Internal Rate of Return and NPV versus IRR

ICAN Skills, Financial Management. Syllabus area C: Investment appraisal.

10 min read · Updated 8 November 2026

Download this topic

In this part

Net present value says how many naira a project adds. Managers often prefer a percentage: “this project returns 20%” is easier to compare with a cost of money of 14% than “this project has a net present value (NPV) of ₦1.7m”. The internal rate of return answers that question.

It is the discount rate at which the net present value is exactly zero, in other words the average annual return the project is expected to earn on the money invested, allowing for the timing of the cash flows.

This topic explains the internal rate of return, how to find it by trial and interpolation (and quickly for level cash flows), the decision rule, a worked example, and then the important comparison with NPV: where they agree, where they conflict, and why NPV is preferred. The next topic covers tax and capital allowances in discounted cash flow.

The internal rate of return was tested in May Diet, 2026, Question 3 (20 marks), where three divisional projects with internal rates of return of 16%, 16% and 18% were compared with divisional costs of capital to decide which to accept. Read net present value and the case for discounted cash flow first.

In 30 seconds

The internal rate of return (IRR) is the discount rate at which the NPV is zero: the expected return on the investment. Rule: accept a project if its IRR is greater than the required return (the cost of capital). To find it, calculate the NPV at two rates (one positive, one negative) and interpolate: IRR = a + [NPVa ÷ (NPVa − NPVb)] × (b − a).

For level flows, divide the outlay by the annual flow and look up the annuity factor. IRR versus NPV: they give the same accept/reject answer for a single conventional project, but can conflict for mutually exclusive projects (different scale or timing), the IRR can give multiple answers if flows change sign more than once, and it assumes reinvestment at the IRR. NPV is preferred.

The internal rate of return

The internal rate of return (IRR) is the cost of capital at which the project has an NPV of zero. In the NPV method the rate is the return required by the investor; in the IRR method it is the actual return expected from the project, an average annual percentage over its life, which is compared with the minimum required return.

Decision rule: undertake the project if its IRR exceeds the required return. For several independent projects, accept every project whose IRR exceeds the cost of capital; for mutually exclusive projects the IRR ranking is unreliable (see below).

Finding the IRR by interpolation

  1. Calculate the NPV at a convenient rate, a.
  2. Calculate the NPV at a second rate, b, chosen so that the NPV changes sign (a positive NPV means the IRR is higher than the rate, a negative NPV means it is lower).
  3. Interpolate: IRR = a + [NPVa ÷ (NPVa − NPVb)] × (b − a).

Delta Packaging, from the last topic, had an NPV of +₦1.70m at 12% and +₦0.05m at 20%, so the IRR is a little above 20%. At 24% the present values are 2.6 × 0.806 = 2.096, 3.1 × 0.650 = 2.015, 3.4 × 0.524 = 1.782 and 4.7 × 0.423 = 1.988, a total of 7.880, so the NPV is 7.880 − 8.5 = −₦0.62m. Interpolating between 20% and 24%: IRR = 20 + [0.0512 ÷ (0.0512 + 0.6197)] × 4 = 20 + 0.31 = 20.3%. Compared with a cost of capital of 12% the project should be accepted.

Interpolation assumes the NPV changes in a straight line between the two rates, which is not exactly true, so the answer is an approximation. It is more accurate when the two rates are close together (the earlier choice of 12% and 24% would have given about 20.8%).

Level cash flows: a shortcut

If the project has a single outlay and equal annual inflows, the IRR is the rate whose annuity factor equals outlay ÷ annual flow. A ₦24m outlay returning ₦7.5m a year for 5 years needs a factor of 24 ÷ 7.5 = 3.2. In the 5-year row of the table, 17% gives 3.199, so the IRR is about 17%.

NPV or IRR?

For a single project with an outlay followed by inflows, NPV and IRR give the same decision: the NPV is positive exactly when the IRR exceeds the cost of capital. They can disagree in other cases.

  • Mutually exclusive projects. The IRR is a percentage and takes no account of scale or of the size of the naira return, so a smaller project with a higher IRR can add less value than a larger one with a lower IRR; the NPV measures value directly. A timing difference can also reverse the ranking, because the two projects respond differently to a change in the discount rate.
  • Multiple IRRs. If the cash flows change sign more than once (for example a large cost at the end of a project, such as site restoration), there can be more than one rate at which the NPV is zero, or none, so the IRR is not meaningful.
  • Reinvestment assumption. The NPV implicitly assumes that interim cash flows are reinvested at the cost of capital, which is realistic; the IRR assumes reinvestment at the IRR itself, which is usually optimistic for a high-return project.
  • A changing cost of capital. The IRR is compared with one rate; if the discount rate changes over the life, the NPV can use a different rate in each year but the IRR cannot.

