0 objective and 6 theory
Time allowed: 31/4 hours (including 15 minutes reading time).
0 objective6 theory140 theory marks set
No.SectionMarksCovers
Q1Section A (compulsory)40LP concept and uses; cost-plus prices; optimal output; shadow prices (e: NPV/IRR outside course).
Q2Section B20Choose forecast with limiting material; principal budget factor, manual, committee.
Q3Section B20Regression forecast with seasonal adjustment; 10 v 5 periods, r squared.
Q4Section B20Redraft school budget with expected values; incremental v zero-based budgeting.
Q5Section B20Stock order quantity under demand probabilities (expected value), compare with EOQ.
Q6Section B20Absorption v ABC cost, effect on cost-plus prices and sales with elasticity.

Theory questions Written questions

1
Theory question 1Section A (compulsory)
40 marks
a 5b 5c 10

The Managing Director of NTAMS Manufacturing Company Limited located in Lagos attended a seminar titled “optimising scarce resource utility in a manufacturing setting with particular reference to linear programming”. On his return after three days of the programme, he called for a management meeting to discuss his experiences at the seminar in view of the board decision to produce two major products in the coming years. The following information are made from the work of a research team earlier conducted by a group of external research experts. The expected products are “Biggi” and “smalli”. The expected costs statistics are as follows: Biggis N Smallis N Material costs (5kg @ N50/kg) 250 (3kg @ N50/kg) 150 Labour costs: Machining time (4 hours@ N15/Hr) 60 (2hours @ N15/Hr) 30 Other Processing Time (4hours @ N10/Hr) 40 (5 hours @ N10/Hr) 50 The company expects to maintain a pricing policy that is hinged on total cost of production plus 20% mark up on cost. The Company further expects to incur annual period overhead of N10,000,000 with normal production expectation of 200,000 units of Biggis and 100,000 units of Smallis absorbing the overhead on 3 to 2 basis respectively. It is expected that in the forth coming year, the company will have the following resources available 56 Materials 1,800,000kgs Machine time 800,000 hours Other Process time 1,400,000 hours You are

RequiredAs the management accountant
a

Explain briefly the concept of linear programming and usefulness of the model

5 marks
b

Compute the Prices that will be adopted by the company for the two products using the company pricing policy

5 marks
c

Advise the company on the output that needs to be produced to maximise its total profit, supporting your answer with full financial analysis

10 marks
d

i. Explain the meaning of ’shadow prices’ and comment on the usefulness of it and its limitation (5 Marks) ii. Calculate the shadow prices of the constraints (7 Marks)

e

Assuming the company’s position in (c) is maintained for three years with an investment cost of N45,000,000 on the day of the commencement of manufacturing business, using a cost of capital of 15%: i. Can this venture be justified for the period? (4 Marks) ii. What is the breakeven discount factor for this project? (4 Marks)

Suggested answer

a. Concept of linear programming and usefulness Linear programming is a mathematical method for determining a way to achieve the best outcome (such as maximum profit or lowest cost) subject to a number of limiting factors (constraints). A linear programming problem involves maximising or minimising a linear function (the objective function) subject to linear constraints. Both the constraints and the “best outcome” are represented as linear relationships. What constitutes the best outcome depends on the objective. The equation constructed to represent the best outcome is known as the objective function. Uses of linear programming (LP)

• Budgeting: In preparing budget, one of the first steps is the identification of the key (limiting) factor. When there is more than one limiting factor, LP can be used to identify the most profitable use of resources.

• Capital budgeting: When we have multi-period capital rationing, LP can be used to optimally allocate the available funds among the competing projects.

• Transfer pricing: In a divisionalised organisation, LP can be used to compute optimal transfer price between divisions when the supplying division does not have sufficient capacity to met all the demands placed upon it.

• Calculating relevant costs: The relevant cost of a scarce resource is calculated as acquisition cost of the resource plus opportunity cost. When more than one scarce resource exist, LP can be used to establish the opportunity cost (Shadow price).

• Maximum payment for the supply of additional scarce resources: If labour is an effective limiting factor, for example, the maximum overtime premium to pay per additional hour is the shadow price which can be determined using LP.

• Control: LP is also useful in the analysis of variances. For example, adverse material usage variances can be indication of material wastage. Such variances 68 should be valued at the standard cost of the material plus the opportunity cost of the loss of one scarce unit of material. LP can be used to determine the opportunity cost.

b. Computation of unit selling price and associated unit profit of the two products. Biggis N Smallis N Material 250 150 Labour costs: Machine time 60 30 Processing 40 50 Overhead cost 30 40 Total costs 380 270 Profit per unit 76 54 Selling price per unit 456 324

c. ADVICE ON THE OUTPUT TO BE PRODUCED TO MAXIMISE TOTAL PROFIT STEP 1 –DETERMINATION OF LIMITING FACTOR Materials needed to produce 200,000 units of Biggis & 100,000 units of Smallis BIGGIS 5kg x 200,000 1,000,000 SMALLIS 3kg x 100,000 300,000 Total Required 1,300,000 Available Material 1,800,000 Conclusion: Materials are not limiting factor since available resources exceed resources needed to meet production levels. Machine time needed to produce 200,000 units of Biggis and 100,000 units of Smallis. 69 BIGGIS 4hrs x 200,000 800,000 SMALLIS 2hrs x 100,000 200,000 Total Required 1,000,000 Available Hours 800,000 Conclusion: Machine time is a limiting factor since hours available are less than the hours needed to meet production levels. Other processing time needed to produce 200,00 units of Biggs and 100,000 units of smallis: BIGGIS 4hrs x 200,000 800,000 SMALLIS 5hrs x 100,000 500,000 Total Required 1,300,000 0 Available Hours 1,400,000 Conclusion: Other processing time is not a limiting factor since hours available exceeds hours needed to meet production levels. STEP 2 – DETERMINATION OF PRIORITY OF PRODUCTION PLAN Biggis Smallis N N Selling price 456 324 Total variable costs (350) (230) Contribution per unit 106 94 Machine time per unit 4 2 Contribution per machine time 26.5 47 Ranking 2nd 1st PRODUCT UNITS HOURS USED HOURS LEFT SMALLIS 100,000 200,000 600,000 BIGGIS 150,000 600,000 - 70 Comment Hence, the optimal production plan for NTAMS Manufacturing Company Ltd is to produce 100,000 units of Smallis and 150,000 units of Biggis.

(d) SHADOW PRICE MEANING The shadow cost of a binding constraint is the amount by which the objective function decreases (or increases) as a result of availability of one unit less or more of the scarce resource. The solutions to the dual problem of the primal problem give the shadow costs (prices), hence the alternative term dual costs (prices). USEFULNESS OF SHADOW PRICES

• Can be used to determine the relevant cost of a scarce resource

• Useful in setting transfer price

• Useful in setting transfer price

• It assists in determining opportunity cost

• Can be used in allocating funds to projects when there is multi-period capital rationing. The major limitation of shadow price is that it is valid for a limited range of output. For example, if labour hour is the limiting factor, the shadow price will tend to zero as more labour hours are supplied. 71 CALCULATION OF SHADOW PRICE OF THE CONSTRAINTS Shadow price only exists for binding resources – hence shadow price will only exist for machine time. If one (1) additional machine time is available, total machine time will be 800,001 Total units of Biggis to be produced wil l be 150,000.25 units (600,001/4) New Total contribution will be (100,000 x 94) + (150,000.25 x 106) = 25,300,026.50 Previous total contribution was (100,000 x 94) + (150,000 x 106) = 25,300,000 Increase in contribution = 25,300,026.50 – 25,300,000 = 26.50 Alternative solution Candidates may reduce the available machine time by 1 hour. If one machine hour is reduced Total units of Biggis =149,999.75 units N New contribution (100,000 x 94 + 149,999.75 x 106) = 25, 299,973.5 Old contribution 25,300,000 Shadow price (reduction in contribution) (26.50) Shadow price = N26.50k

ei) NPV (Discount Factor 15%) = 2.283 Total contribution = 25,300,000 (2.283) = 57,759,900 Total Outflow = 45,000,000 = 45,000.000 NPV = N12,759,000 Yes, the project’s NPV is positive and therefore worthwhile.

ii) If a discount factor = 35% Total contribution = 25.300,000 x 1.696 = N42,908,800 Total Outflow = N 45,000,000 NPV at 35% = (N2,091,200) IRR = a + ( BA

- A) (b – a) 72 a = Positive NPV discount rate A = Positive NPV b = Negative NPV discount rate B = Negative NPV = 15% + ( 200,091,2000,759,12 000,759,12 \+ ) (35% – 15%) = 15% + ( 000,759,12 100,851,14 ) (20%) = 15% + 17.18% = 32.18%

Examiner’s report The question tests students’ understanding of resource allocation using contribution per limiting factor. It was attempted by the majority of the candidates being a compulsory question. The performance was below average. The major pitfall was the lack of understanding in the subject area and the conditions that must be satisfied before the linear programming is applied. Candidates are advised to read the ICAN study text when preparing for future examination of the Institute.

Marking guide Mark Total a. Definition of linear programming 1 Explanation of linear programming 1 Usefulness (3 points at 1 mark per point) 3 5 b. Selling Price (20 ticks at ¼ mark per tick) 5 c. Advice on the optimal output 10 d. Shadow Price/usefulness/limitation 5 Shadow price computations 7 12 e. Investment analysis - NPV 4 Calculation of IRR 4 8 40 73

SECTION B

Source: ICAN Pathfinder, Skills Level Examination, Performance Management, May 2021, Question 1
2
Theory question 2Section B
20 marks

PQR Plc is preparing its budgets for next year. It has already prepared forecasts of demand levels for its product range. These are as follows: Forecast 1 Forecast 2 Price Quantity Price Quantity ₦ ₦ Product A 10.00 500 15.00 350 Product B 20.00 800 25.00 700 Product C 30.00 2,200 40.00 1,000 57 You are to assume that only one of either forecast 1 or forecast 2 would be accepted. The expected variable unit costs of each product are as follows: Product A Product B Product C ₦ ₦ ₦ Direct materials (50k per kg) 2.00 3.50 7.00 Direct labour 3.00 5.00 7.40 Variable overhead 1.50 2.50 3.70 6.50 11.00 18.10 General fixed costs are budgeted as ₦20,000 for the year and no specific fixed costs are expected for any product. All three products use the same direct material which is expected to be limited in supply to a maximum of 22,020 kgs in the budget year. Required:

a

Recommend, with supporting calculations, whether forecast 1 or forecast 2 should be adopted for the budget period.

