Sign inSign upSign in
Menu

Behavioural Effects of Variances: Staff Motivation, JIT and TQM

ICAN Skills, Performance Management. Syllabus area D: Budgeting and control.

14 min read · Updated 8 November 2026

Download this topic

In this part

A purchasing officer in a Lagos food factory is judged on the material price variance. In March a supplier offers a 4% discount for an order that will last three months, and the officer accepts. The month-end report shows a handsome favourable price variance and the officer is praised.

Three months later the factory has a store full of flour that is going stale, a bank overdraft that has grown, and a warehouse lease it had to extend. The variance was favourable; the company was worse off. Variances measure the difference between actual and standard, but people respond to how they are measured, and they will often improve the measure rather than the business.

This topic explains the effects of variances on staff motivation and behaviour; why some variances are dysfunctional in a just-in-time (JIT) or total quality management (TQM) environment; the behavioural problems of using standard costs in a rapidly changing environment; and how to reduce them. It builds on the earlier topic on overhead variances and reconciling budgeted and actual profit. The next topic covers profitability ratios and financial performance measures.

In 30 seconds

Staff will accept variances as a measure of performance if they are not held responsible for poor planning or faulty standards. When variances are used to blame, the effects can be demotivation and frustration, low morale and burnout from unattainable goals, defensiveness and resistance to change, lower quality and absenteeism.

When variances are well managed and fairly used, they raise motivation and commitment, encourage collaboration, give a sense of ownership, point to areas for improvement, and improve cost control. In a JIT environment (minimum stock, producing to demand), some standard-costing variances become dysfunctional: a favourable material price variance encourages bulk buying and stock; a labour efficiency or fixed overhead volume variance encourages producing for stock to keep workers busy.

In a TQM environment (continuous improvement, customer satisfaction, zero defects), standards that allow for waste accept it, cutting cost by cheaper materials can reduce quality, and a focus on short-term variances ignores long-term improvement. In a rapidly changing environment, standards go out of date, so variances mislead, staff chase unattainable standards, data may be manipulated and innovation suffers.

Remedies: revise standards regularly, use flexed and ex post standards, report operational variances, add non-financial measures, reward the total result not individual variances, and involve staff. Full marks come from linking each variance to the behaviour it provokes.

Variances and staff motivation

Why variances affect behaviour

Variances and budgetary control are accepted as a tool of performance measurement if staff believe they will not be blamed for deviations that come from poor planning or faulty standard setting. But managements often treat a variance as evidence of inefficiency, so that staff feel held responsible. How variances are used therefore shapes motivation and action, for better or for worse.

Negative effects of unmanaged or unfair variances

  • Demotivation and frustration: a sense of being blamed unfairly, lower morale, reduced effort.
  • Burnout: staff driven to meet unattainable standards; absenteeism and resentment may rise.
  • Defensiveness and resistance to change: staff protect themselves, hide problems and resist innovations that change the standards.
  • Lower quality and productivity: pressure to hit targets at any cost; shortcuts.
  • Manipulation: reports adjusted, costs moved between periods, honest forecasts withheld.

Positive effects of well-managed variances

  • Motivation and commitment when performance is shown to be good and the system seen as fair.
  • Continued improvement in productivity and a culture of continuous improvement.
  • Collaboration and open communication, since staff discuss variances to find causes.
  • Ownership and accountability: staff act to remove deviations.
  • Targeted improvement: areas needing attention are isolated and corrected.
  • Fairness and transparency, and lower costs and better operations.

The difference between the two lists is mainly whether standards are realistic, whether variances are reported only to those who can control them, and whether they are used to learn or to punish.

JIT, TQM and rapidly changing environments

Variances in a JIT environment

JIT aims to hold minimum stock of materials and finished goods, produce only to meet demand, and eliminate waste, so reducing storage cost and improving cash flow. Traditional variance analysis concentrates on individual cost items and on short-term cost reduction. Used in a JIT plant, it can reward behaviour that works against JIT:

  • Material price variance: favourable variances reward buying in bulk, at the cheapest supplier, in large quantities, building stock; JIT needs small, frequent deliveries from reliable suppliers, perhaps at a higher price.
  • Labour efficiency and idle time variances: a manager avoids an adverse idle time variance by keeping workers busy, producing for stock that no customer has ordered.
  • Fixed overhead volume and capacity variances: a favourable volume variance comes from producing more than was budgeted, so a manager has an incentive to overproduce, again building stock.
  • Material usage: pressure to avoid adverse usage may delay the stopping of a line to correct faults.

