Overhead Variances and Reconciling Budgeted Profit to Actual Profit

ICAN Skills, Performance Management. Syllabus area D: Budgeting and control.

11 min read · Updated 8 November 2026

Download this topic

In this part

At the end of a month a management accountant in a tyre factory has the cost variances for materials and labour, and now has to deal with overheads. The variable overhead is easy: it behaves like labour, because it is driven by hours.

The fixed overhead is odd: it does not change with output, yet the product cost includes a share of it, so the difference between what the factory absorbed and what it spent has to be explained. Then, the managing director asks for a single page that explains why profit was ₦1.4 million below budget. This page is the operating statement.

This topic covers the variable overhead variances (expenditure and efficiency); the fixed overhead variances under absorption costing (total, expenditure, volume, and the split of volume into capacity and efficiency); the sales variances in the statement; the three resource utilisation ratios (efficiency, capacity and production volume); and the operating statement under both standard absorption costing and standard marginal costing, so that the budgeted profit is reconciled with the actual profit.

It builds on the earlier topic on planning and operational variances for materials and labour. The next topic covers the behavioural effects of variances: motivation, JIT and TQM.

In 30 seconds

Variable overhead. Expenditure = (actual hours worked × standard rate) − actual variable overhead (idle hours incur no variable overhead). Efficiency = the labour efficiency variance in hours × the standard variable overhead rate per hour. Fixed overhead (absorption costing). Total = overhead absorbed (actual units × standard fixed overhead per unit) − actual fixed overhead (over- or under-absorption). Expenditure = budgeted − actual fixed overhead.

Volume = (actual units − budgeted units) × standard fixed overhead per unit; it splits into efficiency (hours variance as for labour × fixed rate per hour) and capacity (actual hours worked − budgeted hours) × fixed rate per hour. Efficiency + capacity = volume; expenditure + volume = total. Ratios: efficiency = standard hours for actual output ÷ actual hours worked; capacity = actual hours worked ÷ budgeted hours; production volume = standard hours for actual output ÷ budgeted hours; efficiency × capacity = production volume.

Operating statement (absorption): budgeted profit ± sales price and volume (at standard profit) → ± cost variances → actual profit. Marginal: start with budgeted contribution; sales volume at standard contribution; no fixed overhead volume variance; fixed overhead shown as budgeted and actual with the expenditure variance. Full marks come from correct bases, signs and a statement that reconciles.

Overhead variances

Variable production overhead

The total variable overhead variance is the standard variable overhead cost of the actual output less the actual variable overhead, split into two parts, just as for labour.

  • Expenditure variance. Variable overhead is incurred during hours actively worked, not during idle time, so it is based on actual hours worked: (actual hours worked × standard rate per hour) − actual variable overhead cost. It resembles a price variance. Causes: price rises in power or consumables; savings not achieved.
  • Efficiency variance. In hours it is the same as the labour efficiency variance (standard hours for the actual output − actual hours worked), valued at the standard variable overhead rate per hour. Causes are the same as for labour efficiency: methods, morale, incentives, the experience of the labour force.

Fixed production overhead (absorption costing)

Under standard absorption costing each unit is charged with a standard fixed overhead cost, found as budgeted fixed overhead ÷ budgeted activity (a rate per hour, or per unit). The fixed overhead variances therefore differ from the variable ones.

  • Total fixed overhead variance = fixed overhead absorbed (actual units × standard fixed overhead per unit) − actual fixed overhead incurred. This is the over-absorption (favourable) or under-absorption (adverse).
  • Expenditure variance = budgeted fixed overhead − actual fixed overhead. Adverse if more was spent than budgeted. It can also be found for administration and selling overheads. Causes: poor control or poor budgeting; an unplanned rise in rent or rates.
  • Volume variance = (actual units produced − budgeted units) × standard fixed overhead per unit. It arises because production differs from the budgeted volume used to set the absorption rate. It can be analysed further into two parts.
  • Efficiency variance (fixed overhead) = (standard hours for actual output − actual hours worked) × the standard fixed overhead rate per hour. It is the labour efficiency variance in hours, again.
  • Capacity variance = (actual hours worked − budgeted hours) × the standard fixed overhead rate per hour. Favourable if more hours were worked than budgeted. Causes: strikes, breakdowns or a shortage of orders (adverse); extra shifts (favourable).