11 marks
b

Prepare a report, addressed to the managing director, to explain the budget preparation process, with particular reference to: i. The principal budget factor (3 Marks) ii. The budget manual (3 Marks) iii. The role of the budget committee (3 Marks)

Suggested answer

(a) Materials supply is a limiting factor for forecast 1, but not for forecast 2. Forecast 1 Product A Product B Product C ₦ ₦ ₦ Sales price per unit 10.00 20.00 30.00 Variable cost per unit 6.50 11.00 18.10 Contribution 3.50 9.00 11.90 Contribution per kg of material 0.88 1.29 0.85 Ranking 2nd 1st 3rd Optimal production plan for forecast 1 Units Contribution kg of material ₦ Product B 800 5,600 7,200 Product A 500 2,000 1,750 Product C 1,030 14,420 12,257 Total contribution 22,020 21,207 Optimal Production Plan for forecast 2 Product A Product B Product C Total ₦per unit ₦ per unit ₦ per unit Sales price 15.00 25.00 40.00 Variable-cost 6.50 11.00 18.10 Contribution 8.50 14.00 21.90 Sales volume (units) 350 700 1,000 Total contribution ₦2,975 ₦9,800 ₦21,900 ₦34,675 74 Recommendation: Forecast 2 should be adopted for the budget period. It produces a contribution of ₦34,675 which is ₦13,468 higher than the contribution for forecast 1.

(b) REPORT To: The Managing Director From: The Finance Manager Subject: Budget Preparation Process Date: 5 May 2021

1. INTRODUCTION In line with the request of the management of our company, PQR Plc (“PQR” or “the Company”) kindly see below the detailed discussion on some of the key issues in the budget preparation process.

2. PRINCIPAL BUDGET FACTOR The principal budget factor or limiting factor or key budget factor is a factor, which at any time is an overriding planning limitation on the activities of the organisation. Examples of principal budget factors include: staffing limitations, scarcity of materials and other logistics, limited financial resources, low sales demand, limited storage facilities, etc.

3. BUDGET MANUAL The budget manual sets out the budget guidelines which are budgeting instructions, that the Budget Committee gives to guide departmental heads involved in the preparation of the budget so that they follow a particular goal, objective, technique, trend or method of estimating the income and expenditure variables.

4. ROLE OF THE BUDGET COMMITTEE The Budget Committee is made up of members of senior management that oversees all budgetary matters. A typical budget committee includes the chief executive officer, heads of strategic business units and the chief finance officer. The committee sets or approves the overall budget goals for the organisation, and its major business units, 75 directs and coordinates budget preparation, approves the final budget, monitors operations as the year unfolds, and reviews the operating results at the end of the period. The budget committee also approves major revisions of the budget during the period. This committee usually consists of sectional or departmental managers and is usually serviced by the Budget Officer who normally is the finance officer. Apart from the above, the functions of the committee may include the following: ➢ Determine budget policy guidelines and selecting budget policies compatible with organisational goals and objectives; ➢ Establishing the budget timetable; ➢ Review budget estimates submitted by sectional heads; ➢ Facilitate the co-ordination of the budgets; ➢ Suggest amendments to budgets and revising budget estimates when necessary; ➢ Approve budgets after amendments; ➢ Facilitate the generation of budgetary control reports; ➢ Analysing budget reports and recommending changes; ➢ Examine variances, recommend investigation of variances and recommend solutions to remedy off-standard performance; and ➢ Advise top management on all matters concerning the budget.

Examiner’s report The question examines candidates on optimal mix of production and some concepts associated with the budgeting process. Majority of the candidates attempted the question, the performance was average. The main pitfall is inability of the students to identify the quantity of the limiting factor. Candidates are encouraged to read the Institute’s study text when preparing for the examination of the Institute.

Marking guide Mark Total a. Forecast to be Adopted/Computation 11 b. i) Principal budget factor 3 ii) Budget manual 3 iii) Role of budget committee 3 9 20 76

Source: ICAN Pathfinder, Skills Level Examination, Performance Management, May 2021, Question 2
3
Theory question 3Section B
20 marks
a 8b 8c 4

Some time ago, Robert launched a new product. At first, sales were good but now the figures are causing concern. Robert wants a more accurate sales forecast to produce detailed cash forecasts. Since there are some seasonality present in the raw data, the series for sales shown below represents the underlying trend based on an averaging process: 58 Year Quarter Trend point Sales (Cartons) x y 2016 3rd 1 10,000 2016 4th 2 10,760 2017 1st 3 10,920 2017 2nd 4 11,000 2017 3rd 5 11,050 2017 4th 6 11,080 2018 1st 7 11,085 2018 2nd 8 11,095 2018 3rd 9 11,120 2018 4th 10 11,130 On average, quarters 1 and 3 are 5% and 6% respectively above trend whilst quarters 2 and 4 are respectively 2% and 9% below trend. Some preliminary calculations on the above ten observations have been carried out and the results are summarised below: Results from ten periods’ observations: Linear regression y = a + bx Slope = 82.67 Intercept = 10,472.33 Coefficient of determination = 0.535 It is required to make forecasts of sales for quarters 3 and 4 in 2019 and for quarters 1 and 2 in 2020 but there is some discussion on whether the ten-period data shown above are suitable for forecasting or whether only the last five periods would provide a better basis for forecasting. Linear analysis of the last five periods only gives the following intermediate results: Results of last five periods’ observations: Σy = 555.10 Σx2 = 330 Σy2 = 61,627.40 Σxy = 4,442.15 Note: the y values have been scaled down by 100 times for ease of calculation. Required:

a

59 Probability No of pupils joining late 0.2 80 0.3 30 0.5 52 Forecast the sales of the four quarters required using the ten- period observations results.

8 marks
b

Prepare similar forecasts based on the last five periods’ observations

8 marks
c

Explain which forecasting bases produce the better forecast

4 marks
Suggested answer

a) Year Quarter Trend point Sales trend (cartons) x y = a + bx 2019 3 13 10,472.33 + (82.67 × 13) = 11,547 2019 4 14 10,472.33 + (82.67 × 14) = 11,630 2020 1 15 10,472.33 + (82.67 × 15) = 11,712 2020 2 16 10,472.33 + (82.67 × 16) = 11,795 The seasonally adjusted forecasts are therefore as follows: Year Quarter Seasonally adjusted forecast sales (cartons) 2019 3 11,547 × 1.06 = 12,240 2019 4 11,630 × 0.91 = 10,583 2020 1 11,712 × 1.05 = 12,298 2020 2 11,795 × 0.98 = 11,559

b) We need to calculate the regression line of the last five periods' observations. This line is y = a + bx where b = n xy− x y n x2− x 2 and a = yn − 𝑏 x n So b = 5 × 4,442.15 − (40 × 555.1) 5 × 330 − 40 × 40 = 6.75 50 = 0.135 a = 555.1 5 − 0.135 × 40 5 = 111.02 − 1.08 = 109.94 We need to multiply the a and b values back up by 100 to compensate for the fact that the y values were scaled down by 100 before the sigma calculations were carried out. So the regression line is y = 10,994 + 13.5x 77 Year Quarter Trend point Sales trend (cartons) x y = a + bx 2019 3 13 10,994 + (13.5 × 13) = 11,169.5 2019 4 14 10,994 + (13.5 × 14) = 11,183.0 2020 1 15 10,994 +(13.5 × 15) = 11,196.5 2020 2 16 10,994 + (13.5 × 16) = 11,210.0 The seasonally adjusted forecasts are therefore as follows: Year Quarter Seasonally adjusted forecast sales (cartons) 2019 3 11,169.5 × 1.06 = 11,840 2019 4 11,183.0 × 0.91 = 10,177 2020 1 11,196.5 × 1.05 = 11,756 2020 2 11,210.0 × 0.98 = 10,986

c) One common method of deciding on which forecasting basis produces the better result is to compare the coefficients of determination. With ten periods' observations we are told that r2 = 0.535. With five periods' observations we have to calculate the coefficient of determination from the equation given in the tables provided. r2 = n xy − x y 2 n x2 − x 2 n 𝑦2 − ( 𝑦)2 = 5 × 4,442.15 − 40 × 555.1 2 5 × 330 − 40 × 40 5 × 61,627.4 − (555.1 × 555.1) = 6.752 50 × 0.99 = 0.92 Prima facie the forecasting method, using five periods' observations is much better than the other using ten periods, since the coefficient of determination of the former is 0.92 compared with 0.535 for the latter. We can explain 92% of the variations in sales by the passage of time using the former method, but can explain only 53.5% of the variations in sales using the latter method. 78

Examiner’s report The question tests candidates’ knowledge of regression analysis in forecasting. Few candidates attempted the question, the performance was average. The major pitfall of the candidates was inability to apply seasonal variation of the trend to the forecast. Candidates are encouraged to read the Institute’s study text when preparing for future examination of the Institute.

Marking guide Mark Total a. Forecast of 4 Quarters using 10-period observation 8 b. Forecast of 4 Quarters using 5-period observation 8 c. Commenting of better of forecast:

- Coefficient of determination formulae 1 - Substituting of figures into the formulae 1 - Comparation of two forecast figures 1 - Decision 1 4 20

Source: ICAN Pathfinder, Skills Level Examination, Performance Management, May 2021, Question 3
4
Theory question 4Section B
20 marks
a 6b 4c 6d 4

