A cost gap is not a failure. It is the normal result of a first design, which is usually drawn to please customers, not to hit a cost. The skill lies in closing the gap without taking away what customers value, and doing it as a team, because the savings are spread across design, purchasing, production, distribution and after-sales service.
This topic explains how a cost gap is managed and the methods used to close it, the advantages of target costing and its effect on pricing, cost control and performance measurement, and how the method works, and where it struggles, in service businesses where overhead is the main cost. It builds on the target costing principles topic. The next topic introduces life cycle costing.
In 30 seconds
The target cost gap is the estimated cost of a product less its target cost, where the target cost is a competitive market price less the required profit margin. It is closed by a multi-disciplinary team: redesign to use common parts and processes, work with suppliers, remove non-value-added features and activities (value analysis), train staff for efficiency, and economies of scale where demand allows.
Advantages: better understanding of cost, cost planned from design onwards, customer focus, co-operation across departments and suppliers, and fit with value engineering, just-in-time, total quality management and continuous improvement. In services, direct materials are small and overhead is large, a single delivery system serves many services, new services can reduce service quality for existing customers, and not-for-profit bodies may have no target price.
Challenges are resistance to change, balancing cost and value, inaccurate market analysis and cost estimates and coordination. Full marks come from linking each method to the business.
Managing a target cost gap
Target costs are rarely met at the first attempt, so ways must be found to cut cost. A multi-disciplinary approach is needed. The management accountant measures estimated costs, while ideas for reducing them come from the sales, manufacturing, engineering and purchasing departments, in product design, manufacturing processes, selling methods and purchase of raw materials. The common methods are:
- Redesign products to use common processes and components that the company already uses for other products.
- Work with key suppliers to reduce materials costs. Target costing involves the whole value chain, from original suppliers to the customer, so negotiation and collaboration with suppliers may give important savings.
- Eliminate non-value-added activities and features. Something is non-value-added if it adds nothing the customer values, so its cost can be saved without loss of value. Value analysis systematically examines all aspects of cost to provide the required quality at the lowest possible cost.
- Train staff in more efficient techniques and working methods, since greater efficiency reduces cost.
- Achieve economies of scale. Larger quantities spread fixed overhead over more units, but only help if sales demand grows by the same amount.
Advantages of target costing
- It improves understanding of product costs within the company.
- It recognises that the most effective way to reduce cost is to plan and control it from the design stage.
- It focuses the company on the final customer, because the concept of value matters: the target must be met without loss of value to the customer.
- It is multi-disciplinary and considers the whole supply chain, so it promotes co-operation between departments and with suppliers and customers.
- It can be used with value analysis, value engineering, just-in-time purchasing and production, total quality management and continuous improvement.
Implications for pricing, cost control and performance measurement
A company can fix a target selling price, for a new or existing product, to win market share or volume, and then work out the target cost.
With target costing, cost control and performance measurement change:
- cost savings are sought continuously over the life of the product
- responsibility for savings is shared, so if one department fails to deliver, others may find the saving
- staff are trained and empowered to find ways to cut cost while keeping quality
The method works best in a company with a culture of continuous improvement.
Target costing in service businesses
Target costing can be used for services as well as products, but services differ, and the differences matter:
- Some services are labour-intensive and direct materials are a small part of cost, so there is little to save on materials.
- Overhead is very high in many services, so effective target costing must focus on reducing overhead.
- One delivery system, using the same staff and assets, often provides several services. Adding or changing a service adds to the work and variety of the same employees, and may reduce the quality of existing services: a new service in a call centre can lengthen waiting times for callers.
- New services may be introduced without checking whether they are profitable. A restaurant may add menu items thinking the only extra cost is the food, but there are also purchasing, preparation and delivery costs, so new items may lose money.
- When one delivery system serves several services, most cost is allocated and apportioned overhead, so a consistent and fair method of attributing overhead to services is needed. Activity based costing helps.
- Not-for-profit bodies, such as a government health service providing free care, can use target costing for new services. But it is doubtful that the concepts of target price and target profit apply, so the basis for the target cost must be decided differently.
The system should therefore focus on quality of service and value to the customer.
Challenges in service industries, and how to meet them
- Cultural shift and resistance to change, from fear of job loss and uncertainty: training, orientation and workshops.
- Balancing cost reduction and value creation: clear customer-focused feedback so the industry stays customer-focused.
- Inaccurate market analysis and problems in cost estimation: good data mining and analysis to handle insufficient or very large data, and proper feedback.
- Interdepartmental coordination and complexity: clear lines of authority and departmental functions, and cross-functional teams.
- Unrealistic staff appraisal and ineffective measures: motivation of staff and effective performance measurement.
Layouts for gap and redesign questions
- Target cost = price × (1 − margin %). Estimated cost = sum of cost elements per unit.
- Cost gap = estimated cost − target cost.
- Cost elements after a redesign: apply each change (a percentage cut, fewer hours, a lower failure rate) to its element; a failure cost is probability × cost of failure.
