A new bakery in Abuja sells loaves at ₦600 each. The owner knows that rent, salaries and the oven lease are paid whether or not anyone buys bread. The question every owner asks is simple: how many loaves must we sell each month before we stop losing money? And a second question follows: if we plan to sell more than that, how far can sales fall before the plan fails?

Cost-volume-profit (CVP) analysis answers both. It is an application of marginal costing. It shows how cost and profit change when the volume of activity changes. This topic explains the assumptions of CVP analysis, the concepts of contribution and the contribution to sales ratio, how to calculate the break-even point in units and in revenue, and how to measure the margin of safety.

It builds on the relevant costs for specific decisions topic, which also uses contribution. The next topic covers the contribution to sales ratio, target profit and target revenue.

In 30 seconds

CVP analysis shows how costs and profits change with volume, and applies marginal costing. Contribution = sales − variable costs (include variable selling costs); profit = contribution − fixed costs. C/S ratio = contribution per unit ÷ selling price per unit. Break-even point (units) = fixed costs ÷ contribution per unit. Break-even point (revenue) = fixed costs ÷ C/S ratio, which is the same as units × price.

Margin of safety = budgeted sales − break-even sales, in units or revenue, and as a percentage of budgeted sales; it is how far sales can fall before a loss. The method assumes that costs are fixed or variable, variable cost and price per unit are constant, and fixed costs are constant. Full marks come from the right formula, a clear unit label, and an interpretation.

The nature of CVP analysis

CVP analysis shows how costs and profits change with the volume of activity. It applies marginal costing, and it rests on these assumptions:

  • Costs are either fixed or variable.
  • The variable cost per unit is the same at all levels of activity.
  • Total fixed costs are constant in each period, whatever the output.
  • The selling price per unit is constant, so the contribution per unit is constant, and so is the contribution to sales ratio.
  • If price, variable cost per unit and fixed costs do not depend on volume, profit is maximised by maximising total contribution.

Contribution

Contribution is sales revenue less variable costs. Profit is contribution less fixed costs. Variable costs include every cost that varies with units sold, including variable selling and distribution costs, so a product with a variable production cost of ₦22 and a variable selling cost of ₦3 has a variable cost of ₦25 a unit. Total contribution = contribution per unit (CPU) × units sold.

At low volumes the contribution does not cover fixed costs and there is a loss; as volume rises the contribution rises, the loss falls, and somewhere there is a volume at which profit is zero. That is the break-even point.

The contribution to sales ratio

The C/S ratio is contribution per unit ÷ selling price per unit, which is the same as total contribution ÷ total sales. It shows how much of each naira of sales is left after variable costs to cover fixed costs and profit. It is constant at all volumes under the assumptions above. Sales revenue can be found from contribution by dividing by the C/S ratio.

Break-even point and margin of safetyA profit and volume line rises from a loss equal to fixed costs at zero sales, crosses zero at the break-even point, and continues into profit. The distance from break-even to the budgeted sales level is the margin of safety.0lossprofitBreak-evenBudgeted salesMargin of safetysalesfixed costs

Break-even and margin of safety

Break-even point is the volume of sales in a period at which profit is zero. Management uses it to find the minimum sales needed to avoid a loss, and to judge the risk in the budget by comparing budgeted sales with it.

  • Method 1, units. Total contribution at break-even equals fixed costs, so break-even units = fixed costs ÷ contribution per unit. Multiply by the price for revenue.
  • Method 2, revenue. Break-even revenue = fixed costs ÷ C/S ratio. Divide by the price for units. The two methods give the same answer.

Break-even units that are not whole numbers are rounded up to the next whole unit, because part of a unit cannot be sold. The loss would continue until the next unit is sold.

Margin of safety

The margin of safety is the difference between budgeted sales and break-even sales, in units or in revenue. It is the greatest amount by which actual sales can fall below budget without a loss. It is often given as a percentage of budgeted sales: margin of safety ratio = margin of safety ÷ budgeted sales, which is the same percentage whether it is measured in units or revenue. A high margin of safety means a low risk of loss.

