A company is financed by several kinds of money: shares, bonds, bank loans, preference shares. Each costs a different amount. To judge whether a project is good enough, the company needs a single figure for what its money costs overall, the average return it must earn on everything it has raised so that every provider of finance is paid what they require.

That figure is the weighted average cost of capital, usually called the WACC. It is the most used discount rate in investment appraisal. It is the figure that the directors try to push down, because the lower it is the more valuable the company. But it is a correct discount rate only under conditions that many projects do not satisfy.

This topic explains how to calculate the weighted average cost of capital from market values, how it links to the value of the company, when it may be used to appraise a project, the difference between the average and the marginal cost of capital, and the limits of the figure, with worked examples.

The next topic shows how to find a project-specific rate when the project’s risk is not that of the company.

The weighted average cost of capital was calculated in May Diet, 2026, Question 2(a) (7 marks), using a cost of equity from the dividend growth model and a cost of debt from the internal rate of return of a bond. Read cost of preference shares and convertibles first.

In 30 seconds

The weighted average cost of capital (WACC) is the average of the after-tax costs of all the sources of long-term finance, each weighted by its market value: WACC = Σ (market value × cost) ÷ total market value. Equity is valued at shares × price; bonds at market price (not nominal); preference shares at market price; bank loans at the amount owed.

For a company with constant annual earnings, value = earnings after tax before interest ÷ WACC, so a lower WACC means a higher value. WACC can be used to appraise a project only if the project is small, has the same business risk, is financed in the same proportions and does not change the investors’ required returns; otherwise a project-specific rate is needed.

The marginal cost of capital is the cost of the next increment of finance.

Calculating the WACC

The weighted average cost of capital is the average cost of all the sources of capital a company uses, weighted by their relative amounts.

The costs are the after-tax costs of the previous topics (the cost of equity, the after-tax cost of debt, the cost of preference shares) and the weights are market values, because the market values show what each provider could actually realise and what the company would have to pay for new money.

Book values are not suitable: they record the amounts originally raised, which may be very different from what the capital is worth today.

Method: for each source find its market value and its cost, multiply, add, and divide by the total market value. Example: Delta has 600m ordinary shares priced at ₦5.00; ₦1,000m nominal of 12% redeemable bonds trading at ₦96 per ₦100 nominal, with an after-tax cost of 9.5%; a bank loan of ₦500m at 21% before tax; and 200m 10% preference shares of ₦1, priced at ₦0.85. The cost of equity is 16%. Tax is 30%.

SourceMarket value ₦mAfter-tax costValue × cost ₦m
Ordinary shares (600m × ₦5.00)3,00016.0%480.0
Bonds (₦1,000m × 0.96)9609.5%91.2
Bank loan50021% × 0.70 = 14.7%73.5
Preference shares (200m × ₦0.85)1700.10 ÷ 0.85 = 11.8%20.0
Total4,630664.7

WACC = 664.7 ÷ 4,630 = 14.4%. The weights are 64.8% equity, 20.7% bonds, 10.8% loan and 3.7% preference shares. If the weights had been taken from book values (say equity ₦1,800m, bonds ₦1,000m at 9.5%, loan ₦500m and preference shares ₦200m) the WACC would have been 13.7%, understating the cost because equity, the dearest source, would have been given too small a weight.

The cost of equity in the WACC

The cost of equity may come from the dividend valuation model or from the capital asset pricing model. With a risk-free rate of 8%, a market return of 16% and a beta of 1.2, the capital asset pricing model (CAPM) gives 8 + 1.2 × 8 = 17.6%. Which model is used affects the WACC; the CAPM is generally preferred because it takes explicit account of systematic risk, while the growth model depends on a forecast of growth. In an examination use the model the question names.

WACC and the value of the company

If the company’s annual earnings (profit after tax before interest) are a constant amount for ever, the total value of the company is earnings ÷ WACC.

With earnings of ₦600m:

  • at a WACC of 12% the value is ₦5,000m
  • at 10% it is ₦6,000m
  • at 15% it is ₦4,000m. A lower WACC means a higher value of the company, so the aim of financing policy is to reach the mix of debt and equity that minimises the WACC

Whether such a mix exists is considered in the topics on gearing and capital structure.

When WACC may be used to appraise projects

The WACC is the return that the company’s existing business must earn to satisfy its investors. It is a correct discount rate for a new project only if the project does not change the risk that the investors face. The conditions are:

  1. the project is small relative to the company;
  2. its business activities and business risk are similar to the company’s;
  3. it is financed in a mix similar to the current capital structure (so financial risk is unchanged); and
  4. the providers of finance do not change the returns they require because of the project.