Example of a conflict. Project P costs ₦100m and returns ₦70m, ₦50m and ₦30m in years 1 to 3; project Q costs ₦100m and returns ₦20m, ₦50m and ₦90m. The IRR of P is 27.6% and of Q 21.8%, so the IRR prefers P. At a cost of capital of 5% the NPV of P is ₦37.9m and of Q ₦42.1m, so the NPV prefers Q; at 10% the order is reversed (P ₦27.5m, Q ₦27.1m).

Q has its cash later, so its value is more sensitive to the discount rate. Which is right depends on the true cost of capital, and the NPV, which uses it, is the correct basis. The crossing point of the two NPV profiles is about 9%.

Why the IRR is still used

Managers find a percentage easy to understand and compare with a target, it does not need the cost of capital to be known exactly (only whether the IRR is clearly above or below it). It is a measure of the margin of safety: a project with an IRR of 20% against a cost of 12% can tolerate a large error in the cash flows or the rate. These are good reasons for reporting it alongside the NPV.

The NPV profile and the IRRA downward sloping curve of NPV against the discount rate. At 12 per cent the NPV is plus 1.70 million, at 20 per cent plus 0.05 million, at 24 per cent minus 0.62 million. The curve crosses the horizontal axis at the IRR of 20.3 per cent. A side box: accept if the cost of capital is below the IRR. A second note: two projects with different timing have profiles that cross.12%: +1.70IRR 20.3%: 024%: −0.62Discount rate (horizontal) and NPV (vertical)Decision ruleaccept if cost of capitalis below the IRRCautionexclusive projects: NPVand IRR can disagree;prefer the NPV

The ideas in more depth

Why the IRR rule works for one project

The NPV falls as the discount rate rises. At the IRR it is zero; below the IRR it is positive; above it, negative. So if the cost of capital is below the IRR the NPV is positive. This holds only when there is one sign change, an outlay followed by inflows.

Why interpolation is an estimate

The NPV curve is a curve, not a straight line, so joining two points with a line gives an approximate answer. The nearer the two trial rates are to the true IRR, the closer the estimate, and in the exam it is enough to use rates 4 to 5 points apart that bracket the answer.

Sources and references

  • No accounting standard governs the method. Discount factors and annuity factors are given in the tables on the formula sheet of the paper.

These points are stated as at 5 November 2026.

Worked examples

Example 1: interpolation. NPV is +₦0.0512m at 20% and −₦0.6197m at 24%. Required: the IRR.

  1. Share.
    0.0512 ÷ (0.0512 + 0.6197) = 0.076.
  2. IRR.
    20 + 0.076 × 4 = 20.3%.

Example 2: level flows. Outlay ₦24m; ₦7.5m a year for 5 years. Required: the IRR.

  1. Factor.
    24 ÷ 7.5 = 3.2.
  2. IRR. The 5-year factor at 17% is 3.199, so about 17%.

Example 3: the decision. IRR 20.3%; cost of capital 12%. Required: the decision.

  1. Compare. 20.3% exceeds 12%, so accept, with a margin of 8.3 percentage points.

How to answer in the exam

  • Calculate two NPVs on either side of zero and interpolate; show the formula.
  • For level flows, use the factor shortcut and check it in the table.
  • State the decision against the required return.
  • Compare with NPV, giving at least two of the weaknesses: scale, timing, multiple rates, reinvestment.

Common mistakes in the exam

  • Choosing two trial rates that both give a positive NPV.
  • Using the wrong sign in the interpolation.
  • Ranking mutually exclusive projects by IRR.
  • Comparing the IRR with a rate that is not the project’s required return.
  • Treating the interpolated figure as exact.
  • Using the IRR for projects with several sign changes.

Quick revision

  • IRR = discount rate at which NPV = 0; accept if above the cost of capital.
  • IRR = a + NPVa ÷ (NPVa − NPVb) × (b − a).
  • Level flows: outlay ÷ flow = annuity factor.
  • NPV preferred: scale, timing, multiple IRRs, reinvestment.

Practice questions

These are original questions written in the style of the Institute’s exams. Try each one before you open the answer. Section A is a recall check, because the paper itself is written.