Using the model

  • Sales strategy: the effect on profit of a price change, which changes both the contribution per unit and the break-even point.
  • Cost control: the effect of changes in fixed or variable cost on the break-even point.
  • New products: the minimum sales needed to justify a launch. Production costs are often known with some accuracy, but sales volume is hard to predict, so the model can be flexed to show different volumes.

Where profit at two volumes is known, the contribution per unit is the change in profit divided by the change in units, because fixed costs do not change. Fixed costs then follow from contribution minus profit at either volume.

Layouts

  1. Contribution per unit = price − variable production cost − variable selling cost.
  2. C/S ratio = contribution per unit ÷ price.
  3. Break-even units = fixed costs ÷ contribution per unit. Break-even revenue = fixed costs ÷ C/S ratio = units × price.
  4. Margin of safety (units) = budgeted units − break-even units. (Revenue) = budgeted revenue − break-even revenue.
  5. Margin of safety ratio = margin of safety ÷ budgeted sales × 100.
  6. Budgeted profit = budgeted units × contribution per unit − fixed costs.

Percentages are to one decimal place, break-even units are rounded up to whole units, and each answer is rounded once at the end.

Worked examples

Example 1: break-even and margin of safety. A company sells a product at ₦45. The variable production cost is ₦22 and the variable selling cost ₦3. Fixed costs are ₦900,000 a year. Budgeted sales are 60,000 units. Required: the contribution per unit and C/S ratio, the break-even point, the margin of safety and the budgeted profit.

  1. Contribution per unit.
    45 − 22 − 3 = ₦20.
    C/S ratio 20 ÷ 45 = 44.4%.
  2. Break-even units.
    900,000 ÷ 20 = 45,000 units.
    Revenue 45,000 × 45 = ₦2,025,000.
    Check: 900,000 ÷ 0.4444 = 2,025,000.
  3. Margin of safety.
    60,000 − 45,000 = 15,000 units, or 15,000 ÷ 60,000 = 25.0% of budgeted sales.
    In revenue: 2,700,000 − 2,025,000 = ₦675,000.
  4. Budgeted profit.
    60,000 × 20 = 1,200,000
    less 900,000 = ₦300,000.
  5. Comment. Sales could fall by a quarter before a loss. That is a comfortable margin, but a competitor’s price cut could remove much of it.

Example 2: a price cut. Continue Example 1. Management considers cutting the price by 10%, with no change in costs. Required: the new break-even point and the margin of safety if sales stay at 60,000 units.

  1. New price.
    45 × 0.90 = ₦40.5.
    New contribution 40.5 − 25 = ₦15.5 a unit.
  2. Break-even.
    900,000 ÷ 15.5 = 58,064.5, rounded up to 58,065 units.
  3. Margin of safety.
    60,000 − 58,065 = 1,935 units, or 1,935 ÷ 60,000 = 3.2%.
  4. Comment. A 10% price cut reduces contribution per unit by a quarter and nearly removes the margin of safety, so volume would have to rise a great deal to justify it.

Example 3: finding the cost structure from two profits. A firm made a profit of ₦300,000 on 60,000 units and ₦500,000 on 70,000 units. Required: the contribution per unit and the fixed costs.

  1. Contribution per unit.
    (500,000 − 300,000) ÷ (70,000 − 60,000) = ₦20.
  2. Fixed costs.
    60,000 × 20 = 1,200,000
    less profit 300,000 = ₦900,000.

Expect variants: the C/S ratio given instead of the unit costs, a margin of safety stated and the break-even to be found, costs changing next year, or break-even in naira only.

Common mistakes

  • Leaving out variable selling costs from the contribution per unit.
  • Using the profit per unit instead of contribution to find break-even.
  • Mixing units and naira. Fixed costs divided by the C/S ratio gives revenue, not units.
  • Not rounding break-even units up.
  • Measuring the margin of safety against the wrong base. It is a percentage of budgeted sales.
  • Forgetting the assumptions when asked for limits.

