A paint factory in Ibadan budgets to make 2,000 tins of a product in March. It makes 2,000, but the cost report shows that materials cost ₦316,000 more than the budget and labour ₦366,000 more. The directors ask the obvious question: was it the price we paid, or the quantity we used?

Was it the wage rate, or the speed of the workers, or the hours they stood idle because the mixing machine broke down? A total difference does not tell them where to look. Variance analysis splits it into parts that point to a cause and a person.

This topic starts the study of variances with the flexed budget on which they all rest, then explains the direct material variances (total, price and usage), the direct labour variances (total, rate, efficiency and idle time), the line-by-line layout for them, how idle time is treated when it is built into the standard, the possible causes, and the interrelationships that mean two variances may come from one decision.

It builds on the earlier topic on standard costing: its uses, how standards are set and the types of standard. The next topic covers material mix and yield variances.

In 30 seconds

A variance is the difference between actual and standard (or budget); it is favourable (F) if profit rises, adverse (A) if it falls. Variances are not found by comparing actual with the fixed budget, because activity differs. A flexed budget restates standard revenue and costs at the actual level of activity, and the comparison with it is like for like.

Materials: total = standard cost of actual output − actual cost; price = (actual quantity purchased × standard price) − (actual quantity × actual price); usage = (standard quantity for actual output − actual quantity used) × standard price. Labour: rate = (hours paid × standard rate) − actual cost; idle time = (hours paid − hours worked) × standard rate, always adverse if idle time is not in the standard; efficiency = (standard hours for actual output − hours worked) × standard rate.

Price + usage = total material variance; rate + idle time + efficiency = total labour variance. If expected idle time is built into the standard, the idle time variance can be favourable, and idle time plus efficiency still total the same. Variances can be interrelated: a dearer, better material may give an adverse price but a favourable usage variance; cheaper, less skilled labour a favourable rate but an adverse efficiency variance.

Full marks come from the layout, the sign (F or A) and an explanation of the cause.

The flexed budget and the basic variances

Why the fixed budget is not used

The fixed budget is the original master plan for a stated volume. If actual volume differs, then actual cost compared with the fixed budget looks lower or higher only because less or more was made. A fair comparison needs a flexed budget, drawn up at the end of the period from the actual activity levels but using standard revenue per unit and standard cost per unit.

The difference between fixed and flexed budget is due only to volume; the difference between flexed budget and actual is due to price, quantity and efficiency, and these are what the cost variances explain. The flexed budget is at the heart of variance analysis.

Each variable cost variance is the actual cost of the actual output compared with the standard cost of the same output, split in two parts: a price part (what was paid per unit of the resource) and a quantity part (how much of the resource was used). In a cost accounting system the cost variances adjust profit: favourable ones increase it, adverse ones reduce it.

Variance reports at the end of each control period (a month) show large adverse variances that need control action, and large favourable ones that may be worth repeating.

Direct materials variances

  • Total direct material cost variance = standard material cost of the actual output − actual material cost of that output. (Actual units × standard quantity × standard price, against actual quantity × actual price.)
  • Price variance = (actual quantity purchased × standard price) − (actual quantity purchased × actual price). It is normally calculated at the point of purchase, so that stock is carried at standard cost. With several materials, calculate each separately.
  • Usage variance = (standard quantity for the actual output − actual quantity used) × standard price. Work first in quantity, then convert at standard price.

Direct labour variances

  • Total labour cost variance = standard labour cost of the actual output − actual labour cost.
  • Rate variance = (hours paid for × standard rate) − actual cost of those hours. With several grades, one for each.
  • Efficiency variance = (standard hours for the actual output − actual hours worked) × standard rate. It is also called the productivity variance.
  • Idle time variance = (hours paid for − hours worked) × standard rate.

Idle time

Idle time is paid time with no work to do: a machine breakdown, a hold-up at an earlier stage, a material shortage, or a lack of orders. Idle time is recorded and its hours measured. If it is not in the standard it is unexpected, so the idle time variance is always adverse, and the efficiency variance is then calculated on hours worked (not paid).

If idle time is not recorded, it stays inside the efficiency variance.

If a regular amount of idle time is expected (for example because of bottlenecks), it can be built into the standard in two ways: method 1, as a separate element of the standard cost (for example 3.0 hours of work and 0.3 hours of idle time per unit); or method 2, as an allowance inside the standard hours per unit (for example 3.3 hours paid, of which 10% is idle).

