A soft drinks plant in Lagos produces millions of identical bottles a month. Each bottle uses the same quantity of syrup, the same bottle, the same minutes of line labour.
When the monthly accounts arrive the finance manager does not want to know the total cost of the month: she wants to know whether the plant used more syrup than it should have, whether it paid more for it than it should have, and whether the line ran as fast as it should.
That calls for a yardstick, set in advance, against which the actual can be compared, and this yardstick is the standard cost.
This topic explains what standard costing is, when it is appropriate, how a standard cost card is built up, who sets each element, the four uses of standard costing, the principle of controllability in reporting variances, the types of standard (ideal, attainable, current and basic) with their behavioural effects, and how often standards should be reviewed.
It builds on the earlier topic on the learning curve in budgeting, which showed one way in which a standard time may change. The next topic covers the basic variances: material, labour and idle time.
In 30 seconds
A standard cost is an estimated, predetermined cost of performing an operation or producing a good or service under normal conditions: standard quantities of materials and labour time, priced at standard rates, plus overhead at a standard rate per hour. Standard costing is a control technique that reports variances between actual and standard costs, so that management can act by exception.
It suits homogeneous products made in large numbers with repetition. Standards are set by those with the expertise: purchasing for material prices, human resources for pay rates, operations or technical staff for usage and efficiency, and a senior management accountant for overhead rates (budgeted overhead ÷ budgeted activity). Four uses: a costing system (units and stock recorded at standard); a basis for the budget; performance measurement; and control reporting.
Variances should be reported to the manager who is responsible and able to control them. Types of standard: ideal (perfect conditions, always adverse, demotivating), attainable (efficient but not perfect, challenging, most motivating), current (present performance, no incentive to improve) and basic (unchanged for long periods, rarely used). Standards should be reviewed regularly, normally each year in the budget process.
Full marks come from building a standard cost correctly and discussing the types with their effects.
Standard costs and standard costing
Standard units and when standard costing is appropriate
Standard costing is most useful when an entity makes homogeneous goods in large numbers and there is a degree of repetition in the process. A standard unit of product (or service) should have exactly the same input resources, at exactly the same prices, as every other, so all units have the same standard cost. It is usually associated with manufacturing, but can be applied to standard services.
In a one-off or highly variable production it is much less useful.
Definitions
A standard cost is an estimated or predetermined cost of performing an operation or producing a good or service under normal conditions. Standard costing is a control technique that reports variances by comparing actual costs with pre-set standards, so facilitating action through management by exception.
A standard cost is a predetermined unit cost built from expected quantities of direct materials and expected direct labour time, priced at predetermined rates per unit of material, per direct labour hour and per hour of overhead. Standard costs of products are normally restricted to production costs; administration and selling overheads are not included. Overhead is normally absorbed into standard production cost at a rate per direct labour hour.
The standard cost card
The standard cost of a unit is recorded on a standard cost card: a document that shows the predetermined standard quantities, prices and rates for materials, labour and overhead needed for one unit. The card links to the budget through activity levels: if 1,200 units are budgeted and a unit needs materials costing ₦5,000, the materials budget is ₦6,000,000.
How the elements are set, and by whom
- Material prices: from past purchase records, adjusted for expected inflation and changes in trade discounts, by managers with purchasing expertise.
- Labour rates: an average rate for each grade, based on current pay or the expected average for the year including an expected pay rise, by managers with expertise in pay, usually human resources.
- Material usage: from past records of use, or from the design specification, by operational or technical managers.
- Labour efficiency (time per unit): from past records, comparison with similar work, or time and motion study, by operational managers.
- Overhead rates: a senior management accountant, using the budgeted overhead and the budgeted activity agreed in the annual budget. The standard fixed overhead cost per unit is the budgeted fixed overhead divided by budgeted activity (in hours or units), multiplied by the hours or units per product.
Standards are normally set by people who understand the process, and are usually reviewed once a year in the budgeting process.
The uses of standard costing
- A system of cost accounting. Units produced are recorded at standard cost and stock is valued at standard production cost.
- The basis of the budget. Budgeted costs are standard cost per unit multiplied by planned activity.
- Performance measurement. The differences between standard and actual costs, the variances, are reported to show good or poor performance.
- Control reporting. Large variances signal that operations may need attention: adverse variances call for control action; large favourable ones should be investigated, to find out why and whether it will continue.
Standard costing can be used with absorption costing or with marginal costing.
Controllability
Variances should be reported to the manager who is responsible for the area to which they relate and who is able to do something to control them. Reporting a variance to someone who cannot influence it has no purpose, and holding a manager accountable for something outside his control is unfair and demotivating.
Types of standard and reviewing standards
Standards are predetermined unit costs, but how much efficiency should they assume? Should they assume perfect conditions, or allow for waste and idle time? The standard is a performance target. If it seems unattainable, employees may be demotivated; if it is too easy, there is no incentive to improve. Four types are used.