Quick revision

  • Contribution = sales − variable costs. Profit = contribution − fixed costs. C/S = contribution ÷ sales.
  • Break-even units = fixed ÷ CPU. Break-even revenue = fixed ÷ C/S.
  • Margin of safety = budgeted − break-even; ratio = margin ÷ budgeted sales.
  • Two profit points: CPU = change in profit ÷ change in units.
  • Assumptions: fixed or variable, constant price and unit variable cost, constant fixed costs.

How the marks are earned

  • Calculate: contribution, C/S ratio, break-even, margin of safety, each with its unit.
  • Interpret: what the margin of safety means for risk.
  • Discuss: assumptions and their effect on reliability.

Practice questions

These are original questions, written in the style of the Skills examination. Work each one before you open the answer.

Recall check: multiple choice

Question 1. CVP analysis is an application of:

  1. Absorption costing
  2. Activity based costing
  3. Marginal costing
  4. Life cycle costing
Show the answer

C. It uses contribution and fixed costs.

Question 2. Contribution equals:

  1. Sales minus variable costs
  2. Sales minus fixed costs
  3. Profit plus variable costs
  4. Sales minus all costs
Show the answer

A. Include variable selling costs.

Question 3. Break-even units equal:

  1. Contribution ÷ fixed costs
  2. Fixed costs ÷ contribution per unit
  3. Fixed costs ÷ price
  4. Profit ÷ contribution
Show the answer

B. At break-even, contribution equals fixed costs.

Question 4. Break-even revenue equals:

  1. Fixed costs × C/S ratio
  2. Contribution ÷ fixed costs
  3. Variable costs ÷ price
  4. Fixed costs ÷ C/S ratio
Show the answer

D. It equals break-even units times price.

Question 5. The margin of safety is:

  1. Budgeted sales minus break-even sales
  2. Break-even sales minus budgeted sales
  3. Fixed costs minus profit
  4. Contribution minus sales
Show the answer

A. It shows how far sales can fall before a loss.

Question 6. The margin of safety ratio is:

  1. Break-even ÷ budgeted
  2. Fixed ÷ variable
  3. Margin of safety ÷ budgeted sales
  4. Profit ÷ fixed
Show the answer

C. The same in units or revenue.

Question 7. The target volume in units for a target profit is:

  1. Profit ÷ price
  2. Fixed costs ÷ profit
  3. Variable ÷ contribution
  4. (Fixed costs + target profit) ÷ contribution per unit
Show the answer

D. Contribution must cover fixed costs and the target.

Question 8. At the break-even point, profit is:

  1. Maximum
  2. Zero
  3. Negative
  4. Equal to fixed costs
Show the answer

B. Contribution equals fixed costs.

Question 9. An assumption of CVP analysis is that:

  1. Fixed costs rise with output
  2. Price falls with volume
  3. Selling price and variable cost per unit are constant
  4. Costs cannot be classified
Show the answer

C. So contribution per unit is constant.

Question 10. A high margin of safety indicates:

  1. A low risk of making a loss
  2. A high risk of loss
  3. Sales below break-even
  4. No fixed costs
Show the answer

A. Sales can fall a long way before a loss.

Section B style: written questions

Question 11 (10 marks). (a) State FOUR assumptions of CVP analysis. (4 marks) (b) Explain what the break-even point and the margin of safety show management. (6 marks)

Question 12 (15 marks). A company sells a product at ₦80 with a variable cost of ₦32. Fixed costs are ₦720,000 and budgeted sales are 22,000 units.

(a) Calculate the contribution per unit and the C/S ratio. (3 marks) (b) Calculate the break-even point in units and revenue. (4 marks) (c) Calculate the margin of safety in units, as a percentage, and in revenue. (4 marks) (d) Calculate the budgeted profit. (2 marks) (e) Comment on the risk. (2 marks)

Question 13 (20 marks). A company has monthly sales of ₦150,000 and a profit of ₦9,000. Its margin of safety is 20% of budgeted sales.

