A paint factory in Ibadan budgets to make 2,000 tins of a product in March. It makes 2,000, but the cost report shows that materials cost ₦316,000 more than the budget and labour ₦366,000 more. The directors ask the obvious question: was it the price we paid, or the quantity we used?
Was it the wage rate, or the speed of the workers, or the hours they stood idle because the mixing machine broke down? A total difference does not tell them where to look. Variance analysis splits it into parts that point to a cause and a person.
This topic starts the study of variances with the flexed budget on which they all rest, then explains the direct material variances (total, price and usage), the direct labour variances (total, rate, efficiency and idle time), the line-by-line layout for them, how idle time is treated when it is built into the standard, the possible causes, and the interrelationships that mean two variances may come from one decision.
It builds on the earlier topic on standard costing: its uses, how standards are set and the types of standard. The next topic covers material mix and yield variances.
In 30 seconds
A variance is the difference between actual and standard (or budget); it is favourable (F) if profit rises, adverse (A) if it falls. Variances are not found by comparing actual with the fixed budget, because activity differs. A flexed budget restates standard revenue and costs at the actual level of activity, and the comparison with it is like for like.
Materials: total = standard cost of actual output − actual cost; price = (actual quantity purchased × standard price) − (actual quantity × actual price); usage = (standard quantity for actual output − actual quantity used) × standard price. Labour: rate = (hours paid × standard rate) − actual cost; idle time = (hours paid − hours worked) × standard rate, always adverse if idle time is not in the standard; efficiency = (standard hours for actual output − hours worked) × standard rate.
Price + usage = total material variance; rate + idle time + efficiency = total labour variance. If expected idle time is built into the standard, the idle time variance can be favourable, and idle time plus efficiency still total the same. Variances can be interrelated: a dearer, better material may give an adverse price but a favourable usage variance; cheaper, less skilled labour a favourable rate but an adverse efficiency variance.
Full marks come from the layout, the sign (F or A) and an explanation of the cause.
The flexed budget and the basic variances
Why the fixed budget is not used
The fixed budget is the original master plan for a stated volume. If actual volume differs, then actual cost compared with the fixed budget looks lower or higher only because less or more was made. A fair comparison needs a flexed budget, drawn up at the end of the period from the actual activity levels but using standard revenue per unit and standard cost per unit.
The difference between fixed and flexed budget is due only to volume; the difference between flexed budget and actual is due to price, quantity and efficiency, and these are what the cost variances explain. The flexed budget is at the heart of variance analysis.
Each variable cost variance is the actual cost of the actual output compared with the standard cost of the same output, split in two parts: a price part (what was paid per unit of the resource) and a quantity part (how much of the resource was used). In a cost accounting system the cost variances adjust profit: favourable ones increase it, adverse ones reduce it.
Variance reports at the end of each control period (a month) show large adverse variances that need control action, and large favourable ones that may be worth repeating.
Direct materials variances
- Total direct material cost variance = standard material cost of the actual output − actual material cost of that output. (Actual units × standard quantity × standard price, against actual quantity × actual price.)
- Price variance = (actual quantity purchased × standard price) − (actual quantity purchased × actual price). It is normally calculated at the point of purchase, so that stock is carried at standard cost. With several materials, calculate each separately.
- Usage variance = (standard quantity for the actual output − actual quantity used) × standard price. Work first in quantity, then convert at standard price.
Direct labour variances
- Total labour cost variance = standard labour cost of the actual output − actual labour cost.
- Rate variance = (hours paid for × standard rate) − actual cost of those hours. With several grades, one for each.
- Efficiency variance = (standard hours for the actual output − actual hours worked) × standard rate. It is also called the productivity variance.
- Idle time variance = (hours paid for − hours worked) × standard rate.
Idle time
Idle time is paid time with no work to do: a machine breakdown, a hold-up at an earlier stage, a material shortage, or a lack of orders. Idle time is recorded and its hours measured. If it is not in the standard it is unexpected, so the idle time variance is always adverse, and the efficiency variance is then calculated on hours worked (not paid).