For variance analysis to be useful in JIT, the emphasis should move to total cost, to throughput and delivery performance, and to continuous improvement, with non-financial measures such as lead time, set-up time and stock levels.

Variances in a TQM environment

TQM aims to reduce cost through continuous improvement and customer satisfaction, aiming at zero defects. Variances can conflict with it:

  • Standards that allow for waste (a normal loss or an attainable standard) accept a level of defects, while TQM seeks to remove them.
  • An adverse material price variance may push managers to buy cheaper, lower-quality material, which raises scrap, rework and returns, and harms customers.
  • Variances measure cost, not quality, delivery or customer satisfaction, so a manager may meet the cost standard while quality falls.
  • Short-term control of variances can discourage investment in training and process improvement whose benefits come later.
  • Employees are less willing to report problems if they are blamed for the variances those problems cause. TQM needs a culture in which problems are brought to light and used to improve, which is what the right use of variances should support.

Behavioural problems of standard costs in a rapidly changing environment

Standards are often based on history, assumptions or averages, which may not reflect current markets, customer preferences or production efficiency.

In a fast-changing environment this causes:

  • an over-focus on unfavourable variances arising from unattainable targets
  • manipulation of data under pressure
  • neglect of true performance improvement and innovation
  • resistance to change when standards are not flexed to match changing conditions
  • low morale and disengagement
  • poor pricing, production and strategic decisions based on inaccurate costs
  • misallocation of resources, with attention on variances rather than the real drivers of performance

Reducing the problems

  • Keep standards current and review often; use ex post standards and report operational variances, so that planning errors are not blamed on managers.
  • Use attainable, challenging standards, set with staff participation, with the idea of continuous improvement built in.
  • Add non-financial measures (quality, delivery, lead time, satisfaction) and judge performance on a balance of measures.
  • Look at variances together and at the total result, not one item in isolation, and report to the manager who can control the item.
  • Use variances to investigate and learn, not to blame; encourage staff to report problems.
  • Reward overall performance (profit, throughput) and not individual variances.
Variance, incentive and unintended behaviourThree boxes joined by arrows from left to right: a variance being measured, the incentive it creates, and the behaviour it may cause. Beneath, three rows give examples: price variance leads to bulk buying; efficiency variance leads to overproduction; cost variance leads to cheaper materials and lower quality.Variance measuredIncentive createdBehaviourFavourable price varianceBuy the cheapest, in bulkStock builds upNo adverse idle timeKeep everyone busyOverproductionLow material costSwitch to cheaper inputQuality falls

Layouts for testing the effect of a variance on behaviour

  1. Compute the variance the manager sees (for example a favourable price variance on the order placed).
  2. Compute the hidden cost of the behaviour it provokes (holding cost, cost of unsold stock, rework).
  3. Compare: net effect on the company = variance − hidden cost.
  4. Name the behaviour and the remedy.

Money is in naira and each answer is rounded once, at the end.

Worked examples

Example 1: the price variance and stock. A material has a standard price of ₦100 a kg and use is 10,000 kg a month. A supplier offers ₦98 a kg for an order of 20,000 kg (two months’ use). Holding cost is ₦12 per kg per month. Under the alternative, 10,000 kg would be bought each month at ₦100. Required: the variance, the hidden cost and the net effect.

  1. Variance seen.
    20,000 × (100 − 98) = ₦40,000 F.
  2. Extra stock held. Buying monthly the average stock is about 5,000 kg; buying two months at a time it is about 10,000 kg, so 5,000 kg extra.
    Over the two months: 5,000 × 12 × 2 = ₦120,000 extra holding cost.
  3. Net effect.
    40,000 − 120,000 = ₦80,000 worse off, although the report shows a favourable variance.
  4. Behaviour and remedy. The purchasing officer is rewarded for the price alone. Judge purchasing on total cost, including holding cost and quality, and agree small, frequent deliveries from reliable suppliers.