Adrac Community School was founded by Adrac Community Resident Association of Garki, Abuja, Nigeria. The school is being supervised by a board of governors made up of selected experienced members of the community. The school is not allowed to charge the pupils any fee as it is a community project donated to assist members of the community. Adrac Community Residents Association pays the school ₦21,000 for each child registered at the beginning of the school year, which is September 1, and ₦18,000 for any child joining the school part-way through the year. The school does not have to refund the money to the association if a child leaves the school part-way through the year. The number of pupils registered at the school on September 1, 2019 is 720, which is 10% lower than the previous year. Based on past experience, the probabilities for the number of pupils starting the school part-way through the year is as follows: The school’s headmistress normally prepares annual budget for consideration of the board of governors. Since she is not too comfortable with figures, she does not understand how to use the probability distribution provided for her annual budget. Therefore, she just used simple average for her calculation of number of pupils expected to join late. The revenue budget for 2019/2020 submitted by the headmistress is as follows: 60 Total income N’000 Pupils registered at beginning of school year 720 ₦21,000 15,120 Average expected number of new joiners 54 N18,000 972 16,092 The headmistress uses incremental budgeting to budget for her expenditure, taking actual expenditure for the previous year as a starting point and simply adjusting it for inflation, as shown below. Note Actual cost for Inflationary Budgeted cost y/e 30 June 2019 adjustment y/e 30 June 2020 N’000 N’000 Repairs and maintenance 1 880 +3% 906.4 Salaries 2 12,400 +2% 12,648 Capital expenditure 3 1,300 +6% 1,378 Total budgeted expenditure 14,932.4 Budget surplus 1,159.6 Notes i. N600,000 of the costs for the year ended 30 June 2019 related to standard maintenance checks and repairs that have to be carried out by the school every year in order to comply with the local government health and safety standards. These are expected to increase by 3% in the coming year. In the year ended 30 June 2019, N280,000 was also spent on redecorating some of the classrooms. There will be no redecoration in the coming year. ii. One teacher earning a salary of N520,000 left the school on 30 June 2019 and there are no plans to replace her. However, a 2% pay rise will be given to all staff with effect from 1 December 2019. iii. The full N1,300,000 actual costs for the year ended 30 June 2019 related to improvements made to the school building. This year, the canteen is going to be substantially improved, although the extent of the improvements and level of service to be offered to pupils is still under discussion. There is a 0·7 probability that the cost will be N1,450,000 and a 0·3 probability that it will be N800,000. These costs must be paid in full before the end of the year ending 30 June 2020. The school’s board of governors, who review the budget, are concerned that the budget surplus has been calculated incorrectly. They believe that it should have been calculated using expected income, based on the probabilities provided, and using expected 61 Pupils Rate per pupil expenditure, based on the information provided in notes i to iii. They believe that incremental budgeting is not a reliable tool for budget setting in the school since, for the last three years, there have been shortfalls of cash despite a budget surplus being predicted. Since the school has no other source of funding available to it, these shortfalls have had serious consequences, such as the closure of the school kitchen for a considerable period in the last school year, meaning that no meals were available to pupils. This is thought to have been the cause of the 10% fall in the number of pupils registered at the school on 1 September 2019. Required:

a

Redraft the school’s budget for the year ending 30 June 2020 based on the views of the board of governors.

6 marks
b

Discuss the advantages and disadvantages of using incremental budgeting

4 marks
c

Discuss the THREE main steps involved in preparing a zero-based budget

6 marks
d

Discuss the extent to which zero-based budgeting could be used by Adrac Community School to improve the budgeting process

4 marks
Suggested answer

ADRAC COMMUNITY SCHOOL

a. REDRAFTING THE BUDGET FOR THE YEAR ENDED 30 JUNE 2020 BUDGETED INCOME N’000 Pupils Rate/Pupil N Pupils registered at the beginning of school year 720 21,000 15, 120 Average Expected Number of New Joiners 51 18,000 918 16,038 79 BUDGETED EXPENDITURE Actual cost for the year Ended 30-June-2019 Budget Cost for the year Ended 30-June-2020 N’000 N’000 Repairs and Maintenance Note 1 600 3% 618 Salary Note 2 11,880 2% 12,019 Improvement of canteen Note 3 1,300 1,255 13,892 Budgeted Surplus/(Deficit) 2,146

Note 1: Repairs & maintenance 600,000 (1.03) = 618,000

Note 2: Salaries (12,400,000 – 520,000) (1 + 0.02 x 7/12) = 12,019,000

Note 3: Improvement of canteen Estimated cost Pro Expected cost 1,450,000 0.7 1,015,000 800,000 0.3 240,000 1,255,000

(b) Advantages of Incremental Budgeting – Incremental budgeting is very easy to prepare. This makes it possible for a person without any accounting training to build a budget. – Incremental budgeting is also very quick to comprehend compared to other budgeting methods. – The information required to complete it is also usually readily available Disadvantages of Incremental Budgeting – There is no incentive to eliminate wasteful or unnecessary spending from the budget; – It encourages more waste (or budget slack) because managers will try to spend up to their budget limit so that budget for next financial year will not reduce. – It increases allocated cost irrespective of performance. 80 Inflationary Adjustment

(c) STEPS IN PREPARING ZERO-BASED BUDGET Zero-based Budget is prepared as follows:

(i) A decision must be taken to provide for a minimum level of operation. This means deciding for each basic operation whether or not to perform the operation. (ii) Having decided on a basic level of operations, a basic expenditure budget can be prepared. (iii) The next step is to consider each incremental decision package and decide whether additional operation is justified. An incremental decision package is justified if the expected benefits exceed the estimated costs.

(d) EXTENT TO WHICH ZERO-BASED BUDGET CAN BE USED BY ADRAC TO IMPROVE BUDGETING PROCESS

i. It can be used to help lower costs by avoiding blanket increases or decreases to a prior period's budget. ii. It can be used to help in efficient allocation of resources (department-wise) as it does not look at the historical numbers but looks at the actual numbers iii. It leads to the identification of opportunities and more cost- effective ways of doing things by removing all the unproductive or redundant activities. iv. Since every line item is to be justified, zero-based budget overcomes the weakness of incremental budgeting of budget inflation. v. It also improves coordination and communication within the department and motivates employees by involving them in decision- making.

Examiner’s report The question tests candidates’ understanding of Incremental Budget and Zero Based Budget. Majority of the candidates attempted the question. Candidates performance was above average. The candidates are advised to read the Institute’s study text when preparing for the Institute’s examination in future. 81

Marking guide Mark Total a. Redrafted budget 6 b. i) Advantages (Any 2 at 1 mark) 2

ii) Disadvantages (Any 2 at 1 mark) 2 4 c. 3 steps at 2 marks 6 d. Extent of use of ZBB by Adrac (Any 2 points at 2 marks each) 4 20

Source: ICAN Pathfinder, Skills Level Examination, Performance Management, May 2021, Question 4
5
Theory question 5Section B
20 marks
a 17b 3

A national boutique chain sells a wide range of high quality customised fashion goods. One particular outfit is bought at ₦8,000 and sold at ₦13,000. Mean holding costs per season per outfit work out at ₦500 and it costs ₦80,000 to order and receive goods in stock. The manufacturers require orders in advance and once a batch has been made it is not possible to place a repeat order. Further, it is not possible for delivery to be staggered over the fashion season. When a customer buys an outfit that requires adjustments, any alterations or adjustments are made and she collects the outfit a day or so later. Generally, if an outfit is out of stock at one boutique it can be readily obtained from another branch, usually in a matter of hours. However, if the chain as a whole runs out of an item, then not only is the profit not earned, but the ₦2,000 or so profit that comes from the extras that customers buy is also lost. If the chain has excess purchase for a season then it is expected that the chain will be able to dispose of the surplus outfits at ₦5,000 each. 62 The pattern of past sales of a comparable outfit show the following probability distribution for the chain as a whole: Outfits Probability sold 1,100 0.30 1,200 0.40 1,300 0.20 1,400 0.10 The problem facing the management accountant of the chain is to decide how many outfits to order for the season ahead, in order to maximise expected profit, bearing in mind the penalties for over and under ordering. You are required to:

a

Determine the number of outfits to order to maximise expected profits.

17 marks
b

Compare and contrast the model that you have developed with the classical economic order model.

3 marks
Suggested answer

a) Unit contribution ₦13,000 – (8,000 + 500) = ₦4,500 Unit loss when surplus sold ₦8,500 – 5,000 = ₦3,500 Unit penalty when demand not satisfied ₦2,000 per outfit not sold Probability of sales levels Sales Probability 1,100 0.3 1,200 0.4 1,300 0.2 1,400 0.1 Contribution calculations (1,100 units purchased) Demand contribution ₦ 1,100 1,100 × ₦4,500 = 4,950,000 1,200 1,100 × ₦4,500 – 100 × ₦2,000 = 4,750,000 1,300 1,100 × ₦4,500 – 200 × ₦2,000 = 4,550,000 1,400 1,100 × ₦4,500 – 300 × ₦2,000 = 4,350,000 (1,200 units purchased) Demand Contribution ₦ 1,100 1,100 × ₦4,500 – 100 × ₦3,500 = 4,600,000 1,200 1,200 × ₦4,500 = 5,400,000 1,300 1,200 × ₦4,500 – 100 × ₦2,000 = 5,200,000 1,400 1,200 × ₦4,500 – 200 × ₦2,000 = 5,000,000 82 (1,300 units purchased) Demand Contribution ₦ 1,100 1,100 × ₦4,500 – 200 × ₦3,500 = 4,250,000 1,200 1,200 × ₦4,500 – 100 × ₦3,500 = 5,050,000 1,300 1,300 × ₦4,500 = 5,850,000 1,400 1,300 × ₦4,500 – 100 × ₦2,000 = 5,650,000 (1,400 units purchased) Demand Contribution ₦ 1,100 1,100 × ₦4,500 – 300 × ₦3,500 = 3,900,000 1,200 1,200 × ₦4,500 – 200 × ₦3,500 = 4,700,000 1,300 1,300 × ₦4,500 – 100 × ₦3,500 = 5,500,000 1,400 1,400 × ₦4,500 = 6,300,000 Summary of outcomes Probability Order quantity Demand 1,100 1,200 1,300 1,400 0.3 0.4 0.2 0.1 Application of probability on the Pay off Matrix State of Nature (Sales) Decision 0.3 0.4 0.2 0.1 Alternatives 1,100 1,200 1,300 1,400 Max 1100 1,485,000 1,900,000 910,000 435,000 1,900,000 1200 1,380,000 2,160,000 1,040,000 500,000 2,160,000 1300 1,275,000 2,020,000 1,170,000 565,000 2,020,000 1400 1,170,000 1,880,000 1,100,000 630,000 1,880,000 :. On the basis of the expected contribution the number of outfits to order is 1,200 units.

Note: The order/receipt costs of ₦80,000 are constant throughout and therefore have been ignored. Expected contribution ₦000 1,100 4,950,000 4,750,000 4,550,000 4,350,000 4,730 1,200 4,600,000 5,400,000 5,200,000 5,000,000 5,080 1,300 4,250,000 5,050,000 5,850,000 5,650,000 5,030 1,400 3,900,000 4,700,000 5,500,000 6,300,000 4,780 83

b) The basic EOQ model assumes a known demand per period e.g., per year and the aim is then to find how often, and therefore how much, to order at a time so as to minimise total costs, each order arriving when the stock level is zero so that there are no ’lost sales’ and no surplus stock. (It has to be said that the basic EOQ model is rarely, if ever applicable in this simple form in a real-life case, although refinements such as variable demand can be built into the model). By contrast, in the model calculated, demand is not known with certainty but is assumed to conform to the probability distribution given. Since the whole of the season’s stock has to be ordered in a single batch at the start of the season, both overstocking and under stocking are possible, with resultant loss of profit contribution.

