether the shortage is temporary and inventory can be built
  • whether more material can be bought at a higher price
  • reliability and quality
  • the effect on future sales
  • other scarce resources (1 each)

Pathfinder on Limiting factors: a single scarce resource

These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.

November Diet, 2025: Question 1 (30 marks)

Marginal mix for one plant, throughput accounting profitability, new plant marginal statement, break-even units and value, combined statement, RI viability.

Revise first: Layouts

May Diet, 2025: Question 3 (20 marks)

LP formulation, simultaneous equations, shadow prices as overtime limits, single-product choice.

Revise first: Layouts

May Diet, 2025: Question 7 (15 marks)

Throughput accounting ratio with bottleneck, optimum mix with contract minimum, ways to raise bottleneck capacity.

Revise first: Layouts

May Diet, 2024: Question 1 (30 marks)

Machine utilisation and bottleneck; marginal analysis; throughput accounting mix; TA inventory valuation; scarce resources in budgets and LP.

Revise first: Layouts

May Diet, 2024: Question 7 (15 marks)

Optimal production plan with machine-hour limits (three types), profit after fixed costs.

Revise first: Layouts

November Diet, 2023: Question 1 (30 marks)

LP objective and constraints, optimum plan, dual prices by one-unit change, slack, ways to overcome capacity limits.

Revise first: Layouts

November Diet, 2023: Question 4 (20 marks)

Marginal costing mix, throughput accounting ratio and mix, TA v marginal contribution.

Revise first: Layouts

November Diet, 2021: Question 1 (30 marks)

Limiting factor with special order and penalty; outsourcing pros and cons; budget constraint causes.

Revise first: Layouts

November Diet, 2021: Question 3 (20 marks)

TAR and profit-maximising output, advantages over marginal costing.

Revise first: Layouts

May Diet, 2021: Question 1 (40 marks)

LP concept and uses; cost-plus prices; optimal output; shadow prices (e: NPV/IRR outside course).

Revise first: Layouts

May Diet, 2021: Question 2 (20 marks)

Choose forecast with limiting material; principal budget factor, manual, committee.

Revise first: Layouts

November Diet, 2020: Question 2 (20 marks)

Marginal costing v throughput accounting, TAR, profit-maximising output.

Revise first: Layouts

March/July Diet, 2020: Question 1 (40 marks)

Single limiting factors for two components, spare capacity outlets, ways to overcome constraints, opportunity cost of material/labour/overhead.

Revise first: Layouts

Source: ICAN Pathfinder, Performance Management. Diets covered: March/July Diet, 2020 to May Diet, 2026. All 13 diets in the Pathfinder are mapped.

Spotted a mistake? Tell us and we will check it.

Where this fits

See every past question on Performance Management and the topic each one tests in the Pathfinder question finder.

This course builds on Management Accounting. After it, move on to Strategic Financial Management.

All Performance Management topics

You are reading topic 23 of 77.

  1. Information systems in organisations: role, costs and benefits01
  2. Internet, intranet, wireless technology and networks in business02
  3. Information needs at strategic, tactical and operational levels03
  4. TPS, MIS, EIS, ERP and CRM systems compared04
  5. Social and ethical issues in strategy and the management accountant’s data role05
  6. Big data principles and the big data pyramid06
  7. Big data, data mining and analytics: uses, benefits, challenges and risks07
  8. Activity based costing: cost pools, cost drivers and calculations08
  9. Activity based costing compared with traditional absorption costing09
  10. Target costing: principles and calculating the target cost10
  11. Managing the target cost gap and target costing in services11
  12. Life cycle costing: product life cycle stages and costs12
  13. Life cycle cost and profit calculations, and the benefits of life cycle costing13
  14. Throughput accounting: theory of constraints and the throughput accounting ratio14
  15. Environmental management accounting and sustainability in business15
  16. Environmental costs: methods, challenges and the management accountant’s role16
  17. Relevant costs and revenues, and opportunity cost17
  18. Relevant costs for specific decisions: materials, labour, equipment and overheads18
  19. Break-even analysis and margin of safety for Skills level decisions19
  20. Contribution to sales ratio, target profit and target revenue20
  21. Break-even charts and profit-volume charts21
  22. Multi-product CVP analysis and its limitations22
  23. Limiting factors: allocating a single scarce resource23 here
  24. Linear programming: formulation and graphical solution24
  25. Linear programming: slack and shadow prices25
  26. Price elasticity of demand and the factors that influence price26
  27. Demand and cost functions: profit-maximising price and output27
  28. Cost-based pricing: cost-plus and relevant-cost pricing28
  29. Market-based pricing: skimming, penetration and other strategies29
  30. Make-or-buy and outsourcing decisions30
  31. One-off contracts, shutdown and further processing of joint products31
  32. Reducing uncertainty: research, simulation and sensitivity analysis32
  33. Expected values and decision rules: maximax, maximin and minimax regret33
  34. Decision trees for multi-stage decisions34
  35. Value of perfect and imperfect information35
  36. Budgetary systems and types of budget: choosing the right one36
  37. Preparing fixed and flexed budgets37
  38. Rolling, activity-based, functional and master budgets38
  39. The beyond budgeting model: benefits and problems39
  40. Participation, negotiation and ethics in budgeting40
  41. High-low method and cost estimation for budgets41
  42. Correlation, regression and time series for budgeting and forecasting42
  43. Learning curve: learning rate and learning effect43
  44. Learning curve in budgeting: steady state and limitations44
  45. Standard costing: uses, how standards are set and types of standard45
  46. Basic variances: material, labour and idle time46
  47. Material mix and yield variances47
  48. Labour mix and yield variances48
  49. Sales mix and quantity variances49
  50. Planning and operational variances: revised budget, sales, market size and market share50
  51. Planning and operational variances for materials and labour51
  52. Overhead variances and reconciling budgeted and actual profit at Skills level52
  53. Behavioural effects of variances: motivation, JIT and TQM53
  54. Profitability ratios and financial performance measures54
  55. Liquidity, solvency and efficiency ratios55
  56. Non-financial performance indicators56
  57. Short-termism and financial manipulation of results57
  58. Sustainability and ESG performance measures58
  59. The balanced scorecard59
  60. The Fitzgerald and Moon building block model60
  61. Performance measurement in not-for-profit organisations61
  62. Value for money as a public sector objective62
  63. Divisional performance: return on investment and residual income63
  64. Economic value added (EVA)64
  65. Transfer pricing methods and the optimal transfer price65
  66. Transfer pricing: problems, tax and repatriation of funds66
  67. Value chain analysis for performance management67
  68. Complex business structures: alliances, joint ventures and supply chains68
  69. The performance pyramid69
  70. Value-based management70
  71. Corporate failure and life cycle issues71
  72. The Z-score and other quantitative failure models72
  73. The Argenti model and qualitative failure prediction73
  74. Preventing corporate failure and performance improvement strategies74
  75. Current developments in management accounting75
  76. Benchmarking and target setting in the public sector76
  77. The changing role of the management accountant and contemporary issues77
See the whole course

Get the complete Performance Management notes

Download as PDF or Word

  • Every topic as PDF and Word, ready to print
  • Edit it in Word or print the PDF. No retyping.
Get this course

Reading stays free. Access lasts 12 months. Pay by card, bank transfer, USSD or QR through Paystack. Your name and email appear on every page of your files. Read our Refund Policy.

PracticeNext topic