Recall check: multiple choice

Question 1. The IRR is the discount rate at which:

  1. Profit is zero
  2. Payback is one year
  3. The NPV is zero
  4. Cash is zero
Show the answer

C. It is the expected return on the investment.

Question 2. A project is accepted on IRR if the IRR is:

  1. Below the cost of capital
  2. Above the cost of capital
  3. Zero
  4. Equal to payback
Show the answer

B. It earns more than the required return.

Question 3. To find the IRR by interpolation you need NPVs at two rates that:

  1. Give one positive and one negative NPV
  2. Are both positive
  3. Are both negative
  4. Are equal
Show the answer

A. So that the IRR lies between them.

Question 4. With level annual flows, the IRR is found where the annuity factor equals:

  1. Flow ÷ outlay
  2. Outlay × flow
  3. Years ÷ rate
  4. Outlay ÷ annual flow
Show the answer

D. Then read the rate from the table.

Question 5. For mutually exclusive projects, the IRR can:

  1. Never be calculated
  2. Give a different ranking from NPV
  3. Always agree with NPV
  4. Equal the cost of capital
Show the answer

B. Because of scale and timing differences.

Question 6. Multiple IRRs can arise when:

  1. The cash flows change sign more than once
  2. The life is short
  3. The cost of capital is high
  4. The tax is zero
Show the answer

A. For example a large restoration cost at the end.

Question 7. The IRR assumes interim cash flows are reinvested at:

  1. Zero
  2. The cost of capital
  3. The IRR itself
  4. The tax rate
Show the answer

C. Often an optimistic assumption.

Question 8. The preferred method for choosing between exclusive projects is:

  1. IRR
  2. Payback
  3. ARR
  4. NPV
Show the answer

D. It measures the value added.

Question 9. An advantage of the IRR is that it:

  1. Ignores risk
  2. Is an absolute amount
  3. Is a percentage that is easy to compare with a target
  4. Needs no cash flows
Show the answer

C. And shows the margin of safety.

Question 10. For one conventional project, NPV and IRR give:

  1. The same accept or reject decision
  2. Opposite decisions always
  3. No decision
  4. Different lives
Show the answer

A. The NPV is positive exactly when the IRR exceeds the cost of capital.

Section B style: written questions

Question 11 (10 marks). (a) Define the IRR and state the decision rule. (4 marks) (b) State the interpolation formula. (3 marks) (c) State THREE weaknesses of the IRR. (3 marks)

Question 12 (15 marks). A project costs ₦18m and returns ₦5.0m a year for 6 years. The annuity factors for 6 years are 3.685 at 16% and 3.589 at 17%. The cost of capital is 14%. (a) Calculate the annuity factor required. (3 marks) (b) Estimate the IRR. (7 marks) (c) State the decision. (3 marks) (d) State why the IRR is only an estimate. (2 marks)

A further written question

Question 13 (20 marks). A project costs ₦12m and returns ₦4.8m, ₦5.5m and ₦6.0m in years 1 to 3. At 15% the factors are 0.870, 0.756 and 0.658; at 20% they are 0.833, 0.694 and 0.579. The cost of capital is 15%.

(a) Calculate the NPV at 15%. (6 marks) (b) Calculate the NPV at 20%. (6 marks) (c) Estimate the IRR. (4 marks) (d) State the decision and TWO other points to consider. (4 marks)

Model answers

Show the model answer to Question 11

(a) The discount rate at which the NPV is zero, the expected return on the investment (2); accept if it exceeds the required return (2).

(b) IRR = a + [NPVa ÷ (NPVa − NPVb)] × (b − a) (3).

(c) It can conflict with NPV for exclusive projects; it can give multiple answers; it assumes reinvestment at the IRR; it ignores the scale of the investment (1 each, any three).

Show the model answer to Question 12

(a) 18 ÷ 5.0 = 3.6 (3).

(b) The factor 3.6 lies between 3.685 (16%) and 3.589 (17%): IRR = 16 + (3.685 − 3.6) ÷ (3.685 − 3.589) × 1 = 16 + 0.885 = 16.9% (7).

(c) 16.9% exceeds 14%, so accept (3).

(d) Interpolation assumes a straight line between the two rates, but the relationship is a curve (2).

Show the model answer to Question 13

(a)

  1. 4.8 × 0.870 = 4.176
  2. 5.5 × 0.756 = 4.158
  3. 6.0 × 0.658 = 3.948 (3)
  4. total 12.282 less 12 = +₦0.28m (3).

(b)

  1. 4.8 × 0.833 = 3.998
  2. 5.5 × 0.694 = 3.817
  3. 6.0 × 0.579 = 3.474 (3)
  4. total 11.289 less 12 = −₦0.71m (3).

(c) IRR = 15 + [0.282 ÷ (0.282 + 0.7106)] × 5 = 15 + 1.42 = 16.4% (4).

(d) Accept: the NPV at 15% is positive and the IRR exceeds the cost of capital (2). Also consider the risk of the cash flows and the size of the margin (only 1.4 points) (2).

Pathfinder on Internal rate of return and NPV versus IRR

These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.

May Diet, 2026: Question 3 (20 marks)

Part (a) asks which of three divisional projects, with internal rates of return of 16%, 16% and 18%, should be accepted against divisional costs of capital, and what changes under a single company-wide rate of 17% (10 marks).