Examiner’s report The question tests the candidates’ understanding of decision making under uncertainty. Few students attempted the question and performance was below average. The major pitfall was lack of understanding in identifying possible scenarios for decision making. Candidates are advised to study the Institute’s text for future Institute’s study examination.

Marking guide Mark Total a. i) Number of outfits to maximise profits (32 ticks at ½ mark) 16 ii) Decision 1 17 b. Compare models 1½ Contrast models 1½ 3 20

Source: ICAN Pathfinder, Skills Level Examination, Performance Management, May 2021, Question 5
6
Theory question 6Section B
20 marks
a 6b 8

Chukwukah Nigeria Limited manufactures three products, JEL, JET and JAL. Demand for products JEL and JET is relatively elastic whilst demand for product JAL is relatively inelastic. Each product uses the same materials and the same type of direct labour but in different quantities. For many years, the company has been using full absorption costing and absorbing overheads on the basis of direct labour hours. Selling prices are then determined using cost plus pricing. This is common in the company’s industry with most competitors applying a standard mark-up. Budgeted production and sales volumes for JEL, JET and JAL for the next year are 25,000, 20,000 and 27,600 units respectively. The budgeted direct costs of the three products are shown below: Product JEL JET JAL N per unit N per unit N per unit Direct materials 250 280 220 Direct labour (N120 per hour) 300 360 240 63 In the coming year, Chukwukah also expects to incur indirect production costs of N6,887,000, which are analysed as follows: Cost pools N’000 Cost drivers Machine set up costs 1,400 Number of batches Material ordering costs 1,580 Number of purchase orders Machine running costs 2,100 Number of machine hours General facility costs 1,807 Number of machine hours 6,887 The following additional data relates to each product: Product JEL JET JAL Batch size (units) 500 800 400 No of purchase orders per batch 4 5 4 Machine hours per unit 1.5 1.25 1.4 The management of Chukwukah Nigeria Limited wants to boost sales revenue in order to increase profits but its capacity to do this is limited because of its use of cost plus pricing and the application of standard mark-up. The management accountant has suggested using activity based costing (ABC) instead of full absorption costing, since this will alter the cost of the products and may therefore enable a different price to be charged. Required:

a

Calculate the budgeted full production cost per unit of each product using absorption costing. All workings should be to two decimal places.

6 marks
b

Calculate the budgeted full production cost per unit of each product using activity based costing. All workings should be to two decimal places.

8 marks
c

Discuss the impact on the selling prices and the sales volumes of each product which a change to activity based costing would be expected to bring about. (6 Marks) 64 Formulae Learning curve Y = axb Where Y = cumulative average time per unit to produce x units a = the time taken for the first unit of output x = the cumulative number of units produced b = the index of learning (log LR/log2) LR = the learning rate as a decimal Demand curve P = a – bQ = b change in price change in quantity a = price when Q = 0 MR = a – 2bQ The linear regression equation of Y on X is given by: Y= 𝑎 + 𝑏𝑋 where b= 𝑛 𝑋𝑌− ( 𝑋)( 𝑌) 𝑛 𝑋2− 𝑋 2 a = 𝑦𝑛 − 𝑏 𝑥 𝑛 Coefficient of determination (r2) r2 = 𝑛 𝑋𝑌 − 𝑥 𝑌1 2 (𝑛 𝑋2− 𝑋 2 (𝑛 𝑦2− 𝑋 2 65 The Miller-Orr Model 𝑆𝑝𝑟𝑒𝑎𝑑 =3 x 134x Transaction Cost x Variance of Cash flows 3 Interest rate as a proportion Annuity Table Present value of an annuity of 1 i.e. 1 - (1 + r)-n r Where r = discount rate n = number of periods Discount rate (r) Periods (n) 1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 1 0·990 0·980 0·971 0·962 0·952 0·943 0·935 0·926 0·917 0·909 1 2 1·970 1·942 1·913 1·886 1·859 1·833 1·808 1·783 1·759 1·736 2 3 2·941 2·884 2·829 2·775 2·723 2·673 2·624 2·577 2·531 2.487 3 4 3·902 3·808 3.717 3·630 3.546 3.465 3·387 3·312 3·240 3·170 4 5 4·853 4·713 4·580 4·452 4·329 4·212 4·100 3·993 3.890 3·791 5 6 5·795 5·601 5·417 5·242 5·076 4·917 4·767 4·623 4.486 4·355 6 7 6·728 6.472 6·230 6·002 5·786 5·582 5·389 5·206 5·033 4·868 7 8 7·652 7·325 7·020 6·733 6·463 6·210 5·971 5·747 5·535 5·335 8 9 8·566 8·162 7·786 7.435 7·108 6·802 6·515 6·247 5·995 5·759 9 10 9·471 8·983 8·530 8·111 7·722 7·360 7·024 6·710 6.418 6·145 10 11 10·368 9·787 9·253 8·760 8·306 7·887 7.499 7·139 6·805 6.495 11 12 11·255 10·575 9·954 9·385 8·863 8·384 7·943 7·536 7'161 6·814 12 13 12·134 11·348 10·635 9·986 9·394 8·853 8·358 7·904 7·487 7·103 13 14 13·004 12·106 11·296 10·563 9·899 9·295 8·745 8·244 7·786 7·367 14 15 13·865 12·849 11·938 11·118 10·380 9·712 9·108 8·559 8·061 7·606 15 (n) 11% 12% 13% 14% 15% 16% 17% 18% 19% 20% 1 0·901 0·893 0·885 0·877 0·870 0·862 0·855 0·847 0·840 0·833 1 2 1·713 1·690 1·668 1·647 1·626 1·605 1·585 1·566 1·547 1·528 2 3 2.444 2.402 2·361 2·322 2·283 2·246 2·210 2·174 2·140 2·106 3 4 3·102 3·037 2·974 2·914 2·855 2·798 2·743 2.690 2·639 2.589 4 5 3·696 3·605 3·517 3·433 3·352 3·274 3·199 3·127 3·058 2·991 5 6 4·231 4·111 3·998 3·889 3·784 3·685 3·589 3.498 3.410 3·326 6 7 4·712 4·564 4.423 4·288 4·160 4·039 3·922 3·812 3·706 3·605 7 8 5·146 4·968 4.799 4·639 4.487 4·344 4·207 4·078 3·954 3·837 8 9 5·537 5·328 5·132 4·946 4·772 4·607 4.451 4·303 4·163 4·031 9 10 5·889 5·650 5.426 5·216 5·019 4·833 4·659 4.494 4·339 4·192 10 11 6·207 5·938 5·687 5.453 5·234 5·029 4·836 4·656 4.486 4·327 11 12 6·492 6·194 5·918 5·660 5·421 5·197 4·988 4·793 4·611 4.439 12 13 6·750 6.424 6·122 5·842 5·583 5·342 5·118 4·910 4·715 4·533 13 14 6·982 6·628 6·302 6·002 5·724 5.468 5·229 5·008 4·802 4·611 14 15 7·191 6·811 6.462 6·142 5·847 5·575 5·324 5·092 4·876 4·675 15 66 67

Suggested answer

CHUKWUKAH NIGERIA LIMITED

(a) Full budgeted production cost per unit using absorption costing Product Jel Jet Jal Total Budgeted annual production (units) 25,000 20,000 27,600 Labour hours per unit 2·5 3 2 Total labour hours 62,500 60,000 55,200 177,700 Overhead absorption rate = N6,887,000/177,700 = N38·76 per hour. 84 Product Jel Jet Jal N per unit N per unit N per unit Direct materials 250.00 280.00 220.00 Direct labour 300.00 360.00 240.00 Overhead (N38·76 x 2·5/3/2) 96.90 116.28 77.52 Full cost per unit 646.90 756.28 537.52

(b) Full budgeted production cost per unit using activity based costing Product Jel Jet Jal Total Budgeted annual production (units) 25,000 20,000 27,600 Batch size 500 800 400 Number of batches (i.e. set ups) 50 25 69 144 Number of purchase orders per batch 4 5 4 Total number of orders 200 125 276 601 Machine hours per unit 1·5 1·25 1·4 Total machine hours 37,500 25,000 38,640 101,140 Cost driver rates: Cost per machine set up N1,400,000/144 = N9,722.22 Cost per order N1,580,000/601 = N2,628.95 Machine running cost = ₦21,000,000/101140 = ₦20.76 General facility cost = 1,807,000/101140 = ₦17.87 Allocation of overheads to each product: Product Jel Jet Jal Total N N N N Machine set up costs 486,111 243,055 670,833 1,400,000 Material ordering costs 525,790 328,619 725,591 1,580,000 Machine running cost 778,624 519,082 802,294 2,100,000 General facility cost 669,987 446,658 690,355 1,807,000 Total 2,460,512 1,537,414 2,889,073 6,887,000 85 Quantity Produced 25,000 20,000 27,600 Overhead cost per unit N98.42 N76.87 N104.68 Allocation of overheads to each product Total cost per unit: N per unit N per unit N per unit Direct materials 250.00 280.00 220.00 Direct labour 300.00 360.00 240.00 Overhead 98.42 76.87 104.68 ABC cost per unit 648.42 716.87 564.68

c. The company prices product on the basis of cost plus pricing model. The application of ABC model will impact the selling price and sales volume of the products as follows: Jel: The demand is elastic. As a result of ABC model, cost will increase from N646.90 to N648.42 meaning increase in selling price and reduction in sales volume Jet: The demand is elastic. As a result pf ABC method, cost will decrease from N756.28 to N716.87 meaning that there will be a decrease in selling price and increase in sales volume. JAL: The demand is inelastic meaning change in price will not affect the quantity demanded. Hence, even though the cost increased from N537.52 to N564.68, selling price will increase but will not affect the sales volume.