Example 2: efficiency variance and overproduction. A cell has 400 idle hours a month at ₦500 an hour because orders are low, which would show an adverse idle time variance of ₦200,000. The supervisor keeps the staff busy by making 200 extra units for which no orders exist. Each unit uses ₦1,500 of materials. Required: the effect.

  1. Variance avoided.
    Idle time of 400 hours × 500 = ₦200,000 no longer appears.
  2. Cost incurred.
    Materials 200 × 1,500 = ₦300,000 tied up in stock that may not be sold, with storage and risk of damage.
  3. Net effect. The wages were paid anyway; the company spends ₦300,000 to hide a ₦200,000 variance and is ₦300,000 worse off in cash until the stock is sold. Under JIT the right response is to report the idle capacity, look for orders or reduce capacity.

Expect variants: a case describing a plant that has just moved to JIT or TQM and asking which variances are now misleading, a requirement to discuss the motivation effects of a budget system, and suggestions for the right measures.

Conditions for successful just-in-time, and level production against JIT

Suppliers: materials of near-perfect quality, delivered on time, in small frequent deliveries, from a few suppliers with long-term close relationships. Production: a smooth flow of production, a pull system (work in one process starts only when the next process needs it, so output follows customer demand), quick and cheap set-ups because runs are short, and preventive maintenance to avoid breakdowns.

Employees: multi-skilled, flexible and empowered, working in teams and responsible for quality. Stocks are kept near zero, so there is no buffer against defects or late delivery.

Level production against JIT. Example. Quarterly demand 300,000, 360,000, 540,000 and 420,000 units (total 1,620,000); regular capacity 450,000 a quarter; holding cost ₦20 per unit a quarter on average stock. Level production makes 405,000 each quarter: closing stock 105,000, 150,000, 15,000 and 0. Average stock 52,500, 127,500, 82,500 and 7,500 gives holding costs of ₦1.05m, ₦2.55m, ₦1.65m and ₦0.15m: ₦5.4m for the year. Under JIT, production equals demand, so holding cost is nil, but quarter 3 needs 540,000 units, which is 90,000 above regular capacity.

If overtime costs an extra ₦75 of labour (50% premium) and ₦10 of variable overhead (25% more) per unit, the extra cost is 90,000 × 85 = ₦7.65m. JIT saves ₦5.4m but costs ₦7.65m: a net cost of ₦2.25m, so with fluctuating demand and limited capacity JIT is not financially beneficial unless other savings (less waste, less space, quality) outweigh it.

Machine utilisation, throughput accounting and inventory

Machine utilisation rate = hours required to meet maximum demand ÷ hours available. Machine 1: 560 required, 500 available, 112%; machine 2: 360 required, 450 available, 80%. The machine above 100% is the bottleneck. Under throughput accounting only materials are variable, so labour paid a guaranteed wage is a fixed cost, and for perishable products where stock should be kept to a minimum the approach suits well.

Example. Price ₦600, ₦900, ₦700 and materials ₦200, ₦300, ₦250 for P, Q and R give throughput ₦400, ₦600, ₦450; machine 1 hours 2, 4 and 2.5 give throughput per hour ₦200, ₦150 and ₦180. Demand P 100, Q 50, R 60; machine 1 has 500 hours. Make P (200 hours), R (150 hours), then Q with the 150 hours left (37.5 units): throughput 40,000 + 27,000 + 22,500 = ₦89,500.

Inventory. Throughput accounting does not treat stock as an asset; it is a sign of unsynchronised production and a barrier to profit. The ideal stock is zero except a buffer before the bottleneck. Stock is valued at material cost only, because no value is added and no profit earned until the item is sold.

This contrasts with absorption costing, which values stock at full cost, so that overproduction spreads overhead and raises reported profit, and which therefore encourages managers to build stock. If demand also exceeds regular plus overtime capacity under a JIT plan, the contribution on the shortfall is lost too.

Cost per factory hour, a minimum contract, and raising bottleneck capacity without new machines

Cost per factory hour = total factory cost ÷ bottleneck hours available (after allowing for utilisation). Example. Factory cost ₦10.8m; the bottleneck runs 12 hours × 5 days × 50 weeks × 90% = 2,700 hours; cost per hour ₦4,000. Red panels throughput ₦7,000 a unit in 1.4 hours = ₦5,000 an hour; TAR = 5,000 ÷ 4,000 = 1.25. Black panels ₦2,160 in 0.6 hours = ₦3,600 an hour; TAR = 0.90, so each hour on black panels earns less than it costs.