Expenditure + volume = total; efficiency + capacity = volume. Interrelationship: higher efficiency means fewer hours are needed for the budgeted output, so a favourable efficiency variance may cause an adverse capacity variance, and the reverse.

Sales variances in the statement

Sales price variance and sales volume variance (at standard profit per unit in absorption costing, at standard contribution per unit in marginal costing) were described in an earlier topic; they join the cost variances in the statement.

Resource utilisation ratios

These ratios express the volume variance in terms of hours and are linked to the fixed overhead variances:

  • Efficiency ratio = standard hours for the actual output ÷ actual hours worked (100% if output takes exactly the expected time; above 100% if faster).
  • Capacity ratio = actual hours worked ÷ budgeted hours (or hours available for work). Idle hours are excluded from hours worked.
  • Production volume (activity) ratio = standard hours for the actual output ÷ budgeted hours.
  • Efficiency ratio × capacity ratio = production volume ratio.
Fixed overhead variancesA tree. The top box is the total fixed overhead variance. It splits into the expenditure variance and the volume variance. The volume variance splits into the efficiency variance and the capacity variance.Total (over/under absorption)ExpenditureVolumeEfficiencyCapacity

The operating statement

An operating statement reconciles the budgeted profit with the actual profit by listing all the variances. Senior management use it to see the effect of each variance on profitability and to assess how well junior managers controlled costs and achieved sales.

Standard absorption costing

  1. Start with budgeted profit (budgeted sales × standard profit per unit).
  2. Add or deduct the sales variances (price, then volume at standard profit). The sub-total is actual sales revenue minus the standard production cost of the units sold.
  3. List the cost variances, favourable and adverse in separate columns: material price and usage; labour rate, efficiency and idle time; variable overhead expenditure and efficiency; fixed overhead expenditure, efficiency and capacity (the volume variance in two parts).
  4. Total the cost variances and deduct (or add) to give actual profit.

Standard marginal costing

Units and stock are valued at standard variable production cost, so budgeted profit differs from that under absorption costing. All the variable cost variances and the sales price variance are the same. The differences:

  • the sales volume variance is valued at standard contribution per unit, not profit
  • there is no fixed overhead volume variance, because fixed overhead is not absorbed
  • only the expenditure variance is shown

The statement starts with budgeted contribution, adjusts for sales variances and variable cost variances to actual contribution, then deducts actual fixed overhead (budgeted fixed overhead plus the adverse expenditure variance) to give actual profit. With no change in stock the two methods give the same actual profit.

Layouts for overhead variances and the operating statement

  1. Variable overhead: actual hours worked × SR v actual cost (expenditure); (SH − AH worked) × SR (efficiency).
  2. Fixed overhead: budget v actual (expenditure); absorbed v budget (volume); AH v budgeted hours (capacity); SH v AH (efficiency).
  3. Ratios: SH ÷ AH; AH ÷ budgeted hours; SH ÷ budgeted hours.
  4. Statement: budget; sales variances; cost variances; actual; verify against the actual figures.

Money is in naira and each answer is rounded once, at the end.

Worked examples

Example: the full reconciliation. The standard for a unit: materials 3 kg at ₦200; labour 2 hours at ₦500; variable overhead 2 hours at ₦150; fixed overhead 2 hours at ₦400 (budgeted fixed overhead ₦4,000,000 for 5,000 units, or 10,000 hours). Standard full cost ₦2,700; selling price ₦3,500; standard profit ₦800; standard contribution ₦1,600. The budget was to make and sell 5,000 units. Actual: 4,600 units made and sold at ₦3,450; materials 14,000 kg at ₦205; labour 9,400 hours worked and paid at ₦510; variable overhead ₦1,457,000; fixed overhead ₦4,150,000. Required: the variances, the ratios and the operating statement.