If the project is of a different business risk from the company, the WACC is the wrong rate: a risky project discounted at the lower WACC may be accepted when it should not be (its internal rate of return (IRR) is above the WACC but below the return its risk demands), and a safe project may be rejected (its IRR is below the WACC but above what its low risk requires).

In these cases a project-specific rate from the capital asset pricing model is used, as in the next topic.

Average and marginal cost of capital

The WACC is an average of the costs of the capital already in use. The marginal cost of capital is the cost of the next increment of capital raised: new debt may cost more than the average because it is raised in current market conditions, and if a large amount is raised the investors may demand more.

For small projects the average is used; for a project big enough to change the structure or the risk, the marginal cost, or a rate for the project’s own financing and risk, is more appropriate.

Building the WACCStacked bars of market value: equity 3,000 million at 16 per cent, bonds 960 million at 9.5, bank loan 500 million at 14.7, preference shares 170 million at 11.8. Total market value 4,630 million and weighted average cost of capital 14.4 per cent. A note: with book-value weights the figure would be 13.7 per cent; a lower WACC means a higher company value.equity 3,000 at 16.0%bonds 960 at 9.5%bank loan 500 at 14.7%preference shares 170 at 11.8%WACC664.7 ÷ 4,630= 14.4%book-value weights: 13.7%(understates the cost)value = earnings ÷ WACC:lower WACC, higher valueBar length proportional to market value

The ideas in more depth

Why market values, and which ones

Equity is valued at the number of shares times the price, excluding any dividend about to be paid (ex-dividend). Bonds are valued at the market price, ex-interest; a bank loan, which is not traded, is taken at the amount owed.

If the share price falls the weight of equity falls and the WACC moves towards the cost of debt, which is lower; so the WACC is not a fixed property of the company but depends on market prices.

Why the WACC is not the cost of the cheapest finance

Debt is cheaper than equity, so it is tempting to appraise a project financed by a loan at the cost of the loan. But borrowing more raises the risk of the equity and so its cost (the topic on gearing), and the loan uses up debt capacity that would otherwise be available for other projects. The WACC averages these effects; the cost of the specific finance does not.

Market weights and book weights

The weights in the WACC should be market values, because they show what the capital would cost to raise today. Suppose a company has equity with a market value of \u20a63,000m and a book value of \u20a61,200m, debt of \u20a6900m, a cost of equity of 16% and an after-tax cost of debt of 9%.

On market values the weights are 3,000 \u00f7 3,900 = 76.9% and 900 \u00f7 3,900 = 23.1%, and the WACC is 0.769 \u00d7 16% + 0.231 \u00d7 9% = 14.38%. On book values the weights are 1,200 \u00f7 2,100 = 57.1% and 900 \u00f7 2,100 = 42.9%, and the WACC is 0.571 \u00d7 16% + 0.429 \u00d7 9% = 13.00%. Book weights understate the equity, whose cost is the higher, and so understate the WACC by 1.38 points.

A project accepted at the lower rate may be one that earns less than investors require. Use book weights only when the question gives no market values.

Sources and references

  • No accounting standard governs the calculation of the cost of capital. Use the market values given in the question and say which model was used for the cost of equity.

These points are stated as at 5 November 2026.

Worked examples

Example 1: the weights. Equity ₦3,000m; bonds ₦960m; loan ₦500m; preference shares ₦170m. Required: the weight of equity.

  1. Total.
    3,000 + 960 + 500 + 170 = ₦4,630m.
  2. Weight.
    3,000 ÷ 4,630 = 64.8%.

Example 2: the WACC. Total of value × cost ₦664.7m; total value ₦4,630m. Required: the WACC.

  1. WACC.
    664.7 ÷ 4,630 = 14.4%.

Example 3: the company value. Earnings ₦600m a year for ever; WACC 12%. Required: the value.

  1. Value.
    600 ÷ 0.12 = ₦5,000m.

How to answer in the exam

  • Set out a table with market value, cost and value × cost for each source.
  • Use after-tax costs for debt and market values for the weights, and say so.
  • Name the model used for the cost of equity and its inputs.
  • State the conditions for using the WACC to appraise a project and whether they hold.

Common mistakes in the exam

  • Using book values or nominal values as weights.
  • Using the pre-tax cost of debt.
  • Using a cum-dividend price for equity or a cum-interest price for debt.
  • Leaving out the preference shares or the bank loan.
  • Applying the WACC to a project of a different risk without comment.
  • Taking the coupon as the cost of the bond.

Quick revision

  • WACC = Σ (market value × after-tax cost) ÷ total market value.
  • Value of a company with constant earnings = earnings ÷ WACC.
  • Use WACC only if business and financial risk are unchanged.
  • Marginal cost = cost of the next increment of finance.

Practice questions

These are original questions written in the style of the Institute’s exams. Try each one before you open the answer. Section A is a recall check, because the paper itself is written.