- Ideal standards assume perfect operating conditions: no waste, no labour inefficiency, no breakdowns. They are never achieved, so variances are always adverse and staff may be demotivated when their performance is always worse than standard. They are useful as long-term targets and show senior management the potential for savings.
- Attainable standards assume efficient but not perfect conditions, with an allowance for waste and inefficiency, set at a higher level than current performance so that some improvement is needed. They are the most likely to motivate, since they are challenging but achievable. The difficulty is deciding how much improvement to require: 1%, 5% or 10%.
- Current standards are based on present working conditions and what the entity can achieve now. They give a realistic guide for budgeting, but no incentive to improve unless bonuses are paid for favourable variances; and where current performance is inefficient they build the inefficiency in. They may include allowances for expected waste or idle time.
- Basic standards stay unchanged over a long period. Variances show trends (improving or worsening performance) but the standards are out of date, do not motivate and are not useful for budgeting. They are the least common.
Reviewing standards. Standards should be revised regularly so that they are meaningful targets that staff may be motivated to achieve, so that reported variances are realistic and not just reflecting out-of-date standards. In practice they are reviewed annually in the budgeting process, since they are long-term averages and some variation is expected over time.
Layouts for building a standard cost
- Materials: quantity per unit × standard price, for each material.
- Labour: hours per unit × standard rate, for each grade.
- Variable overhead: hours per unit × variable rate per hour.
- Standard variable (marginal) cost = total of the above.
- Fixed overhead rate = budgeted fixed overhead ÷ budgeted hours (or units); fixed overhead per unit = hours per unit × rate.
- Standard full production cost = variable cost + fixed overhead per unit.
Money is in naira and each answer is rounded once, at the end.
Worked examples
Example 1: a standard cost card. A unit of Alpha needs 3 kg of material A at ₦250 a kg and 2 kg of material B at ₦400 a kg; grade 1 labour 1.5 hours at ₦600 and grade 2 labour 1 hour at ₦450; variable overhead ₦120 per labour hour. Budgeted fixed production overhead is ₦4,500,000 for 12,000 units. Required: the standard variable cost and standard full production cost.
- Materials.
A 3 × 250 = 750; B 2 × 400 = 800; total ₦1,550. - Labour.
Grade 1 1.5 × 600 = 900; grade 2 1 × 450 = 450; total ₦1,350. - Variable overhead.
2.5 hours × 120 = ₦300. - Standard variable cost.
1,550 + 1,350 + 300 = ₦3,200. - Fixed overhead.
Budgeted hours = 12,000 × 2.5 = 30,000
rate = 4,500,000 ÷ 30,000 = ₦150 an hour
per unit 2.5 × 150 = ₦375. - Standard full production cost.
3,200 + 375 = ₦3,575.
A budget for 1,200 units would show materials ₦1,860,000 (1,200 × 1,550).
Example 2: the type of standard changes the variance. A plant made 5,000 units and used 12,500 labour hours at a standard rate of ₦600 an hour. The standard time per unit is 2.0 hours (ideal), 2.4 hours (attainable) or 2.5 hours (current). Required: the labour efficiency variance under each.
- Ideal.
Standard hours 5,000 × 2.0 = 10,000; actual 12,500; 2,500 hours adverse × 600 = ₦1,500,000 A. - Attainable.
Standard hours 5,000 × 2.4 = 12,000
500 hours adverse × 600 = ₦300,000 A. - Current.
Standard hours 5,000 × 2.5 = 12,500; variance nil. - Comment. The performance is identical; the variance depends entirely on the standard. The ideal standard gives a large permanent adverse figure that tells the manager nothing new and may discourage; the current standard shows nothing and gives no push to improve; the attainable standard shows a modest adverse figure that points to a possible 500 hours of improvement.
Expect variants: a standard cost card with a normal loss, a standard for a service (hours and rates), a request to say who should set each standard, and a discussion of the behavioural effects of each type.
Common mistakes
- Including selling and administration costs in the standard production cost.
- Dividing fixed overhead by units when the rate is per labour hour, or the reverse.
- Calling an ideal standard attainable.
- Listing the types without their behavioural effects.
- Reporting variances to the wrong person.
- Forgetting to review standards when conditions change.
Quick revision
- Standard cost = predetermined unit cost; standard costing reports variances for management by exception; suits repetitive, homogeneous output.
- Setters: purchasing (prices), HR (rates), operations (usage and efficiency), management accountant (overhead rates).
- Uses: costing system, budget basis, performance measure, control report.
- Types: ideal, attainable, current, basic; attainable motivates most; review at least annually.
How the marks are earned
- Build the card in the correct order.
- Explain who sets what and why.
- Discuss the types with their behavioural effects.
Practice questions
These are original questions, written in the style of the Skills examination. Work each one before you open the answer.