  1. Sales.
    Price: 4,600 × 3,500 = 16,100,000 against 15,870,000, ₦230,000 A.
    Volume (absorption): (4,600 − 5,000) × 800 = ₦320,000 A.
  2. Materials.
    Price: 14,000 × 200 = 2,800,000 against 2,870,000, ₦70,000 A.
    Usage: standard 13,800 kg, used 14,000; 200 A × 200 = ₦40,000 A.
  3. Labour.
    Rate: 9,400 × 500 = 4,700,000 against 4,794,000, ₦94,000 A.
    Efficiency: standard hours 9,200; worked 9,400; 200 A × 500 = ₦100,000 A.
  4. Variable overhead.
    Expenditure: 9,400 × 150 = 1,410,000 against 1,457,000, ₦47,000 A.
    Efficiency: 200 A × 150 = ₦30,000 A.
  5. Fixed overhead.
    Absorbed 4,600 × 800 = 3,680,000; actual 4,150,000; total ₦470,000 A.
    Expenditure 4,000,000 − 4,150,000 = ₦150,000 A.
    Volume (4,600 − 5,000) × 800 = ₦320,000 A.
    Efficiency 200 A × 400 = ₦80,000 A.
    Capacity (9,400 − 10,000) = 600 A × 400 = ₦240,000 A.
    Check 80,000 + 240,000 = 320,000
    150,000 + 320,000 = 470,000.
  6. Ratios.
    Efficiency 9,200 ÷ 9,400 = 97.87%
    capacity 9,400 ÷ 10,000 = 94.0%
    production volume 9,200 ÷ 10,000 = 92.0%
    97.87% × 94% = 92.0%.
  7. Operating statement (absorption), ₦000.
    Budgeted profit 5,000 × 800 = 4,000.
    Sales price (230) A; sales volume (320) A; sub-total 3,450.
    Cost variances (A): material price 70, usage 40; labour rate 94, efficiency 100; variable overhead expenditure 47, efficiency 30; fixed overhead expenditure 150, efficiency 80, capacity 240; total 851 A.
    Actual profit 2,599.
  8. Verification.
    Revenue 15,870 − materials 2,870 − labour 4,794 − variable overhead 1,457 − fixed overhead 4,150 = 2,599.
  9. Marginal costing, ₦000.
    Budgeted contribution 5,000 × 1,600 = 8,000.
    Sales price (230); sales volume 400 × 1,600 = (640); sub-total 7,130.
    Variable cost variances (A): 70 + 40 + 94 + 100 + 47 + 30 = 381; actual contribution 6,749.
    Fixed overhead: budgeted 4,000 plus expenditure variance 150 = actual 4,150.
    Actual profit 2,599, the same.

Expect variants: a statement with opening and closing stock (production and sales differ), idle time shown, partial data from which to derive missing variances, and requirements to explain the variances and ratios to management.

Factors to consider before investigating a variance

Investigation costs management time, so not every variance should be investigated.

Consider: the size of the variance (materiality, often as a percentage of the standard); whether it is adverse or favourable (adverse ones usually get more attention because they cut profit, but a large favourable one may signal a loose standard or falling quality); the probability that the cause is controllable; the cost and benefit of investigating (do not investigate unless the expected benefit exceeds the cost); the reliability and accuracy of the figures; possible interdependencies between variances (a favourable price and an adverse usage variance may have one cause); and the inherent variability of the item, since some costs normally fluctuate.

A common rule is to investigate when a variance exceeds both a set percentage and a set amount, or forms part of a trend.

Common mistakes

  • Variable overhead expenditure on hours paid instead of hours worked.
  • Fixed overhead volume on units but valued at a rate per hour, or the reverse. Match the base.
  • Using profit for volume in marginal costing and contribution in absorption costing.
  • Showing a fixed overhead volume variance in a marginal statement.
  • Not verifying the actual profit from the actual figures.
  • Wrong signs in the statement. Adverse variances reduce profit.