Recall check: multiple choice

Question 1. The weights in the WACC are based on:

  1. Nominal values
  2. Book values
  3. Market values
  4. Tax rates
Show the answer

C. What each source is worth today.

Question 2. The WACC may be used to appraise a project if the project:

  1. Is much larger than the company
  2. Does not change the company’s business or financial risk
  3. Is financed only by debt
  4. Is in a different industry
Show the answer

B. And is small.

Question 3. The cost of debt in the WACC is the:

  1. After-tax cost
  2. Pre-tax coupon
  3. Dividend yield
  4. Nominal rate
Show the answer

A. Because interest is tax-deductible.

Question 4. A lower WACC means:

  1. A lower company value
  2. No change in value
  3. A higher dividend
  4. A higher company value for given earnings
Show the answer

D. Value = earnings ÷ WACC.

Question 5. A condition for using the WACC is that:

  1. The project is risk free
  2. The financing mix is similar to the existing one
  3. The project is large
  4. Equity is not used
Show the answer

B. So that financial risk is unchanged.

Question 6. Using book values as weights usually:

  1. Misstates the WACC because they differ from market values
  2. Is correct
  3. Raises the value
  4. Removes tax
Show the answer

A. Typically it gives too little weight to equity.

Question 7. The marginal cost of capital is the cost of:

  1. All existing capital
  2. Old debt
  3. The next increment of capital raised
  4. Equity only
Show the answer

C. Which may differ from the average.

Question 8. Preference shares in the WACC are taken at:

  1. Nominal value
  2. Zero
  3. Their dividend
  4. Market value and their own cost
Show the answer

D. Like any other source.

Question 9. The value of a company with constant earnings is:

  1. Earnings × WACC
  2. WACC ÷ earnings
  3. Earnings ÷ WACC
  4. Earnings − WACC
Show the answer

C. A perpetuity.

Question 10. Using the WACC for a project riskier than the company may:

  1. Lead to accepting a project that should be rejected
  2. Lead to rejecting a good project
  3. Have no effect
  4. Increase tax
Show the answer

A. The rate is too low for the risk.

Section B style: written questions

Question 11 (10 marks). (a) State the formula for the WACC and the weights used. (3 marks) (b) State FOUR conditions for using the WACC in appraisal. (4 marks) (c) State why market values are used. (3 marks)

Question 12 (15 marks). A company has 400m shares at ₦3.00 with a cost of equity of 14%, and debt with a market value of ₦600m and an after-tax cost of 8%. (a) Calculate the market values and weights. (5 marks) (b) Calculate the WACC. (6 marks) (c) State what the WACC means for the company. (4 marks)

A further written question

Question 13 (20 marks). The risk-free rate is 7%, the market return 15% and the equity beta 1.1. The equity has a market value of ₦2,400m; bonds have a market value of ₦900m and an after-tax cost of 10%; a bank loan is ₦400m with an after-tax cost of 8.4%.

(a) Calculate the cost of equity. (4 marks) (b) Calculate the WACC. (8 marks) (c) A project in the same business with a similar financing mix has an IRR of 14%; state the decision. (4 marks) (d) State TWO reasons why the WACC might not suit another project. (4 marks)

Model answers

Show the model answer to Question 11

(a) WACC = Σ (market value × after-tax cost) ÷ total market value (2); weights are market values (1).

(b) Project is small; similar business risk; similar financing mix; investors’ required returns unchanged (1 each).

(c) They show what each source is worth now and what new capital would cost (3).

Show the model answer to Question 12

(a) Equity 400m × 3.00 = ₦1,200m; debt ₦600m; total ₦1,800m (3); weights 66.7% and 33.3% (2).

(b) 1,200 × 14% = 168; 600 × 8% = 48; total 216; 216 ÷ 1,800 = 12.0% (6).

(c) It is the average return the company must earn on its investments to pay all providers of finance what they require (4).

Show the model answer to Question 13

(a) 7 + 1.1 × (15 − 7) = 15.8% (4).

(b) 2,400 × 15.8% = 379.2; 900 × 10% = 90; 400 × 8.4% = 33.6; total 502.8; total value 3,700; WACC = 13.6% (8).

(c) The conditions for using the WACC hold, and the IRR of 14% exceeds 13.6%, so accept (4).

(d) A different business risk; a different financing mix; a project large enough to change the structure; investors changing their required returns (2 each, any two).

Pathfinder on The weighted average cost of capital

These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.

May Diet, 2026: Question 2 (20 marks)

Part (a) (7 marks) calculates the weighted average cost of capital, with the cost of equity from the dividend growth model and the cost of debt from the internal rate of return of a redeemable bond.