If idle time is not recorded, it stays inside the efficiency variance.
If a regular amount of idle time is expected (for example because of bottlenecks), it can be built into the standard in two ways: method 1, as a separate element of the standard cost (for example 3.0 hours of work and 0.3 hours of idle time per unit); or method 2, as an allowance inside the standard hours per unit (for example 3.3 hours paid, of which 10% is idle).
Then the idle time variance compares actual idle hours with expected idle hours, and may be favourable or adverse. The two methods give the same total for idle time plus efficiency, but split it differently.
Causes and interrelationships
- Material price, favourable: a different, cheaper supplier; a bulk discount; lower-quality material. Adverse: a dearer supplier; an unexpected price rise or inflation; a shortage; better-quality material.
- Material usage, favourable: less waste; better methods. Adverse: more waste; poor handling and breakages; cheaper material that causes more rejects.
- Labour rate, favourable: less experienced and cheaper employees; a smaller pay rise than expected. Adverse: a pay rise; overtime premium; more skilled and better-paid staff.
- Labour efficiency, favourable: better methods; good morale and management; incentive schemes; more experienced staff. Adverse: less experienced staff; poor morale.
Interrelationships. Two variances may share one cause, so they should be read together. A dearer, better material gives an adverse price variance, but if there is less waste, a favourable usage variance. A lower grade of labour gives a favourable rate variance but, if the work takes longer, an adverse efficiency variance, and inexperienced staff may also waste more material (adverse usage).
A higher price that raises the sales price variance may reduce demand and so the volume variance. Finally, the value of variances depends on reliable standards: if the standard is wrong, a variance reflects the poor standard and not good or bad performance. Variances should also be reported to the manager who can control them.
Layouts for material and labour variances
- Standard cost of actual output = units × standard cost per unit.
- Material: AQ purchased × AC; AQ purchased × SC (price variance); AQ used × SC (movement in stock); SQ for actual output × SC (usage variance).
- Labour: AH paid × AR; AH paid × SR (rate); AH worked × SR (idle time); SH × SR (efficiency).
- Label each F or A and add to the total variance as a check.
Money is in naira and each answer is rounded once, at the end.
Worked examples
Example 1: material variances. Product Z has a standard material cost of 4 kg at ₦500 a kg = ₦2,000 a unit. In March 2,000 units were made. 8,300 kg were purchased and used, costing ₦4,316,000. Required: the total, price and usage variances.
- Total. Standard cost of 2,000 units = 4,000,000; actual 4,316,000; ₦316,000 A.
- Price.
8,300 kg should cost 8,300 × 500 = 4,150,000; did cost 4,316,000; ₦166,000 A (the actual price was ₦520 a kg). - Usage.
2,000 units should use 8,000 kg; did use 8,300; 300 kg A × ₦500 = ₦150,000 A. - Check.
166,000 + 150,000 = 316,000.
Example 2: labour variances with idle time not in the standard. The standard labour cost is 3 hours at ₦800 = ₦2,400 a unit. For the 2,000 units, 6,300 hours were paid, costing ₦5,166,000; 6,100 hours were worked. Required: the total, rate, idle time and efficiency variances.
- Total.
Standard 2,000 × 2,400 = 4,800,000; actual 5,166,000; ₦366,000 A. - Rate.
6,300 × 800 = 5,040,000; actual 5,166,000; ₦126,000 A. - Idle time.
(6,300 − 6,100) = 200 hours × 800 = ₦160,000 A. - Efficiency.
Standard hours 2,000 × 3 = 6,000; worked 6,100; 100 hours A × 800 = ₦80,000 A. - Check.
126,000 + 160,000 + 80,000 = 366,000.