Quick revision

  • VOH: expenditure on hours worked; efficiency = labour efficiency hours × VOH rate.
  • FOH: expenditure = budget − actual; volume = (actual − budgeted units) × rate per unit; volume = efficiency + capacity.
  • Ratios: efficiency × capacity = production volume.
  • Statement: budget → sales → cost → actual; marginal uses contribution and has no FOH volume variance.

How the marks are earned

  • Each variance with base and sign.
  • Statement that reconciles to actual profit.
  • Explanation of causes and links.

Practice questions

These are original questions, written in the style of the Skills examination. Work each one before you open the answer.

Recall check: multiple choice

Question 1. The variable overhead expenditure variance is based on:

  1. Hours paid
  2. Actual hours worked
  3. Budgeted hours
  4. Units
Show the answer

B. No variable overhead is incurred in idle time.

Question 2. The variable overhead efficiency variance in hours equals:

  1. The capacity variance
  2. The rate variance
  3. The labour efficiency variance in hours
  4. Zero
Show the answer

C. It is valued at the overhead rate.

Question 3. The total fixed overhead variance is:

  1. The over- or under-absorption
  2. The expenditure variance
  3. The capacity variance
  4. Zero
Show the answer

A. Absorbed less actual.

Question 4. The fixed overhead volume variance is:

  1. Budget − actual spending
  2. Hours × rate
  3. Revenue − cost
  4. (Actual − budgeted units) × standard fixed overhead per unit
Show the answer

D. It reflects production differing from budget.

Question 5. The volume variance splits into:

  1. Efficiency and capacity
  2. Price and usage
  3. Mix and yield
  4. Rate and idle time
Show the answer

A. Each at the fixed overhead rate per hour.

Question 6. The fixed overhead expenditure variance is:

  1. Absorbed − actual
  2. Hours × rate
  3. Budgeted − actual fixed overhead
  4. Zero
Show the answer

C. Adverse if more was spent.

Question 7. In standard marginal costing there is no:

  1. Sales price variance
  2. Fixed overhead volume variance
  3. Material price variance
  4. Labour rate variance
Show the answer

B. Fixed overhead is not absorbed.

Question 8. In an absorption costing operating statement the sales volume variance uses:

  1. Revenue
  2. Cost
  3. Contribution
  4. Standard profit per unit
Show the answer

D. Contribution is used in marginal costing.

Question 9. Efficiency ratio × capacity ratio equals:

  1. The production volume ratio
  2. One
  3. Zero
  4. The yield
Show the answer

A. The three ratios are linked.

Question 10. An operating statement starts with:

  1. Actual profit
  2. Actual revenue
  3. Budgeted profit (or contribution)
  4. Variances
Show the answer

C. Then variances reconcile to actual.

Section B style: written questions

Question 11 (10 marks). (a) Explain the fixed overhead expenditure, volume, efficiency and capacity variances. (8 marks) (b) State why a marginal costing statement has no fixed overhead volume variance. (2 marks)

Question 12 (15 marks). Budget: 6,000 units at 3 hours = 18,000 hours; fixed overhead ₦5,400,000. Actual: 5,800 units made; 17,700 hours worked; fixed overhead ₦5,520,000.

(a) Calculate the total fixed overhead variance. (3 marks) (b) Calculate the expenditure variance. (2 marks) (c) Calculate the volume variance. (3 marks) (d) Split the volume variance into efficiency and capacity. (4 marks) (e) Calculate the efficiency, capacity and production volume ratios. (3 marks)

Question 13 (20 marks). Budget: 2,000 units at a standard price of ₦1,000 and standard cost ₦700. Actual: 1,900 units sold at ₦990. Variances: material price 12,000 F, usage 8,000 A; labour rate 5,000 A, efficiency 15,000 F; variable overhead expenditure 4,000 A, efficiency 6,000 F; fixed overhead expenditure 10,000 A, efficiency 9,000 F, capacity 12,000 A.