(a) Calculate the break-even sales. (2 marks) (b) Calculate total costs at budgeted sales and at break-even, and from these the variable cost percentage and the fixed costs. (6 marks) (c) Calculate the C/S ratio. (2 marks) (d) Calculate the sales needed for a profit of ₦15,000. (4 marks) (e) Discuss the limitations of CVP analysis. (6 marks)

Model answers

Show the model answer to Question 11

(a) Any four:

  • costs are fixed or variable
  • variable cost per unit is constant
  • total fixed cost is constant
  • selling price per unit is constant
  • contribution per unit and C/S ratio are constant
  • a constant sales mix for several products (1 each)

(b) The break-even point is the sales volume at which there is neither profit nor loss, so it is the minimum sales to avoid a loss (2). Comparing budgeted sales with it shows the risk in the budget (1).

The margin of safety is budgeted sales minus break-even sales, the amount by which sales can fall before a loss (2); expressed as a percentage of budgeted sales it allows comparison. A high figure means low risk (1).

Show the model answer to Question 12

(a)

  1. 80 − 32 = ₦48
  2. C/S 48 ÷ 80 = 60.0% (3).

(b)

  1. 720,000 ÷ 48 = 15,000 units
  2. revenue 15,000 × 80 = ₦1,200,000 (4).

(c)

  1. 22,000 − 15,000 = 7,000 units
  2. 7,000 ÷ 22,000 = 31.8%
  3. revenue 1,760,000 − 1,200,000 = ₦560,000 (4).

(d)

  1. 22,000 × 48 = 1,056,000
  2. less 720,000 = ₦336,000 (2).

(e) Sales can fall by nearly a third before a loss, so the risk is low, though a price cut or a fall in demand would reduce it (2).

Show the model answer to Question 13

(a) Break-even sales = 80% × 150,000 = ₦120,000 (2).

(b)

  1. Total costs at budget 150,000 − 9,000 = ₦141,000; at break-even ₦120,000 (2).
  2. Difference in cost 21,000 over difference in sales 30,000 = 70% variable cost (2).
  3. Variable cost at budget 0.70 × 150,000 = 105,000
  4. fixed costs 141,000 − 105,000 = ₦36,000 (2).

(c) C/S ratio = 100% − 70% = 30% (2).

(d) (36,000 + 15,000) ÷ 0.30 = ₦170,000 (4).

(e) Costs are hard to split into fixed and variable; variable cost per unit may change with volume (overtime, discounts); fixed costs are fixed only within a range and may step up; the price may change with volume; products are not sold in constant ratios; the analysis ignores the uncertainty in estimates; the answers may be outside the range of the data (any six, 1 each).

Pathfinder on Break-even analysis and margin of safety

These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.

November Diet, 2025: Question 1 (30 marks)

Marginal mix for one plant, throughput accounting profitability, new plant marginal statement, break-even units and value, combined statement, RI viability.

Revise first: Layouts

November Diet, 2025: Question 5 (15 marks)

Selling price, sales, break-even and margin of safety from contribution data; choose price-cut strategy; challenges in developing an MIS.

Revise first: Layouts

May Diet, 2022: Question 1 (30 marks)

Product contribution/profit, drop a product, extra sales to cover advertising; relevant cost quote for a one-off job; incremental, differential, committed, sunk, opportunity cost.

Revise first: Layouts

Source: ICAN Pathfinder, Performance Management. Diets covered: March/July Diet, 2020 to May Diet, 2026. All 13 diets in the Pathfinder are mapped.

Spotted a mistake? Tell us and we will check it.

Where this fits

See every past question on Performance Management and the topic each one tests in the Pathfinder question finder.

This course builds on Management Accounting. After it, move on to Strategic Financial Management.

All Performance Management topics

You are reading topic 19 of 77.