Then the idle time variance compares actual idle hours with expected idle hours, and may be favourable or adverse. The two methods give the same total for idle time plus efficiency, but split it differently.

The line-by-line layout for labour variancesFour stacked lines: actual hours paid at actual rate, actual hours paid at standard rate, actual hours worked at standard rate, and standard hours for actual output at standard rate. Brackets between the lines name the rate variance, the idle time variance and the efficiency variance.Hours paid × actual rateHours paid × standard rateHours worked × standard rateStandard hours × standard rateRate varianceIdle time varianceEfficiency variance

Causes and interrelationships

  • Material price, favourable: a different, cheaper supplier; a bulk discount; lower-quality material. Adverse: a dearer supplier; an unexpected price rise or inflation; a shortage; better-quality material.
  • Material usage, favourable: less waste; better methods. Adverse: more waste; poor handling and breakages; cheaper material that causes more rejects.
  • Labour rate, favourable: less experienced and cheaper employees; a smaller pay rise than expected. Adverse: a pay rise; overtime premium; more skilled and better-paid staff.
  • Labour efficiency, favourable: better methods; good morale and management; incentive schemes; more experienced staff. Adverse: less experienced staff; poor morale.

Interrelationships. Two variances may share one cause, so they should be read together. A dearer, better material gives an adverse price variance, but if there is less waste, a favourable usage variance. A lower grade of labour gives a favourable rate variance but, if the work takes longer, an adverse efficiency variance, and inexperienced staff may also waste more material (adverse usage).

A higher price that raises the sales price variance may reduce demand and so the volume variance. Finally, the value of variances depends on reliable standards: if the standard is wrong, a variance reflects the poor standard and not good or bad performance. Variances should also be reported to the manager who can control them.

Layouts for material and labour variances

  1. Standard cost of actual output = units × standard cost per unit.
  2. Material: AQ purchased × AC; AQ purchased × SC (price variance); AQ used × SC (movement in stock); SQ for actual output × SC (usage variance).
  3. Labour: AH paid × AR; AH paid × SR (rate); AH worked × SR (idle time); SH × SR (efficiency).
  4. Label each F or A and add to the total variance as a check.

Money is in naira and each answer is rounded once, at the end.

Worked examples

Example 1: material variances. Product Z has a standard material cost of 4 kg at ₦500 a kg = ₦2,000 a unit. In March 2,000 units were made. 8,300 kg were purchased and used, costing ₦4,316,000. Required: the total, price and usage variances.

  1. Total. Standard cost of 2,000 units = 4,000,000; actual 4,316,000; ₦316,000 A.
  2. Price.
    8,300 kg should cost 8,300 × 500 = 4,150,000; did cost 4,316,000; ₦166,000 A (the actual price was ₦520 a kg).
  3. Usage.
    2,000 units should use 8,000 kg; did use 8,300; 300 kg A × ₦500 = ₦150,000 A.
  4. Check.
    166,000 + 150,000 = 316,000.

Example 2: labour variances with idle time not in the standard. The standard labour cost is 3 hours at ₦800 = ₦2,400 a unit. For the 2,000 units, 6,300 hours were paid, costing ₦5,166,000; 6,100 hours were worked. Required: the total, rate, idle time and efficiency variances.

  1. Total.
    Standard 2,000 × 2,400 = 4,800,000; actual 5,166,000; ₦366,000 A.
  2. Rate.
    6,300 × 800 = 5,040,000; actual 5,166,000; ₦126,000 A.
  3. Idle time.
    (6,300 − 6,100) = 200 hours × 800 = ₦160,000 A.
  4. Efficiency.
    Standard hours 2,000 × 3 = 6,000; worked 6,100; 100 hours A × 800 = ₦80,000 A.
  5. Check.
    126,000 + 160,000 + 80,000 = 366,000.

Example 3: idle time built into the standard (method 1). As Example 2, but the standard allows 0.3 hours of idle time a unit in addition to 3 hours of work, so the standard cost is (3 + 0.3) × 800 = ₦2,640. Required: the variances.