A guaranteed minimum supply (say 1,000 black panels) is made first, then the best-ranked product (red) with the hours left.

Ways to raise bottleneck output without new machines:

  • do maintenance outside production hours (contractors work around the clock)
  • cross-train staff so that absence does not idle a machine
  • stagger lunch breaks so that the bottleneck keeps running
  • lengthen the working day or add a working day
  • make sure the bottleneck never waits for work (a buffer of stock before it)

Common mistakes

  • Listing behavioural problems without naming the variance that causes them.
  • Saying variances are always bad for motivation. Fairly used, they help.
  • Ignoring the quality side of TQM and writing only about cost.
  • No remedy. Always state how to reduce the problem.
  • Confusing JIT with TQM. JIT concerns inventory and flow; TQM concerns quality and customers.
  • Treating a favourable variance as always good.

Quick revision

  • Staff accept variances if not blamed for bad plans. Unfair variances demotivate; fair ones motivate.
  • JIT: price variance → stock; efficiency/volume variance → overproduction.
  • TQM: allowances for waste, cheaper inputs, cost not quality.
  • Fast change: out-of-date standards. Remedies: review, ex post, non-financial measures, total result.

How the marks are earned

  • Link each variance to its behaviour.
  • Quantify the hidden cost where numbers are given.
  • Recommend remedies.

Practice questions

These are original questions, written in the style of the Skills examination. Work each one before you open the answer.

Recall check: multiple choice

Question 1. Staff are most likely to accept variances as a performance measure if:

  1. They are not held responsible for poor planning or faulty standards
  2. They are always adverse
  3. They are secret
  4. They are large
Show the answer

A. Fairness is the key.

Question 2. Unattainable standards tend to:

  1. Motivate everyone
  2. Have no effect
  3. Demotivate and cause resentment
  4. Cut all costs
Show the answer

C. Reported variances are always adverse.

Question 3. JIT aims to:

  1. Hold large stocks
  2. Hold minimal stock and produce only to demand
  3. Maximise output
  4. Avoid suppliers
Show the answer

B. It reduces waste and storage cost.

Question 4. A favourable price variance from bulk buying conflicts with JIT because it:

  1. Raises quality
  2. Cuts cost
  3. Speeds delivery
  4. Encourages stock-holding
Show the answer

D. JIT needs small frequent deliveries.

Question 5. A fear of adverse efficiency or idle time variances may encourage:

  1. Overproduction to keep workers busy
  2. Underproduction
  3. Higher quality
  4. Shorter hours
Show the answer

A. This builds unwanted stock.

Question 6. TQM emphasises:

  1. Short-term cost cutting
  2. Stock building
  3. Continuous improvement and customer satisfaction
  4. Imposed budgets
Show the answer

C. And aims at zero defects.

Question 7. Standards that allow for normal waste may conflict with TQM because they:

  1. Are too tight
  2. Accept waste instead of aiming to eliminate it
  3. Are too complex
  4. Raise quality
Show the answer

B. TQM seeks zero defects.

Question 8. In a rapidly changing environment standards:

  1. Stay accurate
  2. Never matter
  3. Are unnecessary
  4. Become out of date, so variances mislead
Show the answer

D. They must be reviewed and flexed.

Question 9. A remedy for the behavioural problems is to:

  1. Review standards often and add non-financial measures
  2. Blame staff more
  3. Ignore variances
  4. Raise targets
Show the answer

A. And use variances to learn.

Question 10. Variances show:

  1. Causes
  2. Solutions
  3. Deviations, but not their causes
  4. Nothing
Show the answer

C. Management must investigate.

Section B style: written questions

Question 11 (10 marks). (a) Explain FOUR negative effects of unfair variances on staff. (4 marks) (b) Explain FOUR positive effects of well-managed variances. (4 marks) (c) State when staff accept variances. (2 marks)

Question 12 (15 marks). The standard price of a material is ₦50 a kg and use is 15,000 kg a month. A supplier offers ₦47 a kg for 30,000 kg (two months’ use). Holding cost is ₦10 per kg per month. Buying monthly would give average stock of 7,500 kg; buying two months at a time gives 15,000 kg.