(a) Prepare the operating statement under absorption costing. (12 marks) (b) State the actual profit. (2 marks) (c) Discuss the usefulness and limits of the statement. (6 marks)

Model answers

Show the model answer to Question 11

(a) Expenditure: budgeted less actual fixed overhead. Volume: (actual − budgeted units) × standard fixed overhead per unit, arising because output differs from the volume used to set the absorption rate. Efficiency: standard hours for actual output less actual hours worked, at the fixed rate per hour. Capacity: actual hours worked less budgeted hours, at the fixed rate per hour. Efficiency plus capacity equals volume (2 each).

(b) Fixed overhead is treated as a period cost and not absorbed into units, so nothing is over- or under-absorbed (2).

Show the model answer to Question 12

(a) Absorbed 5,800 × 900 = 5,220,000; actual 5,520,000; ₦300,000 A (3).

(b) 5,400,000 − 5,520,000 = ₦120,000 A (2).

(c)

  1. (5,800 − 6,000) = 200 A × 900 = ₦180,000 A.
  2. Check 120,000 + 180,000 = 300,000 (3).

(d)

  1. Rate ₦300 an hour.
  2. Efficiency.
    standard hours 17,400; worked 17,700; 300 A × 300 = ₦90,000 A.
  3. Capacity.
    (17,700 − 18,000) = 300 A × 300 = ₦90,000 A.
  4. Total 180,000 A (4).

(e)

  1. Efficiency 17,400 ÷ 17,700 = 98.3%
  2. capacity 17,700 ÷ 18,000 = 98.3%
  3. production volume 17,400 ÷ 18,000 = 96.7% (3).
Show the model answer to Question 13

(a)

  1. Budgeted profit 2,000 × 300 = 600,000.
  2. Sales price.
    1,900 × 1,000 = 1,900,000 against 1,881,000, (19,000) A.
  3. Sales volume.
    (1,900 − 2,000) × 300 = (30,000) A.
  4. Sub-total 551,000.
  5. Favourable cost variances: material price 12,000; labour efficiency 15,000; variable overhead efficiency 6,000; fixed overhead efficiency 9,000; total 42,000.
  6. Adverse: material usage 8,000; labour rate 5,000; variable overhead expenditure 4,000; fixed overhead expenditure 10,000; capacity 12,000; total 39,000.
  7. Net 3,000 F (12).

(b) Actual profit 551,000 + 3,000 = ₦554,000 (2).

(c) Usefulness: reconciles budget to actual; shows the effect of each variance and who is responsible; directs attention to large items. Limits: depends on reliable standards; variances may be interrelated; says nothing about causes or non-financial aspects; planning variances are not shown separately; a favourable variance is not always good (6).

Pathfinder on Overhead variances and profit reconciliation

These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.

November Diet, 2022: Question 3 (20 marks)

Standard cost card; April variances; reconcile budgeted and actual contribution; fixed overhead capacity/efficiency; factors in investigating variances.

Revise first: Layouts for overhead variances and the operating statement

November Diet, 2020: Question 3 (20 marks)

Variance reconciliation under marginal costing, fixed overhead variances, causes of labour variances.

Revise first: Layouts for overhead variances and the operating statement

Source: ICAN Pathfinder, Performance Management. Diets covered: March/July Diet, 2020 to May Diet, 2026. All 13 diets in the Pathfinder are mapped.

Spotted a mistake? Tell us and we will check it.

Where this fits

See every past question on Performance Management and the topic each one tests in the Pathfinder question finder.

This course builds on Management Accounting. After it, move on to Strategic Financial Management.

All Performance Management topics

You are reading topic 52 of 77.