  1. Total.
    Standard 2,000 × 2,640 = 5,280,000; actual 5,166,000; ₦114,000 F.
  2. Rate. unchanged, ₦126,000 A.
  3. Idle time.
    Expected idle time 2,000 × 0.3 = 600 hours; actual 200; 400 hours F × 800 = ₦320,000 F.
  4. Efficiency. Standard hours worked 6,000; actual 6,100; ₦80,000 A.
  5. Check.
    −126,000 + 320,000 − 80,000 = 114,000 F.
    The idle time is now favourable because less was lost than expected, though the efficiency of the hours worked was still poor.

Expect variants: several materials or grades of labour, opening and closing stock of materials (price on purchases, usage on use), a normal loss in the standard, a question that gives the variances and asks you to work back, or discussion of causes.

Common mistakes

  • Comparing with the fixed budget instead of the flexed budget.
  • Valuing usage at the actual price. Use the standard price.
  • Efficiency on hours paid instead of hours worked when idle time is recorded.
  • Calling idle time favourable when it is not in the standard.
  • Wrong sign. Costs above standard are adverse.
  • Not reading variances together, or blaming a manager for a cause outside his control.

Quick revision

  • Flexed budget = actual activity at standard prices and costs.
  • Material price (on purchases) + usage (at standard price) = total.
  • Labour rate (hours paid) + idle time + efficiency (hours worked) = total.
  • Idle time not in standard: always adverse; in standard: actual v expected idle hours.
  • Interrelated: price/usage, rate/efficiency.

How the marks are earned

  • Layout and correct quantities.
  • Sign and check to the total.
  • Cause and interrelationship for the case.

Practice questions

These are original questions, written in the style of the Skills examination. Work each one before you open the answer.

Recall check: multiple choice

Question 1. A flexed budget is based on:

  1. The original plan
  2. Last year
  3. Actual activity at standard revenue and standard costs
  4. Actual costs
Show the answer

C. It makes the comparison like for like.

Question 2. The material price variance is normally calculated on:

  1. The actual quantity purchased
  2. The standard quantity
  3. The budgeted quantity
  4. Opening stock
Show the answer

A. So that stock is carried at standard cost.

Question 3. The usage variance is valued at the:

  1. Actual price
  2. Average price
  3. Selling price
  4. Standard price
Show the answer

D. The price effect is in the price variance.

Question 4. The labour rate variance uses:

  1. Hours worked
  2. Hours paid for
  3. Standard hours
  4. Budgeted hours
Show the answer

B. Pay is for the hours paid.

Question 5. The efficiency variance compares:

  1. Standard hours for actual output with hours worked
  2. Rates
  3. Budgeted with actual sales
  4. Hours paid with budgeted hours
Show the answer

A. It is valued at the standard rate.

Question 6. If idle time is not in the standard, the idle time variance is:

  1. Favourable
  2. Zero
  3. Always adverse
  4. Either
Show the answer

C. All idle time is unexpected.

Question 7. Using cheaper, less skilled labour may give:

  1. Adverse rate and favourable efficiency
  2. Favourable rate and adverse efficiency
  3. Two favourable variances
  4. No variances
Show the answer

B. The two variances are interrelated.

Question 8. A dearer, better material may give:

  1. Favourable price and adverse usage
  2. Two adverse variances
  3. No variance
  4. Adverse price and favourable usage
Show the answer

D. Less waste offsets some of the cost.

Question 9. Variances are meaningful only if:

  1. The standards are reliable
  2. They are all favourable
  3. Costs are fixed
  4. Output is small
Show the answer

A. A wrong standard distorts every variance.

Question 10. Price variance plus usage variance equals:

  1. The sales variance
  2. The efficiency variance
  3. The total material cost variance
  4. The idle time variance
Show the answer

C. They split the total in two.

Section B style: written questions

Question 11 (10 marks). (a) Explain why the flexed budget is used. (3 marks) (b) State the formulae for the material price and usage variances. (3 marks) (c) Explain how idle time is treated if it is, and is not, in the standard. (4 marks)

Question 12 (15 marks). A unit has a standard material cost of 6 litres at ₦40 = ₦240. In a month 3,000 units were made, using 18,500 litres costing ₦762,200.