- Residual gap = revised cost − target cost. Share of gap closed = savings ÷ original gap.
- Service items: overhead per minute (or hour) × minutes used; add direct costs; compare with target.
Money is in naira per unit, figures are rounded once at the end, and percentages to one decimal place.
Worked examples
Example 1: redesign of a manufactured product. A company will sell a product at ₦80,000 with a required margin of 25% of price. Its first design costs per unit: parts ₦36,000; assembly labour 10 hours at ₦450; machine cost ₦12,000; quality assurance 8 hours at ₦700; rework 8% of units at ₦9,000 each; distribution ₦8,000; warranty, 10% of units at ₦14,000 each. A redesign would cut parts cost by 10%, assembly time by 20%, quality assurance to 6 hours, rework to 4%, distribution to ₦7,000 and warranty failures to 5%.
Required: the target cost, the original gap, the revised cost and what remains.
- Target cost.
80,000 × 0.75 = ₦60,000. - First design.
Parts 36,000; labour 10 × 450 = 4,500; machine 12,000; quality 8 × 700 = 5,600; rework 8% × 9,000 = 720; distribution 8,000; warranty 10% × 14,000 = 1,400.
Total ₦68,220.
Gap 68,220 − 60,000 = ₦8,220. - Redesign.
Parts 36,000 × 0.90 = 32,400; labour 8 × 450 = 3,600; machine 12,000; quality 6 × 700 = 4,200; rework 4% × 9,000 = 360; distribution 7,000; warranty 5% × 14,000 = 700.
Total ₦60,260. - Savings.
68,220 − 60,260 = ₦7,960, which is 96.8% of the gap. - Residual gap.
60,260 − 60,000 = ₦260. - Comment. The redesign nearly closes the gap. The remaining ₦260 is less than 1% of the parts cost (₦324 would be 1%), so a small price concession from suppliers would close it. The team should confirm that the redesign keeps the features customers value.
Example 2: a new service item. A restaurant plans a new dish to sell at ₦4,500 with a required margin of 40% of price. Food costs ₦1,300; kitchen labour is 0.25 hours at ₦1,600; overhead is ₦3,600,000 a month shared over 24,000 preparation minutes, so ₦150 a minute, and the dish takes 8 minutes. Required: the target cost, the expected cost and the gap, and the effect of cutting preparation to 6 minutes.
- Target cost.
4,500 × 0.60 = ₦2,700. - Expected cost.
Food 1,300; labour 0.25 × 1,600 = 400; overhead 8 × 150 = 1,200.
Total ₦2,900. - Gap.
2,900 − 2,700 = ₦200. - After redesign.
Overhead 6 × 150 = 900, a saving of 300.
Cost ₦2,600, which is ₦100 below the target. - Comment. Most of the cost is overhead, so the saving came from time in the kitchen, not from food. The kitchen’s total minutes are limited, so the restaurant should check that the new dish does not slow other orders, which would reduce service to existing customers.
Expect variants: several redesign changes at once, a price that must be set from a required return, overhead absorbed by an activity driver, or a question on a not-for-profit service where the target is a budget.
Common mistakes
- Closing the gap by cutting quality. Value to the customer must be kept.
- Giving a list of methods with no link to the business. Say which department would deliver each.
- Forgetting that service cost is mostly overhead and so looking for material savings.
- Failing to allocate overhead fairly across services that share one delivery system.
- Treating a failure rate as a cost per unit. Multiply the rate by the cost of the failure.
- Ignoring resistance to change when advising on adoption.
Quick revision
- Gap = estimated cost − target cost; close by redesign, suppliers, removing non-value-added items, training, scale.
- Advantages: cost understanding, planned from design, customer focus, co-operation, links to other methods.
- Implications: continuous saving, joint responsibility, empowered staff; needs a continuous improvement culture.
- Services: overhead-heavy, shared delivery systems, new services can harm old ones, fair overhead allocation needed, not-for-profit difficulty.
- Challenges: resistance to change, cost against value, estimation errors, coordination.
How the marks are earned
- Advise on closing a gap: each method with a business application, about one mark each.
- Discuss services: a feature of services and its effect on target costing.
- Calculate: each revised element, the new total, the residual gap.
Practice questions
These are original questions, written in the style of the Skills examination. Work each one before you open the answer.