Examiner’s report The question tests the candidates’ understanding of overhead apportionment using Traditional and Activity Based Costing Method. Majority attempted the question and the performance was average. The major pitfall was the determination of the number of batches involved. Candidates are encouraged to make use of the Institute’s text for future Institute’s examination. 86

Marking guide Mark Total a. Budgeted full cost per unit (12 ticks at ½ mark each tick) 6 b. Budgeted ABC full production cost per unit Cost driver rate (4 ticks at ½ mark each) 2 Production cost per unit (12 ticks at ½ mark each) 6 8 c. Impact of ABC on selling price/sales volume 6 20 87 THE INSTITUTE OF CHARTERED ACCOUNTANTS OF NIGERIA

Source: ICAN Pathfinder, Skills Level Examination, Performance Management, May 2021, Question 6

November 2021 diet

0 objective and 7 theory
Time allowed: 31/4 hours (including 15 minutes reading time).
0 objective7 theory135 theory marks set
No.SectionMarksCovers
Q1Section A (compulsory)30Limiting factor with special order and penalty; outsourcing pros and cons; budget constraint causes.
Q2Section B20Make or buy with discounting, indifference price, non-financial factors.
Q3Section B20TAR and profit-maximising output, advantages over marginal costing.
Q4Section B20Deseasonalise and forecast; participation in budget setting arguments and challenges.
Q5Section C15Expected NPV with three uncertain factors and joint probabilities (NPV itself outside course).
Q6Section C15No-calculation explanation of maximin, maximax, minimax regret, expected value and risk attitudes.
Q7Section C15Alba/Beta transfer price from residual income target; sub-optimality; negotiated v market price.

Theory questions Written questions

1
Theory question 1Section A (compulsory)
30 marks
a 6b 9c 6d 9

Kikelomo Limited manufactures three products K, T and F, using different quantities of the same resources. Budget information per unit is as follows: K T F ₦ ₦ ₦ Market selling price 1,800 2,520 3,000 Direct labour (₦140/hour) 280 560 700 Material A (₦60/kg) 300 240 420 Material B (₦120/kg) 480 720 600 Variable overhead (₦80/hour) 160 320 400 Fixed overhead 240 140 240 Total cost 1,460 1,980 2,360 Profit 340 540 640 Total budgeted sales units 500 800 1,600 The budgeted sales are for the month of June but do not include an order from a major customer to supply 400 units per month of each of the three products, at a discount of ₦200 per unit from the market selling price. During June, the management of Kikelomo Ltd anticipated that there will be a shortage of material B, and that only 17,500 kgs will be available. It is not possible for Kikelomo Ltd to hold inventory of any raw materials, work-in- progress or finished products. Required:

a

State THREE factors which may cause input materials to be a budget constraint and identify steps which may be taken to overcome this constraint.

6 marks
b

Prepare calculations to show production that will maximise Kikelomo Ltd’s profit for June.

9 marks
c

Kikelomo Ltd has now realised that the contract with the major customer does not have to be met in full for any of the three products. The customer will accept whatever Kikelomo is prepared to supply at the contracted 58 prices but they will charge a financial penalty if Kikelomo does not supply them in full in June. Based on this additional information: Calculate: The lowest value of the financial penalty that the major customer would need to insert in the contract to ensure that Kikelomo Ltd meets the order in full in June.

6 marks
d

Now assume that the shortage of material B is expected to continue far beyond June and management of Kikelomo Ltd has decided to outsource the production of some of the products, advise the management of Kikelomo Ltd on the advantages and disadvantages of outsourcing.

9 marks
Suggested answer

a) The availability of materials may be a constraint when formulating the budget.

i) There may be a shortage of supply of materials e.g. where they are Imported and it is known that a bad harvest or political unrest will limit the total quantity available. ii) The company may have a limited quantity of specialist storage space available. For example raw material may require specially humidified storage or special storage container space where it is toxic or dangerous in nature. Such constraints may limit the overall amount of material which can be made available during the budget period. iii) The level of material losses in stores and in the production process may be unacceptably high. This will increase the total input materials required and could lead to a shortfall arising. iv) Seasonal material input v) Surge in demand vi) Storage facility and capacity vii) Transport system to move material viii) Price of related input material for substitute and complementary goods The steps: The company may attempt to minimise the effect of potential shortages by placing forward orders for materials. It may also consider possible substitute materials which are more readily available. Where storage space is a problem, the company may consider the renting of extra storage facilities. It may also wish to negotiate a ’just-in-time’ agreement whereby deliveries of material are guaranteed by suppliers to coincide with the forward production plan. In order to reduce the level of material losses, stores layout and control procedures should be reviewed. In the production process additional focus on the efficiency of machinery and the level of training of the work force should help reduce the level of material losses and hence the total material input required. 69

b) Computation of Production that maximises profit Product K T F N N N Selling Price 1,800 2,520 3,000 Less Variable cost: Direct labour (280) (560) (700) Material A (300) (240) (420) Material B (480) (720) (600) Variable overhead (160) (320) (400) Contribution/Unit 580 680 880 Ranking the products using contribution/kg of material B Kg of material B 4 6 5 Contribution/kg N145 N113.33 N176 Ranking 2nd 3rd 1st Use of material B 3,600kg 3,900kg 10,000kg Optimal Production 900 650 2,000

c) Producing with no special emphasis on special order K T F Contr./Unit N580 N680 N880 Normal Production 500 800 1,600 Unit of material B 4 6 5 2,000 4,800 8,000 = 14,800 Ranking 2nd 3rd 1st Bal. to be used for special Order 700kg 0 2,000kg = 2,700 Units to be produced under special order 175 units 400 units Normal contribution 580 x 500 =290,000 800 x 680 544,000 1,600 x 880 = 1,408,000 = N2,242,000 Special Order 175 x 380 = 66,500 - 400 x 680 = 272,000 N338,500 N356,500 N544,000 N1,680,000 = N2,580,500 70 Producing with Emphasis on Special order Optimal Production (units) 900 650 2,000 N Contribution/unit N580 N680 N880 Total Contribution N522,000 N442,000 N1,760,000 2,724,000 Less Discount N80,000 N80,000 N80,000 (240,000) N442,000 N362,000 N1,680,000 = 2,484,000 Financial Penalty N2,580,500 – N2,484,000 = N 96,500

d) Advantages of outsourcing:

i. It allows each party to focus on core competences. This should lead to improved quality of the final products produced by Alice. In addition, this should lead to improved efficiency in that part of the overall operations. ii. It should lead to improved services provided to customers, leading to an increase in customer satisfaction. This will assist in retaining existing customers and achieving repeat sales. iii. Outsourcing will mean that the amount of capital expenditure is reduced, as the company will no longer be required to invest in the plant and equipment needed to carry out the outsourced activity. iv. It should lead to less incidence of under-utilisation of assets. This will lead to greater efficiency, and will impact positively on a number of important performance measures (e.g. ROA, asset turnover, ROE, etc). v. It is possible, but by no means certain, that an activity can be provided by an outsourcer at lower cost than is possible in-house, as a result of the outsourcer’s ability to specialise. Disadvantages of outsourcing: i. Staff resistance: Members of staff, particularly those currently working in the activity to be outsourced, may be resistant, as they will fear that their jobs will be lost. ii. Loss of critical skill: In the medium to long term, the skills associated with the outsourced activity will be lost to the company. It is probable that replacing such skills could prove to be costly. If an inappropriate activity is outsourced, or the outsourcing initiative is unsuccessful, this could prove to be very costly. Once such skills have been lost, the supplier may seek to increase prices. In such circumstances there would be little option to accept the increased cost, unless an alternative supplier can be identified. 71

iii. Quality of the supplier: The success of an outsourcing initiative will be heavily influenced by the quality of the supplier. It may be difficult to identify a supplier who can provide the correct skills and meet the required specification. iv. Loss of confidential data: When an activity is outsourced, there is a danger that it allows competitors to obtain access to data which otherwise would remain in-house. This may lead to a commercial disadvantage. This is most likely to occur in the case of a product, and competitors may now be able to carry out a tear-down analysis more easily. v. Reputational problems: The most significant potential problem is the damage to reputation which may result if the supplier does not meet the required specification. vi. Outsourcing firm may turn to a competitor vii. Loss of managerial control viii. Failure to meet delivery targets

ix. Selection of vendors may take time and effort

Examiner’s report This is a compulsory question that tests candidates’ knowledge on how to handle limiting factor. Being a compulsory question, it was attempted by almost all the candidates. The candidates recorded an average performance. The pitfall is that most candidates failed to compute the financial penalty that will be expected when Kikelomo Ltd fails to supply the special order in full as well as failure to treat the discount as an attributable variable costs that only applies to the special order. Candidates are encouraged to study the Institute’s study manual when preparing for ICAN examinations. 72

Marking guide Marks a 3 factors that cause material input constraint 3 3 Steps to overcome them 3 6 b - Contribution per unit 1 ½ - Contribution per kg of material B 1 ½ - Ranking 1 ½ - Optimal Production 4 ½ 9 c Computation of lowest value of financial penalty (36 ticks at 16 mark) 6 d Advantages of outsourcing (2 points at 21/2 marks) 5 Disadvantage of outsourcing (2 points at 2 marks) 4 9 30

Source: ICAN Pathfinder, Skills Level Examination, Performance Management, November 2021, Question 1
2
Theory question 2Section B
20 marks
a 10b 5

Divine Grace (DG) Limited currently makes as many units of “Part-2011” as it needs. The company has recently received a bid from another company, KK Plc, for making “Part 2011”. The company will supply 1,000 units of “Part 2011” per year at N100 a unit. The company can begin the supply and continue for five years, after which time DG Limited will not need the part. KK Plc can accommodate any change in DG Limited’s demand for the part and will supply it for N100 regardless of quantity. Ayo Ayuba, the cost accountant, reports the following costs for manufacturing 1,000 units of “Part 2011”. N Direct materials 44,000 Direct production labour 22,000 Variable production overhead 14,000 Depreciation on machine 20,000 Product and process engineering 8,000 Rent 4,000 General overheads 10,000 122,000 59 The following additional information is available: (i) “Part 2011” is made on a machine used exclusively for the production of “Part 2011”. The machine was acquired on January 1, last year at a cost of N120,000. The machine has a useful life of six years and zero terminal disposal price. Depreciation is calculated on the straight-line method. (ii) The machine could be sold today for N30,000. (iii) Product and process engineering costs are incurred to ensure that the production process for “Part 2011” works smoothly. Although these costs are fixed in the short run, with respect to units of “Part 2011” produced, they can be saved in the long run if “Part 2011” is no longer produced. If “Part 2011” is outsourced, product and process engineering costs of N8,000 will be incurred for next year only. (iv) Rent costs of N8,000 are apportioned to products on the basis of the floor space used for manufacturing the product. If “Part 2011” is discontinued, the space currently used to manufacture it would become available. The company could then use the space for storage purposes and save N2,000 currently paid for outside storage. (v) General overheads are apportioned to each department on the basis of direct production labour costs. These costs will not change in total, but no general overhead will be apportioned to “Part 2011” if the part is outsourced. Assume the required rate of return is 12%. Required:

a

Should DG Limited outsource “Part 2011”?

10 marks
b

What maximum price should KK Limited quote on the 1,000 units to make Divine Grace indifferent between outsourcing and internal production?