(a) Calculate the total material cost variance. (3 marks) (b) Calculate the price variance. (3 marks) (c) Calculate the usage variance. (3 marks) (d) State THREE possible causes. (3 marks) (e) Explain how the price and usage variances may be related. (3 marks)

Question 13 (20 marks). The standard labour cost is 0.5 hours at ₦1,200 = ₦600 a unit. 8,000 units were made. 4,300 hours were paid, costing ₦5,031,000; 4,100 hours were worked.

(a) Calculate the total, rate, idle time and efficiency variances. (10 marks) (b) Present them in the line-by-line layout. (4 marks) (c) Discuss possible causes and how the variances may be related. (6 marks)

Model answers

Show the model answer to Question 11

(a) Actual cost compared with a fixed budget at a different volume is not like for like. The flexed budget restates standard revenue and costs at actual activity, so that differences are due to price and efficiency (3).

(b) Price = actual quantity purchased × (standard price − actual price). Usage = (standard quantity for actual output − actual quantity used) × standard price (3).

(c) Not in the standard: all idle time is adverse, valued at the standard rate, and efficiency is based on hours worked. In the standard: compare actual with expected idle hours; the variance may be favourable or adverse; the total of idle time and efficiency is the same under either method (4).

Show the model answer to Question 12

(a) Standard 3,000 × 240 = 720,000; actual 762,200; ₦42,200 A (3).

(b) 18,500 × 40 = 740,000; actual 762,200; ₦22,200 A (3).

(c) Standard 3,000 × 6 = 18,000 litres; used 18,500; 500 A × 40 = ₦20,000 A; 22,200 + 20,000 = 42,200 (3).

(d) Any three: price rise or inflation; dearer supplier or shortage; better quality; more waste; poor handling; cheaper material causing rejects (3).

(e) A dearer, better quality material could cause an adverse price variance and a favourable usage variance from less waste; the reverse for cheaper material (3).

Show the model answer to Question 13

(a)

  1. Total.
    standard 8,000 × 600 = 4,800,000; actual 5,031,000; ₦231,000 A.
  2. Rate.
    4,300 × 1,200 = 5,160,000; actual 5,031,000; ₦129,000 F.
  3. Idle time.
    200 × 1,200 = ₦240,000 A.
  4. Efficiency.
    standard hours 8,000 × 0.5 = 4,000; worked 4,100; 100 A × 1,200 = ₦120,000 A.
  5. Check.
    −129 + 240 + 120 = 231 A (10).

(b) Hours paid × actual rate 5,031,000; hours paid × standard rate 5,160,000 (rate 129,000 F); hours worked × standard rate 4,920,000 (idle 240,000 A); standard hours × standard rate 4,800,000 (efficiency 120,000 A) (4).

(c) The rate variance may come from using lower-paid, less experienced staff; if so, they may also explain the adverse efficiency variance. Idle time may come from breakdowns, hold-ups or a lack of orders. The favourable rate variance should not be seen as good performance on its own (6).

Pathfinder on Basic variances

These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.

November Diet, 2025: Question 3 (20 marks)

Sales price and volume contribution variances; material price planning and operational variances; labour rate and efficiency; why management cares.

Revise first: Layouts for material and labour variances

November Diet, 2024: Question 1 (30 marks)

Price, mix, yield, sales price, market size and share variances; strategy in a declining market.

Revise first: Layouts for material and labour variances

November Diet, 2022: Question 3 (20 marks)

Standard cost card; April variances; reconcile budgeted and actual contribution; fixed overhead capacity/efficiency; factors in investigating variances.

Revise first: Layouts for material and labour variances

November Diet, 2020: Question 3 (20 marks)

Variance reconciliation under marginal costing, fixed overhead variances, causes of labour variances.

Revise first: Layouts for material and labour variances

Source: ICAN Pathfinder, Performance Management. Diets covered: March/July Diet, 2020 to May Diet, 2026. All 13 diets in the Pathfinder are mapped.

Spotted a mistake? Tell us and we will check it.

Where this fits

See every past question on Performance Management and the topic each one tests in the Pathfinder question finder.

This course builds on Management Accounting. After it, move on to Strategic Financial Management.

All Performance Management topics

You are reading topic 46 of 77.