  1. Information systems in organisations: role, costs and benefits01
  2. Internet, intranet, wireless technology and networks in business02
  3. Information needs at strategic, tactical and operational levels03
  4. TPS, MIS, EIS, ERP and CRM systems compared04
  5. Social and ethical issues in strategy and the management accountant’s data role05
  6. Big data principles and the big data pyramid06
  7. Big data, data mining and analytics: uses, benefits, challenges and risks07
  8. Activity based costing: cost pools, cost drivers and calculations08
  9. Activity based costing compared with traditional absorption costing09
  10. Target costing: principles and calculating the target cost10
  11. Managing the target cost gap and target costing in services11
  12. Life cycle costing: product life cycle stages and costs12
  13. Life cycle cost and profit calculations, and the benefits of life cycle costing13
  14. Throughput accounting: theory of constraints and the throughput accounting ratio14
  15. Environmental management accounting and sustainability in business15
  16. Environmental costs: methods, challenges and the management accountant’s role16
  17. Relevant costs and revenues, and opportunity cost17
  18. Relevant costs for specific decisions: materials, labour, equipment and overheads18
  19. Break-even analysis and margin of safety for Skills level decisions19
  20. Contribution to sales ratio, target profit and target revenue20
  21. Break-even charts and profit-volume charts21
  22. Multi-product CVP analysis and its limitations22
  23. Limiting factors: allocating a single scarce resource23
  24. Linear programming: formulation and graphical solution24
  25. Linear programming: slack and shadow prices25
  26. Price elasticity of demand and the factors that influence price26
  27. Demand and cost functions: profit-maximising price and output27
  28. Cost-based pricing: cost-plus and relevant-cost pricing28
  29. Market-based pricing: skimming, penetration and other strategies29
  30. Make-or-buy and outsourcing decisions30
  31. One-off contracts, shutdown and further processing of joint products31
  32. Reducing uncertainty: research, simulation and sensitivity analysis32
  33. Expected values and decision rules: maximax, maximin and minimax regret33
  34. Decision trees for multi-stage decisions34
  35. Value of perfect and imperfect information35
  36. Budgetary systems and types of budget: choosing the right one36
  37. Preparing fixed and flexed budgets37
  38. Rolling, activity-based, functional and master budgets38
  39. The beyond budgeting model: benefits and problems39
  40. Participation, negotiation and ethics in budgeting40
  41. High-low method and cost estimation for budgets41
  42. Correlation, regression and time series for budgeting and forecasting42
  43. Learning curve: learning rate and learning effect43
  44. Learning curve in budgeting: steady state and limitations44
  45. Standard costing: uses, how standards are set and types of standard45
  46. Basic variances: material, labour and idle time46
  47. Material mix and yield variances47
  48. Labour mix and yield variances48
  49. Sales mix and quantity variances49
  50. Planning and operational variances: revised budget, sales, market size and market share50
  51. Planning and operational variances for materials and labour51
  52. Overhead variances and reconciling budgeted and actual profit at Skills level52 here
  53. Behavioural effects of variances: motivation, JIT and TQM53
  54. Profitability ratios and financial performance measures54
  55. Liquidity, solvency and efficiency ratios55
  56. Non-financial performance indicators56
  57. Short-termism and financial manipulation of results57
  58. Sustainability and ESG performance measures58
  59. The balanced scorecard59
  60. The Fitzgerald and Moon building block model60
  61. Performance measurement in not-for-profit organisations61
  62. Value for money as a public sector objective62
  63. Divisional performance: return on investment and residual income63
  64. Economic value added (EVA)64
  65. Transfer pricing methods and the optimal transfer price65
  66. Transfer pricing: problems, tax and repatriation of funds66
  67. Value chain analysis for performance management67
  68. Complex business structures: alliances, joint ventures and supply chains68
  69. The performance pyramid69
  70. Value-based management70
  71. Corporate failure and life cycle issues71
  72. The Z-score and other quantitative failure models72
  73. The Argenti model and qualitative failure prediction73
  74. Preventing corporate failure and performance improvement strategies74
  75. Current developments in management accounting75
  76. Benchmarking and target setting in the public sector76
  77. The changing role of the management accountant and contemporary issues77
See the whole course

Get the complete Performance Management notes

Download as PDF or Word

  • Every topic as PDF and Word, ready to print