Example 3: idle time built into the standard (method 1). As Example 2, but the standard allows 0.3 hours of idle time a unit in addition to 3 hours of work, so the standard cost is (3 + 0.3) × 800 = ₦2,640. Required: the variances.
- Total.
Standard 2,000 × 2,640 = 5,280,000; actual 5,166,000; ₦114,000 F. - Rate. unchanged, ₦126,000 A.
- Idle time.
Expected idle time 2,000 × 0.3 = 600 hours; actual 200; 400 hours F × 800 = ₦320,000 F. - Efficiency. Standard hours worked 6,000; actual 6,100; ₦80,000 A.
- Check.
−126,000 + 320,000 − 80,000 = 114,000 F.
The idle time is now favourable because less was lost than expected, though the efficiency of the hours worked was still poor.
Expect variants: several materials or grades of labour, opening and closing stock of materials (price on purchases, usage on use), a normal loss in the standard, a question that gives the variances and asks you to work back, or discussion of causes.
Common mistakes
- Comparing with the fixed budget instead of the flexed budget.
- Valuing usage at the actual price. Use the standard price.
- Efficiency on hours paid instead of hours worked when idle time is recorded.
- Calling idle time favourable when it is not in the standard.
- Wrong sign. Costs above standard are adverse.
- Not reading variances together, or blaming a manager for a cause outside his control.
Quick revision
- Flexed budget = actual activity at standard prices and costs.
- Material price (on purchases) + usage (at standard price) = total.
- Labour rate (hours paid) + idle time + efficiency (hours worked) = total.
- Idle time not in standard: always adverse; in standard: actual v expected idle hours.
- Interrelated: price/usage, rate/efficiency.
How the marks are earned
- Layout and correct quantities.
- Sign and check to the total.
- Cause and interrelationship for the case.
Practice questions
These are original questions, written in the style of the Skills examination. Work each one before you open the answer.
Recall check: multiple choice
Question 1. A flexed budget is based on:
- The original plan
- Last year
- Actual activity at standard revenue and standard costs
- Actual costs
Show the answer
C. It makes the comparison like for like.
Question 2. The material price variance is normally calculated on:
- The actual quantity purchased
- The standard quantity
- The budgeted quantity
- Opening stock
Show the answer
A. So that stock is carried at standard cost.
Question 3. The usage variance is valued at the:
- Actual price
- Average price
- Selling price
- Standard price
Show the answer
D. The price effect is in the price variance.
Question 4. The labour rate variance uses:
- Hours worked
- Hours paid for
- Standard hours
- Budgeted hours
Show the answer
B. Pay is for the hours paid.
Question 5. The efficiency variance compares:
- Standard hours for actual output with hours worked
- Rates
- Budgeted with actual sales
- Hours paid with budgeted hours
Show the answer
A. It is valued at the standard rate.
Question 6. If idle time is not in the standard, the idle time variance is:
- Favourable
- Zero
- Always adverse
- Either
Show the answer
C. All idle time is unexpected.
Question 7. Using cheaper, less skilled labour may give:
- Adverse rate and favourable efficiency
- Favourable rate and adverse efficiency
- Two favourable variances
- No variances
Show the answer
B. The two variances are interrelated.
Question 8. A dearer, better material may give:
- Favourable price and adverse usage
- Two adverse variances
- No variance
- Adverse price and favourable usage
Show the answer
D. Less waste offsets some of the cost.
Question 9. Variances are meaningful only if:
- The standards are reliable
- They are all favourable
- Costs are fixed
- Output is small
Show the answer
A. A wrong standard distorts every variance.
Question 10. Price variance plus usage variance equals:
- The sales variance
- The efficiency variance
- The total material cost variance
- The idle time variance
Show the answer
C. They split the total in two.
Section B style: written questions
Question 11 (10 marks). (a) Explain why the flexed budget is used. (3 marks) (b) State the formulae for the material price and usage variances. (3 marks) (c) Explain how idle time is treated if it is, and is not, in the standard. (4 marks)
Question 12 (15 marks). A unit has a standard material cost of 6 litres at ₦40 = ₦240. In a month 3,000 units were made, using 18,500 litres costing ₦762,200.