5 marks
c

What non-financial factors would favour internal production rather than outsourcing? (5 Marks) 60

Suggested answer

a) Outsourcing Cost Year Particular CF DCF@12% PV N N 1-5 Outsourcing Cost (100,000) 3.605 (360,500) 0 Sales of machine 30,000 1.000 30,000 1 Engineering cost (8,000) 0.893 (7143) 1-5 Rent 2,000 3.605 7,210 330,433 Internal Production Cost Year Particular CF DCF@12% PV N N 1-5 Direct material (44,000) 3.605 (158,620) 1-5 Direct Labour (22,000) 3.605 (79,310) 1-5 Variable O/H (14,000) 3.605 (50,470) 1-5 Engineering cost (8,000) 3.605 (28,840) 317,240 Decision: Produce internally The company should continue to produce “Part 2011”. 73 Alternative Approach

a) There are two options to evaluate

- Outsource......................A - Produce .......................B In the solution that follows, we use incremental approach Cash flows (N) Items Yr A B A-B PVF@12% PV Sales of machine 0 30,000 0 30,000 1 30,000 Outsourcing costs 1-5 (100,000) 0 (100,000) 3.605 (360,500) Direct materials 1-5 0 (44,000) 44,000 3.605 158,200 Direct labour 1-5 0 (22,000 22,000 3.605 79,310 Variable overhead 1-5 0 (14,000) 14,000 3.605 50,470 Product, etc engineering 1 (8,000) (8,000) 0 0.893 0 2-5 0 (8,000) 8,000 2.712 21,696 Rent 1-5 0 (2,000) 2,000 3.606 7,210 NPV if outsourcing N(13,614) The company should continue to produce part 2011.

b) NPV =N330,433 – N317,240= N13,193 Sensitivity of the quoted price = NPV PV of outsourcing cost x 100 = N13,139 N360,500 x 100 = 3.66% This means that the unit price should not reduce more than N100 - (N100 x 3.66%) = N100 - N3.66 = N96.34 Alternative Solution: 3.605 x 1000 units x Price =N360,500 – NPV = 3,605 P = N360,500 – N13,193 3,605P = N347,307 P = N347,307 3,605 P = N96.34 74

c) The following are the non-financial factors that would favour internal production:

i) Labour Union: If outsourcing leads to laying off operatives who are currently producing the components, labour union may react adversely, if not properly handled.

ii) Quality: To maintain high level of quality of the component, it might be better to produce rather than to outsource.

iii) Ability to meet delivery scheduling: Internal production should ensure that the components are delivered as and when needed.

iv) Continuity of supply: This component will be needed for the next five years. Strategic reasons will demand that the company should keep the supply under its control. Thus, for harmonious labour relationship, desired level of quality, ability to meet delivery scheduling and continuity of supply, it better to produce rather than outsourcing.

Examiner’s report This is one of the open-ended questions that tests candidates’ understanding of relevant cost. The attempt on this question by candidates was very low. The candidates recorded below average performance. The pitfall noticed is candidates’ failure to apply the discounting aspect of the question. Candidates are encouraged to study the Institute’s study manual when preparing for ICAN future examinations.

Marking guide Marks A DG to outsource or not (20 ticks at ½ mark) 10 B Maximum price to be quoted by KK Ltd 5 C Non-financial factors that affect internal production (Any 2 points at 2½ marks) 5 20 75

Source: ICAN Pathfinder, Skills Level Examination, Performance Management, November 2021, Question 2
3
Theory question 3Section B
20 marks
a 4b 4c 8

Kahkiri Limited manufactures two products, product X and product Y, on the same machines. Sales demand for the products exceed the machine capacity of the company’s production department. The potential sales demand in each period is for 16,000 units of Product X and 24,000 units of Product Y. Sales prices cannot be increased due to competition from other firms in the market. The maximum machine capacity in the production department is 64,000 hours in each period. The following cost and profitability estimates have been prepared: Product X Product Y ₦ ₦ Sales price 44 54 Direct materials 20 18 Direct Labour 6 11 Variable overhead 6 11 Contribution per unit 12 14 Attributable fixed cost N10,000 N10,000 Machine hours per unit 1.5 hours 2 hours Fixed costs in each period are N100,000 Required:

a

Using marginal costing approach, calculate the profit-maximising output for the period, and the associated profit for each product and company.

4 marks
b

What are the advantages of throughput accounting over marginal costing method in profit maximising decisions?.

4 marks
c

Calculate the throughput accounting ratio for Product X and for Product Y.

8 marks
d

Using throughput accounting principles, calculate the profit-maximising output in each period, and calculate the amount of the profit. (4 Marks) 61

Suggested answer

a. Using marginal costing principles to calculate the profit maximising output and profit: Products X Y Sales volume 16,000 units 24,000 units N N Sales Price 44 54 Less variable costs: Direct material 20 18 Direct labour 6 11 Variable overheads 6 11 Total variable costs 32 40 Contribution per unit 12 14 Machine hours per product 1.50 hours 2 hours Contribution per machine hours N8 N7 Ranking 1st 2nd Hours Required: Product X = 16,000 x 1.50 = 24,000hours Product Y = 24,000 x 2 = 48,000 hours Total hours machine required = 72,000 hours Available hours: 64,000 hours Production Mix = Product X = 16,000 units x 1.50 hours = 24,000 hours Product Y = 40,000 /2 = 20,000 units = 40,000 Hours Therefore, profit maximising output = Product X = 16,000 units Product Y = 20,000 units Associated Profit Product X Y Total N Unit contribution 12 14 Total contribution N192,000 N280,000 472,000 Less Attributable fixed cost N(10,000) N(10,000) (20,000) Less General Fixed costs (100,000) Net Profit N182,000 N270,000 352,000 76

b. The advantages of throughput accounting over marginal costing method in profit maximising decisions include:

(i) It helps to identify the factors that limit the organisation from realising its goal. (ii) It helps management to solve organisational crisis and improve business processes to ensure a competitive edge. (iii) It identifies method which the organisation can use to improve its financial management.

c. Calculation of the throughput accounting ratio for Products X and Y Computing throughput return per bottleneck X Y Sales volume 16,000 units 24,000 units Sales Price N44 N54 Less: Throughput costs: Direct material N20 N18 Throughput return N24 N36 Machine hours per unit 1.50 hours 2 hours Throughput returns per machione hours N16 N18 Ranking 2nd 1st Factory operating cost per bottleneck Particulars X Y Total N Units of production 16,000 24,000 Direct labour N96,000 N264,000 360,000 Variable overhead N96,000 N264,000 360,000 Attributable fixed costs N10,000 N10,000 20,000 Other fixed costs 100,000 Tot Throughput accounting ratio = Throughput return per bottleneck Factory cost per bottle neck Product X Y Throughput returns per machione hours N16 N18 Factory operating cost per machine hour N13.125 13.125 Throughput Accounting ratio = 16 18 = 13.125 13.125 = 1.22 1.37 Ranking to manufacture 2nd 1st

d. Product X Y Total N Total machine hours 16000 hours 48,000 hours Machine hours/Unit 1.5 hours 2 hours Profit maximising output 10,667 units 24,000 units Throughput return/hour N16 N18 Total Return N256,000 N864,000 1,120,000 Total operating cost 840,000 Total operating costs 280,000

Examiner’s report The question tests candidates’ understanding of throughput accounting and marginal costing analysis. The attempt on this question by candidates was very high. The candidates recorded above average performance. The pitfall noticed is inability of the candidates to compute throughput accounting ratio. Candidates are advised to use ICAN study manual intensively when preparing for ICAN future examinations. 78

Marking guide Marks a Computation of profit maximising output and profit (20 ticks at 1/5 mark) 4 b Advantages of throughput accounting over marginal costing. (2 points at 2 marks) 4 c Computation of Throughput accounting ratio. (40 ticks at 1/5 mark) 8 d Computation of profit maximising output and profit using throughput Accounting. (16 ticks ¼ mark) 4 20

Source: ICAN Pathfinder, Skills Level Examination, Performance Management, November 2021, Question 3
4
Theory question 4Section B
20 marks

You work as the assistant to the management accountant for Henry Limited, a medium-sized manufacturing company. One of its products, Product P, has been very successful in recent years, showing a steadily increasing trend in sales volumes. Sales volumes for the four quarters of last year were as follows: Quarter Quarter Quarter Quarter 1 2 3 4 Actual sales volume (units) 420,000 450,000 475,000 475,000 A new assistant has recently joined the marketing department and she has asked you for help in understanding the terminology which is used in preparing sales forecasts and analysing sales trends. She said: “My main problem is that I do not see why my boss is so enthusiastic about the growth in Product P’s sales volume. It looks to me as though the rate of growth is really slowing down and has actually stopped in quarter 4. I am told that I should be looking at the deseasonalised or seasonally adjusted sales data, but I do not understand what is meant by this’’. You have found that Product P’s sales are subject to the following seasonal variations: Quarter Quarter Quarter Quarter 1 2 3 4 Seasonal variation (units) +25,000 +15,000 0 -40,000 Required:

a

i. Adjust for the seasonal variations to calculate deseasonalised or seasonally adjusted sales volume (i.e., the trend figures) for each quarter of last year. (5 Marks) ii. Assuming that the trend and seasonal variations will continue, forecast the sales volumes for each of the four quarters of next year. (4 Marks)

b

Explain what is meant by seasonal variations and deseasonalised or seasonally adjusted data. Indicate how they can be useful in analysing a time series and preparing forecasts.