  1. Information systems in organisations: role, costs and benefits01
  2. Internet, intranet, wireless technology and networks in business02
  3. Information needs at strategic, tactical and operational levels03
  4. TPS, MIS, EIS, ERP and CRM systems compared04
  5. Social and ethical issues in strategy and the management accountant’s data role05
  6. Big data principles and the big data pyramid06
  7. Big data, data mining and analytics: uses, benefits, challenges and risks07
  8. Activity based costing: cost pools, cost drivers and calculations08
  9. Activity based costing compared with traditional absorption costing09
  10. Target costing: principles and calculating the target cost10
  11. Managing the target cost gap and target costing in services11
  12. Life cycle costing: product life cycle stages and costs12
  13. Life cycle cost and profit calculations, and the benefits of life cycle costing13
  14. Throughput accounting: theory of constraints and the throughput accounting ratio14
  15. Environmental management accounting and sustainability in business15
  16. Environmental costs: methods, challenges and the management accountant’s role16
  17. Relevant costs and revenues, and opportunity cost17
  18. Relevant costs for specific decisions: materials, labour, equipment and overheads18
  19. Break-even analysis and margin of safety for Skills level decisions19
  20. Contribution to sales ratio, target profit and target revenue20
  21. Break-even charts and profit-volume charts21
  22. Multi-product CVP analysis and its limitations22
  23. Limiting factors: allocating a single scarce resource23
  24. Linear programming: formulation and graphical solution24
  25. Linear programming: slack and shadow prices25
  26. Price elasticity of demand and the factors that influence price26
  27. Demand and cost functions: profit-maximising price and output27
  28. Cost-based pricing: cost-plus and relevant-cost pricing28
  29. Market-based pricing: skimming, penetration and other strategies29
  30. Make-or-buy and outsourcing decisions30
  31. One-off contracts, shutdown and further processing of joint products31
  32. Reducing uncertainty: research, simulation and sensitivity analysis32
  33. Expected values and decision rules: maximax, maximin and minimax regret33
  34. Decision trees for multi-stage decisions34
  35. Value of perfect and imperfect information35
  36. Budgetary systems and types of budget: choosing the right one36
  37. Preparing fixed and flexed budgets37
  38. Rolling, activity-based, functional and master budgets38
  39. The beyond budgeting model: benefits and problems39
  40. Participation, negotiation and ethics in budgeting40
  41. High-low method and cost estimation for budgets41
  42. Correlation, regression and time series for budgeting and forecasting42
  43. Learning curve: learning rate and learning effect43
  44. Learning curve in budgeting: steady state and limitations44
  45. Standard costing: uses, how standards are set and types of standard45
  46. Basic variances: material, labour and idle time46 here
  47. Material mix and yield variances47
  48. Labour mix and yield variances48
  49. Sales mix and quantity variances49
  50. Planning and operational variances: revised budget, sales, market size and market share50
  51. Planning and operational variances for materials and labour51
  52. Overhead variances and reconciling budgeted and actual profit at Skills level52
  53. Behavioural effects of variances: motivation, JIT and TQM53
  54. Profitability ratios and financial performance measures54
  55. Liquidity, solvency and efficiency ratios55
  56. Non-financial performance indicators56
  57. Short-termism and financial manipulation of results57
  58. Sustainability and ESG performance measures58
  59. The balanced scorecard59
  60. The Fitzgerald and Moon building block model60
  61. Performance measurement in not-for-profit organisations61
  62. Value for money as a public sector objective62
  63. Divisional performance: return on investment and residual income63
  64. Economic value added (EVA)64
  65. Transfer pricing methods and the optimal transfer price65
  66. Transfer pricing: problems, tax and repatriation of funds66
  67. Value chain analysis for performance management67
  68. Complex business structures: alliances, joint ventures and supply chains68
  69. The performance pyramid69
  70. Value-based management70
  71. Corporate failure and life cycle issues71
  72. The Z-score and other quantitative failure models72
  73. The Argenti model and qualitative failure prediction73
  74. Preventing corporate failure and performance improvement strategies74
  75. Current developments in management accounting75
  76. Benchmarking and target setting in the public sector76
  77. The changing role of the management accountant and contemporary issues77
See the whole course

Get the complete Performance Management notes

Download as PDF or Word

  • Every topic as PDF and Word, ready to print
  • Edit it in Word or print the PDF. No retyping.
Get this course

Reading stays free. Access lasts 12 months. Pay by card, bank transfer, USSD or QR through Paystack. Your name and email appear on every page of your files. Read our Refund Policy.

PracticeNext topic