(a) Calculate the favourable price variance. (3 marks) (b) Calculate the extra holding cost over two months. (4 marks) (c) State the net effect. (2 marks) (d) Explain the behavioural problem. (3 marks) (e) Suggest a remedy. (3 marks)

Question 13 (20 marks). A company is introducing JIT and TQM.

(a) Discuss the effects of variances on staff motivation. (8 marks) (b) Explain how some variances are dysfunctional under JIT and TQM. (8 marks) (c) Discuss the behavioural problems of standard costs in a rapidly changing environment and how to reduce them. (4 marks)

Model answers

Show the model answer to Question 11

(a) Any four: demotivation and frustration; lower morale and burnout; defensiveness and resistance to change; reduced quality or productivity; absenteeism and resentment; manipulation of figures (1 each).

(b) Any four: increased motivation and commitment; continued improvement; collaboration and communication; ownership and accountability; areas for improvement isolated; fairness and transparency (1 each).

(c) When they are not held responsible for poor planning or faulty standards (2).

Show the model answer to Question 12

(a) 30,000 × (50 − 47) = ₦90,000 F (3).

(b)

  1. Extra average stock 15,000 − 7,500 = 7,500 kg
  2. × ₦10 × 2 months = ₦150,000 (4).

(c) 90,000 − 150,000 = ₦60,000 worse off, despite the favourable variance (2).

(d) The buyer is judged on the price variance alone and so is rewarded for buying in bulk, which builds stock, ties up cash and risks damage and obsolescence, contrary to JIT (3).

(e) Judge purchasing on total cost, including holding cost and quality; agree frequent small deliveries; add delivery and quality measures (3).

Show the model answer to Question 13

(a) Unfair or unattainable variances demotivate, cause frustration, burnout, defensiveness and manipulation; fair, well-managed variances raise motivation and commitment, encourage collaboration and ownership, and identify areas for improvement. The deciding factor is whether staff are blamed for planning errors (8).

(b) JIT: favourable price variances reward bulk buying and stock; efficiency, idle time and volume variances reward overproduction. TQM: allowances for waste accept defects; cost focus encourages cheaper, lower-quality inputs; short-term cost control discourages training and improvement; fear of blame hides problems (8).

(c) Standards become out of date, giving misleading variances, unattainable targets, manipulation and resistance. Reduce by frequent review, flexed and ex post standards, operational variances, non-financial measures and rewarding overall results (4).

Pathfinder on Behavioural effects of variances

These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.

May Diet, 2025: Question 6 (15 marks)

Flexible budgets using high-low and step cost; variance report and follow-up.

Revise first: Layouts for testing the effect of a variance on behaviour

November Diet, 2023: Question 2 (20 marks)

JIT conditions, constant production and holding cost, JIT overtime effect (JIT outside the map).

Revise first: Layouts for testing the effect of a variance on behaviour

May Diet, 2022: Question 6 (15 marks)

Flexible budgets from high-low cost split with step cost; budget report and variance follow-up.

Revise first: Layouts for testing the effect of a variance on behaviour

November Diet, 2020: Question 3 (20 marks)

Variance reconciliation under marginal costing, fixed overhead variances, causes of labour variances.

Revise first: Layouts for testing the effect of a variance on behaviour

Source: ICAN Pathfinder, Performance Management. Diets covered: March/July Diet, 2020 to May Diet, 2026. All 13 diets in the Pathfinder are mapped.

Spotted a mistake? Tell us and we will check it.

Where this fits

See every past question on Performance Management and the topic each one tests in the Pathfinder question finder.

This course builds on Management Accounting. After it, move on to Strategic Financial Management.

All Performance Management topics

You are reading topic 53 of 77.