Recall check: multiple choice
Question 1. A target cost gap can be reduced by:
- Raising the target price without limit
- Ignoring customers
- Redesigning the product to use common components
- Removing the target
Show the answer
C. Common parts spread cost over more products.
Question 2. In many service businesses most of the cost is:
- Overhead
- Direct materials
- Packaging
- Raw materials
Show the answer
A. So target costing must focus on overhead.
Question 3. A challenge of target costing in services is:
- Too many raw materials
- Fairly attributing overhead to services that share one delivery system
- Too little overhead
- No customers
Show the answer
B. Activity based costing can help.
Question 4. Value analysis:
- Sets selling prices
- Audits accounts
- Values inventory
- Examines all aspects of cost to provide the required quality at the lowest cost
Show the answer
D. It finds non-value-added features.
Question 5. A non-value-added feature is one that:
- Customers value most
- Is free
- Adds nothing the customer values
- Is legally required
Show the answer
C. Its cost can be saved without loss of value.
Question 6. Under target costing, performance measurement emphasises:
- Continuous savings over the product life and joint responsibility
- One-off savings
- Individual blame
- Ignoring cost
Show the answer
A. Other departments may find the saving if one fails.
Question 7. Target costing is most likely to succeed in a company with:
- No budget
- A single product
- Secret costs
- A culture of continuous improvement
Show the answer
D. Staff are trained and empowered to find savings.
Question 8. Resistance to change in service target costing is best met by:
- Threats
- Training, orientation and workshops
- Silence
- Dropping the project
Show the answer
B. Fear of job loss is a common cause.
Question 9. Economies of scale help close a gap only if:
- Prices fall
- Costs rise
- Demand rises by the same amount
- Suppliers refuse
Show the answer
C. Larger output without sales only builds inventory.
Question 10. In a not-for-profit service, target costing is difficult because:
- It is doubtful that target price and target profit apply
- There are no costs
- There are no staff
- Services are illegal
Show the answer
A. The basis for the target cost must be decided differently.
Section B style: written questions
Question 11 (10 marks). (a) Describe FIVE ways in which a target cost gap can be closed. (5 marks) (b) State FIVE advantages of target costing. (5 marks)
Question 12 (15 marks). A product will sell at ₦50,000 with a required margin of 30% of price. The first design costs per unit: parts ₦20,000; assembly 6 hours at ₦500; machine ₦7,500; quality assurance 5 hours at ₦600; rework 10% of units at ₦8,000; distribution ₦4,500; warranty, 10% of units at ₦9,000. A redesign cuts parts by 12%, assembly time by 25%, quality assurance to 3.5 hours, rework to 5%, distribution to ₦3,800 and warranty to 5% of units at ₦7,000.
(a) Calculate the target cost. (2 marks) (b) Calculate the first-design cost and the gap. (5 marks) (c) Calculate the cost after redesign. (5 marks) (d) State whether the target is met, and by how much. (3 marks)
Question 13 (20 marks). A restaurant will sell a new dish at ₦6,000 with a margin of 35% of price. Food costs ₦1,700; kitchen labour is 0.3 hours at ₦1,500; overhead is absorbed at ₦180 for each preparation minute, and the dish takes 10 minutes.
(a) Calculate the target cost, the expected cost and the gap. (6 marks) (b) Explain the features of service businesses that make target costing harder. (7 marks) (c) Advise how the gap could be closed and the risks of doing so. (7 marks)
Model answers
Show the model answer to Question 11
(a) Redesign to use common components and processes; negotiate with suppliers; remove non-value-added features and activities using value analysis; train staff in efficient methods; achieve economies of scale if demand rises (1 each).
(b) Any five:
- better understanding of product costs
- cost planned and controlled from design
- focus on the customer and value
- multi-disciplinary and whole-supply-chain co-operation
- works with value analysis, just-in-time and total quality management
- continuous improvement (1 each)
Show the model answer to Question 12
(a) 50,000 × 0.70 = ₦35,000 (2).
(b)
- Parts 20,000; assembly 6 × 500 = 3,000; machine 7,500; quality 5 × 600 = 3,000; rework 10% × 8,000 = 800; distribution 4,500; warranty 10% × 9,000 = 900.
- Total ₦39,700.
- Gap 39,700 − 35,000 = ₦4,700 (5).
(c)
- Parts 20,000 × 0.88 = 17,600; assembly 4.5 × 500 = 2,250; machine 7,500; quality 3.5 × 600 = 2,100; rework 5% × 8,000 = 400; distribution 3,800; warranty 5% × 7,000 = 350.
- Total ₦34,000 (5).
(d) The target is met: 34,000 is ₦1,000 below the target cost, a margin of safety. The team should check that customer value is unchanged and monitor cost in production (3).
Show the model answer to Question 13
(a)
- Target cost 6,000 × 0.65 = ₦3,900.
- Expected cost.
food 1,700; labour 0.3 × 1,500 = 450; overhead 10 × 180 = 1,800; total ₦3,950. - Gap ₦50 (6).
(b) Direct materials are a small part of cost, so there is little material saving; overhead is large, so the focus must be overhead; one kitchen and staff serve many dishes, so a new dish adds work and may slow existing orders; new items may be added without checking profitability; overhead must be attributed fairly, for example by preparation time; and in not-for-profit services target price and profit may not apply (any seven points, 1 each).
(c) Cut preparation time, for example by preparing sauces in batches, which reduces overhead absorbed; negotiate food prices; simplify the dish without losing what customers value; train kitchen staff. Risks: lower quality or portion, slower service for other diners if the kitchen is overloaded, resistance from staff, and a saving that exists only on paper if total kitchen minutes do not fall (any seven points) (7).
Spotted a mistake? Tell us and we will check it.