5 marks
c

State the arguments for and challenges arising from managers participating in setting their budget targets. (6 Marks) 62

Suggested answer

a) HENRY LIMITED Quarter 1 Quarter 2 Quarter 3 Quarter 4 (i) units units units units Actual sales volumes 420,000 450,000 475,000 475,000 Seasonal variation + 25,000 + 15,000 0 40,000 Deasonalised sales volumes 395,000 435,000 475,000 515,000 Quarter 1 Quarter 2 Quarter 3 Quarter 4 (ii) units units units units Trend projection 555,000 595,000 635,000 675,000 Seasonal variation +25,000 +15,000 - 40,000 Forecast sales volume 580,000 610,000 635,000 635,000

b) Seasonal variations Seasonal variations are short term variations in data that occur due to the time or season of the year. These variations could be due to hourly, daily, weekly, monthly or yearly changes in sales patterns. Due to these variations, forecast data do not always follow the historical trend and hence, the figures have to be adjusted to account for these variations. Deseasonalised or seasonally adjusted data: Actual data recorded already include seasonal variations. In order to get a clear picture of the trend (i.e. the underlying pattern), the effect of seasonal variations have to be adjusted - a process referred to as deaseasonalising the data. 79 Observation of the actual data suggests that the rate of increase in sales is declining. Uses Provided that the observed trend in deseasonalised data continues, the deseasonalised data can be used to project the trend in future sales. The trend values are adjusted by seasonal variations in each quarter to predict actual sales.

c) Argument for manager’s participation

i) Managers have experience of the day-to-day running of the business. Their knowledge can help ensure that budget targets are on the one hand: realistic, and on the other hand, a reflection of the full capabilities of the business. ii) Through manager participation the budgeting process can also become an opportunity for senior management to communicate organisational strategy, policies and expectations. This should encourage subordinate managers to concentrate on corporate goals rather than their own personal goals and will therefore help to achieve goal congruence. iii) Participation tends to increase motivation since managers feel they are valued. In addition, input to target setting encourages greater commitment to budgets as the budgets are then perceived to be fair. This again leads to improved goal congruence. iv) Grooming of managers for top posts: The consultation processes involved can be used to access manager potential and help provide training in the skills needed for higher-level management. Challenges arising from manager participation

i) Since managers are required to implement budgets, they may attempt to set easily achievable targets, over-estimating resource requirements for instance. This can be a particular problem if bonuses depend on achieving such targets. Occasionally, the reverse problem can arise: managers might be over optimistic, thinking an ambitious target will improve their status.

ii) Managers may have different degress of skill in determining an appropriate level of difficulty for budget targets, particularly in a changing business environment. Lack of confidence may also make a manager reluctant to participate.

iii) Although participation is usually perceived to improve motivation, if managers’ ideas are rejected, they may feel slighted and have less motivation and commitment to the budget than if it had been imposed from above. 80

Examiner’s report This is an unpopular question which dwells on trend analysis, seasonal variation and de-seasonalised adjusted data as tools for forecasting and budgeting. The (a) aspect tests candidates ability to compute trend figures using trend and seasonal variation information while the (b) and (c) parts dwelt on theories of seasonal variation, deseasonalised variations and participative budgetary process.

Marking guide Marks Marks Marks a (i) Adjusting for personal variation (20 ticks at ¼ mark) 5 (ii) Forecasts for sales volumes (16 ticks at ¼ mark) 4 9 b - Explanation of seasonal valuation 1½

- Explanation of deseasonalised adjusted data 1½ - Uses of time series/Forecast 2 5 - c Advantages of participative budgeting (2 points at 1 ½ marks) 3 Disadvantages of participative budgeting (2 points at 1½ marks) 3 6 20

Source: ICAN Pathfinder, Skills Level Examination, Performance Management, November 2021, Question 4
5
Theory question 5Section C
15 marks
a 13b 2

Gaskiya Nigeria Limited is considering whether or not to invest in any of the two projects where the initial cash investment would be ₦13,000,000 for A and N14,000,000 for B. The project would have a five-year life and the estimated annual cash flows are as follows: Project A Year Cash inflows Cash outflows N N 1 6,000,000 3,000,000 2 8,000,000 4,000,000 3 10,000,000 4,000,000 4 9,000,000 3,000,000 5 6,000,000 3,000,000 Total 39,000,000 17,000,000 Project B Year Cash inflows Cash outflows N N 1 10,000,000 5,000,000 2 9,000,000 4,000,000 3 8,000,000 3,000,000 4 8,000,000 3,000,000 5 4,000,000 2,000,000 Total 39,000,000 17,000,000 The company’s cost of capital is 10%. The estimates of cash outflows are considered fairly reliable. However, the estimates of cash inflows are much more uncertain. Several factors could make the annual cash flows higher or lower than expected. Factor 1: There is a 20% probability that government measures to control the Industry will reduce annual cash inflows by 25%. Factor 2: There is a 30% probability that another competitor will also enter the market: this would reduce the estimated cash inflows by 10%. Factor 3: There is a 40% probability that demand will be stronger than expected. The company would not be able to supply more products to the market, but it 63 would be able to sell at higher prices and cash inflows would be 5% higher than estimated. Required:

a

Calculate the expected net present value of the two projects.

13 marks
b

Which of the Projects will be more profitable?

2 marks
Suggested answer

GASKIYA NIG LTD a. Calculation of the expected net present value of the two Projects Computation of joint Probability distribution S/N Factor 1 Factor 2 Factor 3 Workings Joint Probability 1 YES YES YES 0.2 X 0.3 X 0.4 0.024 2 YES YES NO 0.2 X 0.3 X. 0.6 0.036 3 YES NO NO 0.2 X 0.7 X 0.6 0.084 4 NO NO NO 0.8 X 0.7 X 0.6 0.336 5 NO NO YES 0.8 X 0. 7 X 0.4 0.224 6 NO YES YES 0.8 X 0.3 X0.4 0.096 7 YES NO YES 0.2 X 0.7 X 0.4 0.056 8 NO YES NO 0.8 X 0.3 X. 0.6 0.144 Total 1.000 81 Impact on inflow S/N Joint Probability Inflow impact Result Final expected value 1 0.024 1 - 0.25 -0.10 + 0.05 0.70 0.0168 2 0.036 1 -0.25 – 0.10 0.65 0.0234 3 0.084 1 – 0.25 0.75 0.0630 4 0.336 1-0.0 1.00 0.3360 5 0.224 1 +0.05 1.05 0.2352 6 0.096 1 -0.10+ 0.05 0.95 0.0912 7 0.056 1 – 0.25 + 0.05 0.80 0.0448 8 0.144 1 – 0.10 0.90 0.1296 1.000 0.9400 Thus the EV of considering the 3 factors is 0.94. Therefore the NPV of Project A and B are: Project A Year Cash inflow EV of Cash flow PV of cash flow N’000 N’000 N’000 N’000 N’000 N’000 0 - (13,000) (13,000) 1.000 (13,000) 1 6,000 x 0.94 Cash Net Cash Discount outflow flow rate 10% 5,640 (3,000) 2,640 0.909 2,399.76 2 8,000 x 0.94 7,520 (4,000) 3,520 0.826 2,907.52 3 10,000 x 0.94 9,400 (4,000) 5,400 0.751 4,055.40 4 9,000 x 0.94 8,460 (3,000) 5,460 0.683 3,729.18 5 6,000 x 0.94 5,640 (3,000) 2,640 0.621 1,639.44 NPV +1,731.30 82 Project B Year Cash inflow EV of Cash flow Cash outflow PV of cash flow N’000 N’000 N’000 N’000 N’000 0 - (14,000) (14,000) 1.000 (14,000) 1 10,000 x 0.94 9,400 (5,000) 4,400 0.909 3,999.60 2 9,000 x 0.94 8,460 (4,000) 4,460 0.826 3,683.96 3 8,000 x 0.94 7,520 (3,000) 4,520 0.751 3,394.52 4 8,000 x 0.94 7,520 (3,000) 4,520 0.683 3,087.16 5 4,000 x 0.94 3,760 (2,000) 1,760 0.621 1,092.96 NPV +1,258.20

b. Project A will be more profitable with a higher NPV of N1,731.30

Examiner’s report The question tests candidates’ understanding of investment appraisal under situations of uncertainty with sensitivity of variables that affected the investment . The question was highly attempted by candidates as it was a popular capital investment appraisal question. The candidates recorded average performance. The pitfall noticed is the inability of the candidates to decipher the several other factors that affect the annual cash inflows and reflect their effect on the present values of net cash flow. Candidates are encouraged to study the Institute’s study pack when preparing for ICAN future examinations.

Marking guide

- Marks Marks Marks - Company Name ½ - Computation of joint probability - (9 ticks at ¼ mark) 2¼ - Computation of expected value ( 9 ticks at ¼ mark) 2¼ - Expected Net Present value of project A (24 ticks at 1/6 mark) 4 - Expected Net Present value of Project B (24 ticks at 1/6 mark) 4 13 - Most profitable project 2 15 83 Net Cash flow Discount rate 10%

Source: ICAN Pathfinder, Skills Level Examination, Performance Management, November 2021, Question 5
6
Theory question 6Section C
15 marks

Mr. Alade, the owner of a business, has been attending a course on scenario planning and decision making. As a result of that advice, the owner has produced, by using cost, volume and profit analysis, 12 scenarios for a new product that the business will launch in the near future. There are four possible marketing packages that could be used (A, B, C, or D) and there are three possible market conditions (poor, average or good) that could be encountered. The Net Present Value of the cash flows resulting from each of the scenarios is shown in the table below. Market package Market conditions A N’000 B N’000 C N’000 D N’000 Poor 180 230 220 190 Average 190 200 210 275 Good 550 260 210 500 Unfortunately, Mr. Alade missed the session on how to deal with risk and uncertainty. He has sent the above table to the tutor for the course and has asked for help. The tutor replied “I will send you some notes. Based on your table, you will need the methods in the section on ’Uncertainty’. If you can estimate the probability of each type of market condition occurring you need ’Risk based methods’. However, whichever method you use, your decision will be influenced by your attitude.”

RequiredNote: Calculations are NOT required. Explain FOUR methods that could help Mr. Alade to decide which marketing package to choose. Your answer should include THREE methods to deal with uncertainty, ONE method to deal with risk, and an explanation of the attitude that would be associated with the decision maker using each of the four methods. (15 Marks) 64
Suggested answer

Mr. Alade could use any of the following three approaches to deal with uncertainty:

(i) Maximin Decision Rule: The decision maker will look at the options and choose the one that has the highest minimum return. This type of decision maker is a pessimist and will look at the worst outcome for each of the options and seeks to get the best of the worst.

(ii) Maximax Decision Rule: The decision maker will look at the options and choose the one that has the highest return. This type of decision maker is an optimist.

(iii) Minimax Decision Rule (Regret): The decision maker will analyse the options and choose an option so that if it is the wrong choice, the regret will not be as much as if the others had been chosen and they were wrong. This type of decision maker seeks to minimise the post-event regret of having made a wrong decision.

(iv) If probabilities can be assigned to the outcomes then “uncertainty” will become “risk”. It will then be possible to calculate “expected values”. The decision will choose the outcome that has the highest expected value. This assumes that the decision maker is risk neutral. METHOD OF DEALING WITH RISK The expected value of an option does not give any indication of the risk associated with the option. The risk, or spread, of the possible outcomes of each option can be measured by calculating the standard deviation. A risk minimiser would choose the option with the lowest standard deviation. The trade off between risk and return can be evaluated by calculating the coefficient of variation (standard deviation over the expected value).