Recall check: multiple choice
Question 1. A standard cost is:
- The actual cost
- A predetermined unit cost
- The selling price
- The tax cost
Show the answer
B. It is set in advance under normal conditions.
Question 2. Standard costing is most useful for:
- One-off jobs
- Unique products
- Services with no pattern
- Homogeneous goods made in large numbers with repetition
Show the answer
D. Units should have the same inputs.
Question 3. Standard material prices are best set by managers with:
- Purchasing expertise
- Sales expertise
- Audit expertise
- No expertise
Show the answer
A. They know supplier prices.
Question 4. Standard labour rates are best set by:
- The sales manager
- The auditor
- Human resources managers
- The customer
Show the answer
C. Using average rates for each grade.
Question 5. The standard fixed overhead rate comes from:
- Budgeted fixed overhead ÷ budgeted activity
- Actual overhead
- Sales
- Direct materials
Show the answer
A. Agreed in the annual budget.
Question 6. An ideal standard assumes:
- Average conditions
- Past performance
- Allowances for waste
- Perfect operating conditions
Show the answer
D. Variances are always adverse.
Question 7. The type of standard most likely to motivate is:
- Ideal
- Attainable
- Basic
- None
Show the answer
B. It is challenging but achievable.
Question 8. Current standards:
- Are perfect
- Are never used
- Reflect present efficiency and give no incentive to improve
- Never change
Show the answer
C. Unless bonuses reward favourable variances.
Question 9. Basic standards:
- Remain unchanged over a long period
- Change monthly
- Are the most common
- Assume perfection
Show the answer
A. They show trends but are out of date.
Question 10. Variances should be reported to:
- Everyone
- Customers
- The manager responsible who can control them
- Nobody
Show the answer
C. This is the controllability principle.
Section B style: written questions
Question 11 (10 marks). (a) State FOUR uses of standard costing. (4 marks) (b) State who should set each of the standard material price, labour rate, material usage and overhead rate. (4 marks) (c) Explain controllability. (2 marks)
Question 12 (15 marks). A product needs 4 kg of material at ₦300 a kg and 2 labour hours at ₦500 an hour. Variable overhead is ₦200 per labour hour. Budgeted fixed production overhead is ₦2,400,000 for 6,000 units.
(a) Calculate the standard variable cost per unit. (4 marks) (b) Calculate the fixed overhead absorption rate per hour. (3 marks) (c) Calculate the standard full production cost per unit. (2 marks) (d) State who sets each element. (4 marks) (e) State TWO limitations of standard costing. (2 marks)
Question 13 (20 marks). A company made 4,000 units using 9,000 labour hours at a standard rate of ₦500 an hour. The standard time per unit is 2.0 hours (ideal), 2.2 hours (attainable) or 2.25 hours (current).
(a) Explain the four types of standard. (8 marks) (b) Calculate the labour efficiency variance under the ideal, attainable and current standards. (6 marks) (c) Discuss the behavioural effects of each type. (6 marks)
Model answers
Show the model answer to Question 11
(a) A costing system; the basis of the budget; performance measurement; control reporting (4).
(b) Material price: purchasing; labour rate: human resources; material usage: operations or technical managers; overhead rate: a senior management accountant (4).
(c) Variances should be reported to the manager who is responsible for the area and able to control them (2).
Show the model answer to Question 12
(a) Materials 4 × 300 = 1,200; labour 2 × 500 = 1,000; variable overhead 2 × 200 = 400; total ₦2,600 (4).
(b)
- Budgeted hours 6,000 × 2 = 12,000
- rate 2,400,000 ÷ 12,000 = ₦200 an hour (3).
(c)
- Fixed overhead per unit 2 × 200 = 400
- full cost 2,600 + 400 = ₦3,000 (2).
(d) Prices: purchasing; rates: human resources; usage and efficiency: operations; overhead rates: management accountant (4).
(e) Any two: unsuitable for non-standard output; standards become out of date; may discourage improvement beyond standard; the variances need interpretation (2).
Show the model answer to Question 13
(a) Ideal: perfect conditions; attainable: efficient but not perfect, with allowances; current: present performance; basic: unchanged for long periods (2 each).
(b)
- Ideal.
standard hours 4,000 × 2 = 8,000 - 1,000 hours adverse × 500 = ₦500,000 A.
- Attainable.
4,000 × 2.2 = 8,800 - 200 hours adverse × 500 = ₦100,000 A.
- Current.
4,000 × 2.25 = 9,000; nil (2 each).
(c) Ideal: constant adverse variances demotivate. Attainable: challenging but achievable, so motivates. Current: realistic but no incentive to improve. Basic: out of date, no motivation (6).
Pathfinder on Standard costing
These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.
Price, mix, yield, sales price, market size and share variances; strategy in a declining market.
Revise first: Layouts for building a standard cost
Standard cost card; April variances; reconcile budgeted and actual contribution; fixed overhead capacity/efficiency; factors in investigating variances.
Revise first: Layouts for building a standard cost
Variance reconciliation under marginal costing, fixed overhead variances, causes of labour variances.