  1. Information systems in organisations: role, costs and benefits01
  2. Internet, intranet, wireless technology and networks in business02
  3. Information needs at strategic, tactical and operational levels03
  4. TPS, MIS, EIS, ERP and CRM systems compared04
  5. Social and ethical issues in strategy and the management accountant’s data role05
  6. Big data principles and the big data pyramid06
  7. Big data, data mining and analytics: uses, benefits, challenges and risks07
  8. Activity based costing: cost pools, cost drivers and calculations08
  9. Activity based costing compared with traditional absorption costing09
  10. Target costing: principles and calculating the target cost10
  11. Managing the target cost gap and target costing in services11
  12. Life cycle costing: product life cycle stages and costs12
  13. Life cycle cost and profit calculations, and the benefits of life cycle costing13
  14. Throughput accounting: theory of constraints and the throughput accounting ratio14
  15. Environmental management accounting and sustainability in business15
  16. Environmental costs: methods, challenges and the management accountant’s role16
  17. Relevant costs and revenues, and opportunity cost17
  18. Relevant costs for specific decisions: materials, labour, equipment and overheads18
  19. Break-even analysis and margin of safety for Skills level decisions19
  20. Contribution to sales ratio, target profit and target revenue20
  21. Break-even charts and profit-volume charts21
  22. Multi-product CVP analysis and its limitations22
  23. Limiting factors: allocating a single scarce resource23
  24. Linear programming: formulation and graphical solution24
  25. Linear programming: slack and shadow prices25
  26. Price elasticity of demand and the factors that influence price26
  27. Demand and cost functions: profit-maximising price and output27
  28. Cost-based pricing: cost-plus and relevant-cost pricing28
  29. Market-based pricing: skimming, penetration and other strategies29
  30. Make-or-buy and outsourcing decisions30
  31. One-off contracts, shutdown and further processing of joint products31
  32. Reducing uncertainty: research, simulation and sensitivity analysis32
  33. Expected values and decision rules: maximax, maximin and minimax regret33
  34. Decision trees for multi-stage decisions34
  35. Value of perfect and imperfect information35
  36. Budgetary systems and types of budget: choosing the right one36
  37. Preparing fixed and flexed budgets37
  38. Rolling, activity-based, functional and master budgets38
  39. The beyond budgeting model: benefits and problems39
  40. Participation, negotiation and ethics in budgeting40
  41. High-low method and cost estimation for budgets41
  42. Correlation, regression and time series for budgeting and forecasting42
  43. Learning curve: learning rate and learning effect43
  44. Learning curve in budgeting: steady state and limitations44
  45. Standard costing: uses, how standards are set and types of standard45
  46. Basic variances: material, labour and idle time46
  47. Material mix and yield variances47
  48. Labour mix and yield variances48
  49. Sales mix and quantity variances49
  50. Planning and operational variances: revised budget, sales, market size and market share50
  51. Planning and operational variances for materials and labour51
  52. Overhead variances and reconciling budgeted and actual profit at Skills level52
  53. Behavioural effects of variances: motivation, JIT and TQM53 here
  54. Profitability ratios and financial performance measures54
  55. Liquidity, solvency and efficiency ratios55
  56. Non-financial performance indicators56
  57. Short-termism and financial manipulation of results57
  58. Sustainability and ESG performance measures58
  59. The balanced scorecard59
  60. The Fitzgerald and Moon building block model60
  61. Performance measurement in not-for-profit organisations61
  62. Value for money as a public sector objective62
  63. Divisional performance: return on investment and residual income63
  64. Economic value added (EVA)64
  65. Transfer pricing methods and the optimal transfer price65
  66. Transfer pricing: problems, tax and repatriation of funds66
  67. Value chain analysis for performance management67
  68. Complex business structures: alliances, joint ventures and supply chains68
  69. The performance pyramid69
  70. Value-based management70
  71. Corporate failure and life cycle issues71
  72. The Z-score and other quantitative failure models72
  73. The Argenti model and qualitative failure prediction73
  74. Preventing corporate failure and performance improvement strategies74
  75. Current developments in management accounting75
  76. Benchmarking and target setting in the public sector76
  77. The changing role of the management accountant and contemporary issues77
See the whole course

Get the complete Performance Management notes

Download as PDF or Word

  • Every topic as PDF and Word, ready to print
  • Edit it in Word or print the PDF. No retyping.
Get this course

Reading stays free. Access lasts 12 months. Pay by card, bank transfer, USSD or QR through Paystack. Your name and email appear on every page of your files. Read our Refund Policy.

PracticeNext topic