(v) Decision tree is a flowchart to represent possible solution based on certain conditions

(vi) Simulation method forecasts the outcome of an event using probabilities associated with the events.

(vii) Sensitivity analysis is a method that determines the effect of risk on the expected outcome of a key variable or factor. 84 Attitude of Decision Makers: (i) Risk averse: This avoids risk without adequate compensation for the risk (ii) Risk neutral: This is indifferent about risk taking and hence, ignores it (iii) Risk seeking: This takes risk without compensation for the risk.

Examiner’s report This question tests candidates theoretical appreciation of decision making under situations of uncertainty and risk. Many candidates attempted the question. The candidates recorded average performance. The major pitfall noticed is the inability of candidates to work in accordance with the examiners’ requirements that no computations are required. Candidates are advised to pay special attention to the requirements of questions as well as use the Institute’s study manual when preparing for ICAN future examinations.

Marking guide Marks Marks - 3 Methods of uncertainty in decisions making. (Any 3 points and explanations) 9 - 1 Method of risk appraisal in decision making. (Any 1 point and explanation) 3 - 3 Attitudes associated with decision making under risk/uncertainty. (Any 3 points and explanations) 3 15 85

Source: ICAN Pathfinder, Skills Level Examination, Performance Management, November 2021, Question 6
7
Theory question 7Section C
15 marks
a 3b 3c 5

Garki plc. is a holding company with four divisions, including Alba and Beta Divisions. Alba Division produces a component that it sells externally, and can also transfer to other divisions within the group. Beta Division uses the components from Alba Division as a raw material for its final product. The division can also obtain the components from external suppliers. The components, when obtained from Alba Division undergoes further processing at a cost of N4.50 per unit, before it is sold to the external market. The Board of Directors, in order to implement a new Appraisal Review, has set up a performance scheme for the divisional managers. A performance target for the next financial year has been set and the following budgeted information relating to the two divisions has been prepared. Alba Division Beta Division Maximum production/ Sales capacity 900,000 units Sales to external customers 700,000 units (no constraints) (Selling price) N6.80 Variable Unit Cost N4.90 Divisional fixed cost \` N160,000 N140,000 Capital employed N4m N3m Residue Income N700,000 N500,000 Divisional cost of capital 12% 10%. Beta Division has asked Alba Division to quote a transfer price for units of the components. Required:

a

Calculate the transfer price per unit which Alba Division should quote to Beta division in order that its budgeted residual income target will be achieved.

3 marks
b

Calculate the selling price per unit which Beta Division should quote to external market in order that its budgeted residual income target will be achieved, based on the transfer price quotation, (state clearly your assumptions).

3 marks
c

Explain why the transfer price calculated in (a) may lead to sub-optimal decision making from the point of view of Garki plc. taken as a whole.

5 marks
d

In what circumstances would a negotiated transfer price be used instead of a market based price? (4 Marks) 65 Formulae Learning curve Y = axb Where Y = cumulative average time per unit to produce x units a = the time taken for the first unit of output x = the cumulative number of units produced b = the index of learning (log LR/log2) LR = the learning rate as a decimal Demand curve P = a – bQ = b change in price change in quantity a = price when Q = 0 MR = a – 2bQ The linear regression equation of Y on X is given by: Y = 𝑎 + 𝑏𝑋 where b = 𝑛 𝑋𝑌− ( 𝑋)( 𝑌) 𝑛 𝑋2− 𝑋 2 a = 𝑦𝑛 − 𝑏 𝑥 𝑛 Coefficient of determination (r2) r2 = n xy− x y1 2 n x2− x 2 n 𝑦2−( 𝑦)2 66 The Miller-Orr Model 𝑆𝑝𝑟𝑒𝑎𝑑 =3 x 134x Transaction Cost x Variance of Cash flows 3 Interest rate as a proportion Annuity Table Present value of an annuity of 1 i

e

1 - (1 + r)-n r Where r = discount rate n = number of periods Discount rate (r) Periods (n) 1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 1 0·990 0·980 0·971 0·962 0·952 0·943 0·935 0·926 0·917 0·909 1 2 1·970 1·942 1·913 1·886 1·859 1·833 1·808 1·783 1·759 1·736 2 3 2·941 2·884 2·829 2·775 2·723 2·673 2·624 2·577 2·531 2.487 3 4 3·902 3·808 3.717 3·630 3.546 3.465 3·387 3·312 3·240 3·170 4 5 4·853 4·713 4·580 4·452 4·329 4·212 4·100 3·993 3.890 3·791 5 6 5·795 5·601 5·417 5·242 5·076 4·917 4·767 4·623 4.486 4·355 6 7 6·728 6.472 6·230 6·002 5·786 5·582 5·389 5·206 5·033 4·868 7 8 7·652 7·325 7·020 6·733 6·463 6·210 5·971 5·747 5·535 5·335 8 9 8·566 8·162 7·786 7.435 7·108 6·802 6·515 6·247 5·995 5·759 9 10 9·471 8·983 8·530 8·111 7·722 7·360 7·024 6·710 6.418 6·145 10 11 10·368 9·787 9·253 8·760 8·306 7·887 7.499 7·139 6·805 6.495 11 12 11·255 10·575 9·954 9·385 8·863 8·384 7·943 7·536 7'161 6·814 12 13 12·134 11·348 10·635 9·986 9·394 8·853 8·358 7·904 7·487 7·103 13 14 13·004 12·106 11·296 10·563 9·899 9·295 8·745 8·244 7·786 7·367 14 15 13·865 12·849 11·938 11·118 10·380 9·712 9·108 8·559 8·061 7·606 15 (n) 11% 12% 13% 14% 15% 16% 17% 18% 19% 20% 1 0·901 0·893 0·885 0·877 0·870 0·862 0·855 0·847 0·840 0·833 1 2 1·713 1·690 1·668 1·647 1·626 1·605 1·585 1·566 1·547 1·528 2 3 2.444 2.402 2·361 2·322 2·283 2·246 2·210 2·174 2·140 2·106 3 4 3·102 3·037 2·974 2·914 2·855 2·798 2·743 2.690 2·639 2.589 4 5 3·696 3·605 3·517 3·433 3·352 3·274 3·199 3·127 3·058 2·991 5 6 4·231 4·111 3·998 3·889 3·784 3·685 3·589 3.498 3.410 3·326 6 7 4·712 4·564 4.423 4·288 4·160 4·039 3·922 3·812 3·706 3·605 7 8 5·146 4·968 4.799 4·639 4.487 4·344 4·207 4·078 3·954 3·837 8 9 5·537 5·328 5·132 4·946 4·772 4·607 4.451 4·303 4·163 4·031 9 10 5·889 5·650 5.426 5·216 5·019 4·833 4·659 4.494 4·339 4·192 10 11 6·207 5·938 5·687 5.453 5·234 5·029 4·836 4·656 4.486 4·327 11 12 6·492 6·194 5·918 5·660 5·421 5·197 4·988 4·793 4·611 4.439 12 13 6·750 6.424 6·122 5·842 5·583 5·342 5·118 4·910 4·715 4·533 13 14 6·982 6·628 6·302 6·002 5·724 5.468 5·229 5·008 4·802 4·611 14 15 7·191 6·811 6.462 6·142 5·847 5·575 5·324 5·092 4·876 4·675 15 67 68

Suggested answer

a) Garki Plc Transfer price per unit for Alba Division: N Residual income 700,000 Notional interest (12% x 4,000,000) 480,000 Net profit 1,180,000 Divisional fixed cost 160,000 Contribution 1,340,000 Variable cost (900,000 x 4.90) 4,410,000 Total revenue 5,750,000 Less: External revenue (700,000 x 6.80) (4,760,000) Internal revenue (A) 990,000 Excess/idle capacity (900,000 – 700,000) (B) 200,000 units Transfer price (A/B)/unit N4.95 b) Selling price of Beta Division N Residual income 500,000 Notional interest (10% x 3,000,000) 300,000 Net profit 800,000 Divisional fixed cost 140,000 Contribution 940,000 Plus Variable cost further of processing cost (200,000 x 4.50) 900,000 Plus Transfer price (200,000 x 4.95) - input cost 990,000 Total revenue (c) 2,830,000 Quantity to sell (D) 200,000 External selling price (C/D) N14.15 Assumption: External offer price from intermediate market from Beta Division is equal to or greater than N4.95 transfer price.

c) The transfer price to Beta Division will be sub-optimal to the company as a whole since N6.80 is the price to external customers while N4.95 is price to the division necessitating a loss of N1.85 per unit. The sub- optimal decision making also can be due to the buying division recognising the fixed costs of N160,000 and mark-up (Profit – residual income and imputed capital cost) of selling divisions as variable costs of N4.95 when it should have been N4.90 in setting the transfer price. 86

d) Negotiated transfer Price Versus Market based Price A negotiated transfer price is a price that is a product of agreements between the managers of the profit centres. Here, managers are given the autonomy to agree on transfer price. Negotiated transfer prices are appropriate when there is an imperfect market for the goods and services that are bought and sold between divisions. Market-based transfer pricing is based on the existence of external market. Market-based transfer pricing is perhaps the easiest form of transfer pricing when it comes to determining the price that will be paid between divisions of the same company. It uses the normal market rate that would be paid if the goods were bought on the open market.

Examiner’s report The question is a transfer pricing question that is computed using expected divisional profit and residual income information. Many candidates attempted the question. The candidates recorded average performance. The pitfall noticed is candidates computation of transfer price based on variable costs and opportunity cost without taking into consideration divisional returns expectation in the areas of divisional profit and residual income which are the basis of sub-optimality. Candidates are advised to pay special attention to the requirements of questions as well as use the Institute’s study manual when preparing for ICAN future examinations.

Marking guide Marks Marks a Transfer price from Alba divison (12 ticks at ¼ mark) 3 b Selling price by Beta division (12 ticks at ¼ mark) 3 c Transfer price as sub-optimal decision (2 reasons at 2 ½ marks) 5 d - Explanation of Negotiated Transfer price 2

- Explanation of market based Transfer Price’ 2 4 Total 15 87 THE INSTITUTE OF CHARTERED ACCOUNTANTS OF NIGERIA

Source: ICAN Pathfinder, Skills Level Examination, Performance Management, November 2021, Question 7
Source and reference. These questions come from the Institute of Chartered Accountants of Nigeria (ICAN) Pathfinder for the Skills Level Examination, Performance Management, 2021. When you use them, please cite the source, for example: ICAN Pathfinder, Skills Level Examination, Performance Management, May or November 2021. Each question carries its own reference and a button to copy it.