Revise first: The internal rate of return

Source: ICAN Pathfinder, Financial Management. Diets covered: Every diet in the Pathfinder, November Diet, 2025 and May Diet, 2026, was reviewed here. The diets listed above test this topic directly..

Spotted a mistake? Tell us and we will check it.

Where this fits

See every past question on Financial Management and the topic each one tests in the Pathfinder question finder.

After it, move on to Strategic Financial Management.

All Financial Management topics

You are reading topic 28 of 75.

  1. The nature and purpose of financial management01
  2. Financial objectives: shareholder wealth, profit, earnings per share and stakeholder value02
  3. Stakeholders and conflicts of objectives03
  4. Agency theory and the agency problem04
  5. Achieving stakeholder objectives: governance codes, listing rules and reward schemes05
  6. Evaluating corporate objectives: ratios and total shareholder return06
  7. Financial management in not-for-profit organisations07
  8. Macroeconomic policy targets, GDP and fiscal policy08
  9. Monetary policy, interest rates, inflation and the exchange rate09
  10. Money markets, banks and money market instruments10
  11. Capital markets and the stock exchange11
  12. The bond market and technology in financial markets12
  13. Working capital: nature, elements and objectives13
  14. The cash operating cycle, working capital ratios and overtrading14
  15. Inventory management: EOQ, reorder levels, just-in-time and ABC analysis15
  16. Managing receivables: credit terms and credit control16
  17. Debt factoring and invoice discounting17
  18. Early settlement discounts and trade payables18
  19. Cash flow forecasts and reasons for holding cash19
  20. Short-term investment and treasury management20
  21. Cash management models: Baumol and Miller-Orr21
  22. Working capital investment policy and determining needs22
  23. Working capital funding strategies23
  24. Capital expenditure, payback and accounting rate of return24
  25. Relevant cash flows in investment appraisal25
  26. The time value of money: discounting and annuities26
  27. Net present value and the case for discounted cash flow27
  28. Internal rate of return and NPV versus IRR28 here
  29. Taxation and capital allowances in DCF29
  30. Inflation in DCF: real and money terms30
  31. Risk and uncertainty in appraisal: sensitivity analysis31
  32. Expected value and decision trees32
  33. The value of perfect information33
  34. Simulation, risk-adjusted discount rates and discounted payback34
  35. Lease or buy and borrow-to-buy decisions35
  36. Asset replacement: equivalent annual cost and the lowest common multiple36
  37. Capital rationing: divisible and indivisible projects37
  38. Short-term sources of finance38
  39. Long-term sources of finance: equity, debt, hybrids and leases39
  40. Issuing shares: public offers, placings, introductions, underwriting and buy-backs40
  41. Rights issues41
  42. Islamic finance: riba, murabaha, ijarah, mudaraba, sukuk and musharaka42
  43. Internal finance and dividend policy43
  44. Cost of equity: the dividend valuation model44
  45. Portfolio theory and diversification45
  46. Systematic and unsystematic risk and the efficient frontier46
  47. The capital asset pricing model and arbitrage pricing theory47
  48. Cost of debt48
  49. Cost of preference shares and convertibles49
  50. The weighted average cost of capital50
  51. Project-specific cost of capital and adjusted WACC51
  52. Capital gearing, business risk and financial risk52
  53. The traditional view and Modigliani and Miller without tax53
  54. Modigliani and Miller with tax, market imperfections and gearing in appraisal54
  55. Pecking order theory and choosing the financing method55
  56. SME financing problems and remedies56
  57. SME finance: venture capital, business angels, crowdfunding and supply chain finance57
  58. Why value a business: reasons and information needed58
  59. Asset-based valuation59
  60. Income-based valuation: P/E, earnings yield and EV/EBITDA60
  61. Dividend valuation of shares61
  62. Discounted cash flow valuation of a business62
  63. Valuing bonds and preference shares63
  64. The efficient market hypothesis64
  65. Practical considerations in share valuation65
  66. Foreign exchange rates and quotations66
  67. Foreign exchange risk: transaction, translation and economic67
  68. Causes of exchange rate movements68
  69. Purchasing power parity, interest rate parity and four-way equivalence69
  70. Covered interest arbitrage and forward rates70
  71. Internal hedging: invoice currency, netting, matching, leading and lagging71
  72. Forward contracts and money market hedges72
  73. Foreign currency derivatives: futures, options and swaps73
  74. Interest rate risk and traditional hedging74
  75. Interest rate derivatives: FRAs, futures, options and swaps75
See the whole course

Get the complete Financial Management notes

Download as PDF or Word

  • Every topic as PDF and Word, ready to print
  • Edit it in Word or print the PDF. No retyping.
Get this course

Reading stays free. Access lasts 12 months. Pay by card, bank transfer, USSD or QR through Paystack. Your name and email appear on every page of your files. Read our Refund Policy.

PracticeNext topic