(a) Calculate the total material cost variance. (3 marks) (b) Calculate the price variance. (3 marks) (c) Calculate the usage variance. (3 marks) (d) State THREE possible causes. (3 marks) (e) Explain how the price and usage variances may be related. (3 marks)
Question 13 (20 marks). The standard labour cost is 0.5 hours at ₦1,200 = ₦600 a unit. 8,000 units were made. 4,300 hours were paid, costing ₦5,031,000; 4,100 hours were worked.
(a) Calculate the total, rate, idle time and efficiency variances. (10 marks) (b) Present them in the line-by-line layout. (4 marks) (c) Discuss possible causes and how the variances may be related. (6 marks)
Model answers
Show the model answer to Question 11
(a) Actual cost compared with a fixed budget at a different volume is not like for like. The flexed budget restates standard revenue and costs at actual activity, so that differences are due to price and efficiency (3).
(b) Price = actual quantity purchased × (standard price − actual price). Usage = (standard quantity for actual output − actual quantity used) × standard price (3).
(c) Not in the standard: all idle time is adverse, valued at the standard rate, and efficiency is based on hours worked. In the standard: compare actual with expected idle hours; the variance may be favourable or adverse; the total of idle time and efficiency is the same under either method (4).
Show the model answer to Question 12
(a) Standard 3,000 × 240 = 720,000; actual 762,200; ₦42,200 A (3).
(b) 18,500 × 40 = 740,000; actual 762,200; ₦22,200 A (3).
(c) Standard 3,000 × 6 = 18,000 litres; used 18,500; 500 A × 40 = ₦20,000 A; 22,200 + 20,000 = 42,200 (3).
(d) Any three: price rise or inflation; dearer supplier or shortage; better quality; more waste; poor handling; cheaper material causing rejects (3).
(e) A dearer, better quality material could cause an adverse price variance and a favourable usage variance from less waste; the reverse for cheaper material (3).
Show the model answer to Question 13
(a)
- Total.
standard 8,000 × 600 = 4,800,000; actual 5,031,000; ₦231,000 A. - Rate.
4,300 × 1,200 = 5,160,000; actual 5,031,000; ₦129,000 F. - Idle time.
200 × 1,200 = ₦240,000 A. - Efficiency.
standard hours 8,000 × 0.5 = 4,000; worked 4,100; 100 A × 1,200 = ₦120,000 A. - Check.
−129 + 240 + 120 = 231 A (10).
(b) Hours paid × actual rate 5,031,000; hours paid × standard rate 5,160,000 (rate 129,000 F); hours worked × standard rate 4,920,000 (idle 240,000 A); standard hours × standard rate 4,800,000 (efficiency 120,000 A) (4).
(c) The rate variance may come from using lower-paid, less experienced staff; if so, they may also explain the adverse efficiency variance. Idle time may come from breakdowns, hold-ups or a lack of orders. The favourable rate variance should not be seen as good performance on its own (6).
Pathfinder on Basic variances
These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.
Sales price and volume contribution variances; material price planning and operational variances; labour rate and efficiency; why management cares.
Revise first: Layouts for material and labour variances
Price, mix, yield, sales price, market size and share variances; strategy in a declining market.
Revise first: Layouts for material and labour variances
Standard cost card; April variances; reconcile budgeted and actual contribution; fixed overhead capacity/efficiency; factors in investigating variances.
Revise first: Layouts for material and labour variances
Variance reconciliation under marginal costing, fixed overhead variances, causes of labour variances.
Revise first: Layouts for material and labour variances
Source: ICAN Pathfinder, Performance Management. Diets covered: March/July Diet, 2020 to May Diet, 2026. All 13 diets in the Pathfinder are mapped.
Spotted a mistake? Tell us and we will check it.