Revise first: Calculating the WACC

Source: ICAN Pathfinder, Financial Management. Diets covered: Every diet in the Pathfinder, November Diet, 2025 and May Diet, 2026, was reviewed here. The diets listed above test this topic directly..

Spotted a mistake? Tell us and we will check it.

Where this fits

See every past question on Financial Management and the topic each one tests in the Pathfinder question finder.

After it, move on to Strategic Financial Management.

All Financial Management topics

You are reading topic 50 of 75.

  1. The nature and purpose of financial management01
  2. Financial objectives: shareholder wealth, profit, earnings per share and stakeholder value02
  3. Stakeholders and conflicts of objectives03
  4. Agency theory and the agency problem04
  5. Achieving stakeholder objectives: governance codes, listing rules and reward schemes05
  6. Evaluating corporate objectives: ratios and total shareholder return06
  7. Financial management in not-for-profit organisations07
  8. Macroeconomic policy targets, GDP and fiscal policy08
  9. Monetary policy, interest rates, inflation and the exchange rate09
  10. Money markets, banks and money market instruments10
  11. Capital markets and the stock exchange11
  12. The bond market and technology in financial markets12
  13. Working capital: nature, elements and objectives13
  14. The cash operating cycle, working capital ratios and overtrading14
  15. Inventory management: EOQ, reorder levels, just-in-time and ABC analysis15
  16. Managing receivables: credit terms and credit control16
  17. Debt factoring and invoice discounting17
  18. Early settlement discounts and trade payables18
  19. Cash flow forecasts and reasons for holding cash19
  20. Short-term investment and treasury management20
  21. Cash management models: Baumol and Miller-Orr21
  22. Working capital investment policy and determining needs22
  23. Working capital funding strategies23
  24. Capital expenditure, payback and accounting rate of return24
  25. Relevant cash flows in investment appraisal25
  26. The time value of money: discounting and annuities26
  27. Net present value and the case for discounted cash flow27
  28. Internal rate of return and NPV versus IRR28
  29. Taxation and capital allowances in DCF29
  30. Inflation in DCF: real and money terms30
  31. Risk and uncertainty in appraisal: sensitivity analysis31
  32. Expected value and decision trees32
  33. The value of perfect information33
  34. Simulation, risk-adjusted discount rates and discounted payback34
  35. Lease or buy and borrow-to-buy decisions35
  36. Asset replacement: equivalent annual cost and the lowest common multiple36
  37. Capital rationing: divisible and indivisible projects37
  38. Short-term sources of finance38
  39. Long-term sources of finance: equity, debt, hybrids and leases39
  40. Issuing shares: public offers, placings, introductions, underwriting and buy-backs40
  41. Rights issues41
  42. Islamic finance: riba, murabaha, ijarah, mudaraba, sukuk and musharaka42
  43. Internal finance and dividend policy43
  44. Cost of equity: the dividend valuation model44
  45. Portfolio theory and diversification45
  46. Systematic and unsystematic risk and the efficient frontier46
  47. The capital asset pricing model and arbitrage pricing theory47
  48. Cost of debt48
  49. Cost of preference shares and convertibles49
  50. The weighted average cost of capital50 here
  51. Project-specific cost of capital and adjusted WACC51
  52. Capital gearing, business risk and financial risk52
  53. The traditional view and Modigliani and Miller without tax53
  54. Modigliani and Miller with tax, market imperfections and gearing in appraisal54
  55. Pecking order theory and choosing the financing method55
  56. SME financing problems and remedies56
  57. SME finance: venture capital, business angels, crowdfunding and supply chain finance57
  58. Why value a business: reasons and information needed58
  59. Asset-based valuation59
  60. Income-based valuation: P/E, earnings yield and EV/EBITDA60
  61. Dividend valuation of shares61
  62. Discounted cash flow valuation of a business62
  63. Valuing bonds and preference shares63
  64. The efficient market hypothesis64
  65. Practical considerations in share valuation65
  66. Foreign exchange rates and quotations66
  67. Foreign exchange risk: transaction, translation and economic67
  68. Causes of exchange rate movements68
  69. Purchasing power parity, interest rate parity and four-way equivalence69
  70. Covered interest arbitrage and forward rates70
  71. Internal hedging: invoice currency, netting, matching, leading and lagging71
  72. Forward contracts and money market hedges72
  73. Foreign currency derivatives: futures, options and swaps73
  74. Interest rate risk and traditional hedging74
  75. Interest rate derivatives: FRAs, futures, options and swaps75
See the whole course

Get the complete Financial Management notes

Download as PDF or Word

  • Every topic as PDF and Word, ready to print
  • Edit it in Word or print the PDF. No retyping.
Get this course

Reading stays free. Access lasts 12 months. Pay by card, bank transfer, USSD or QR through Paystack. Your name and email appear on every page of your files. Read our Refund Policy.

PracticeNext topic