  1. Information systems in organisations: role, costs and benefits01
  2. Internet, intranet, wireless technology and networks in business02
  3. Information needs at strategic, tactical and operational levels03
  4. TPS, MIS, EIS, ERP and CRM systems compared04
  5. Social and ethical issues in strategy and the management accountant’s data role05
  6. Big data principles and the big data pyramid06
  7. Big data, data mining and analytics: uses, benefits, challenges and risks07
  8. Activity based costing: cost pools, cost drivers and calculations08
  9. Activity based costing compared with traditional absorption costing09
  10. Target costing: principles and calculating the target cost10
  11. Managing the target cost gap and target costing in services11
  12. Life cycle costing: product life cycle stages and costs12
  13. Life cycle cost and profit calculations, and the benefits of life cycle costing13
  14. Throughput accounting: theory of constraints and the throughput accounting ratio14
  15. Environmental management accounting and sustainability in business15
  16. Environmental costs: methods, challenges and the management accountant’s role16
  17. Relevant costs and revenues, and opportunity cost17
  18. Relevant costs for specific decisions: materials, labour, equipment and overheads18
  19. Break-even analysis and margin of safety for Skills level decisions19 here
  20. Contribution to sales ratio, target profit and target revenue20
  21. Break-even charts and profit-volume charts21
  22. Multi-product CVP analysis and its limitations22
  23. Limiting factors: allocating a single scarce resource23
  24. Linear programming: formulation and graphical solution24
  25. Linear programming: slack and shadow prices25
  26. Price elasticity of demand and the factors that influence price26
  27. Demand and cost functions: profit-maximising price and output27
  28. Cost-based pricing: cost-plus and relevant-cost pricing28
  29. Market-based pricing: skimming, penetration and other strategies29
  30. Make-or-buy and outsourcing decisions30
  31. One-off contracts, shutdown and further processing of joint products31
  32. Reducing uncertainty: research, simulation and sensitivity analysis32
  33. Expected values and decision rules: maximax, maximin and minimax regret33
  34. Decision trees for multi-stage decisions34
  35. Value of perfect and imperfect information35
  36. Budgetary systems and types of budget: choosing the right one36
  37. Preparing fixed and flexed budgets37
  38. Rolling, activity-based, functional and master budgets38
  39. The beyond budgeting model: benefits and problems39
  40. Participation, negotiation and ethics in budgeting40
  41. High-low method and cost estimation for budgets41
  42. Correlation, regression and time series for budgeting and forecasting42
  43. Learning curve: learning rate and learning effect43
  44. Learning curve in budgeting: steady state and limitations44
  45. Standard costing: uses, how standards are set and types of standard45
  46. Basic variances: material, labour and idle time46
  47. Material mix and yield variances47
  48. Labour mix and yield variances48
  49. Sales mix and quantity variances49
  50. Planning and operational variances: revised budget, sales, market size and market share50
  51. Planning and operational variances for materials and labour51
  52. Overhead variances and reconciling budgeted and actual profit at Skills level52
  53. Behavioural effects of variances: motivation, JIT and TQM53
  54. Profitability ratios and financial performance measures54
  55. Liquidity, solvency and efficiency ratios55
  56. Non-financial performance indicators56
  57. Short-termism and financial manipulation of results57
  58. Sustainability and ESG performance measures58
  59. The balanced scorecard59
  60. The Fitzgerald and Moon building block model60
  61. Performance measurement in not-for-profit organisations61
  62. Value for money as a public sector objective62
  63. Divisional performance: return on investment and residual income63
  64. Economic value added (EVA)64
  65. Transfer pricing methods and the optimal transfer price65
  66. Transfer pricing: problems, tax and repatriation of funds66
  67. Value chain analysis for performance management67
  68. Complex business structures: alliances, joint ventures and supply chains68
  69. The performance pyramid69
  70. Value-based management70
  71. Corporate failure and life cycle issues71
  72. The Z-score and other quantitative failure models72
  73. The Argenti model and qualitative failure prediction73
  74. Preventing corporate failure and performance improvement strategies74
  75. Current developments in management accounting75
  76. Benchmarking and target setting in the public sector76
  77. The changing role of the management accountant and contemporary issues77
See the whole course

Get the complete Performance Management notes

Download as PDF or Word

  • Every topic as PDF and Word, ready to print
  • Edit it in Word or print the PDF. No retyping.
Get this course

Reading stays free. Access lasts 12 months. Pay by card, bank transfer, USSD or QR through Paystack. Your name and email appear on every page of your files. Read our Refund Policy.

PracticeNext topic