Sign inSign upSign in
Menu

Expected Value and Decision Trees

ICAN Skills, Financial Management. Syllabus area C: Investment appraisal.

9 min read · Updated 8 November 2026

Download this topic

In this part

A forecast of a single net present value (NPV) pretends to know the future. In reality the same project may turn out well, badly or middling, and a manager may be able to put rough probabilities on each. Probability analysis turns those into one number, the expected value, and into a map of the decision when choices follow one another, a decision tree.

This topic explains the expected value of the NPV, how to use it in a decision, its advantages and its limits (it hides risk, and it is an average of outcomes that will never happen), how to measure the spread of outcomes with the standard deviation, and how to build and solve a decision tree with decision points and outcome points, with worked examples. The next topic covers the value of perfect information.

Probabilities are used when a question says that the outcomes can be assigned chances, so this topic applies to risk rather than to uncertainty. Read risk and uncertainty in appraisal: sensitivity analysis first.

In 30 seconds

The expected value (EV) of a project’s NPV is the probability-weighted average of the possible NPVs: EV = Σpx. Rule: undertake the project if the expected NPV is positive, unless the risk seems too great for the return. Advantages: uses all outcomes and gives one figure.

Limits: the probabilities are judgements, the EV is not a real outcome, it suits repeated events better than a once-only project, and it does not measure risk; the standard deviation of the outcomes does.

A decision tree shows decisions (squares) and chance outcomes (circles) in sequence; draw it from left to right, solve it from right to left (folding back): at each outcome point take the expected value, at each decision point take the best option.

Expected value

An expected value is a weighted average calculated from the probabilities of the possible outcomes: EV = Σpx, where p is the probability of each outcome and x its value. In appraisal, x is the NPV of each outcome and the result is the expected net present value (the EV of the NPV).

The basic decision rule is to undertake the project if the expected NPV is positive, though a project with a positive EV may be rejected if the risk looks too great for the return.

Example: a project has four possible results.

Probability pNPV x, ₦mpxp(x − EV)2
0.15406.0143.2
0.35186.327.7
0.3041.27.8
0.20(22)(4.4)193.5
Total9.1372.2

The expected NPV is +₦9.1m, so on the basic rule the project is accepted. But there is a 20% chance of a loss of ₦22m, and the outcomes are spread widely. The variance is Σp(x − EV)2 = 372.2 and the standard deviation is its square root, ₦19.3m, a measure of the risk: when two projects have the same EV, the one with the smaller standard deviation is less risky.

Advantages and disadvantages

  • Advantages: it is a weighted average of all possible outcomes, arguably a better measure than the single most likely outcome, and it gives a single figure for the decision.
  • Disadvantages: the probabilities are subjective and may be guesswork; the EV is not a value of any actual outcome (the project will not earn ₦9.1m: it will earn one of the four results); it is much more reliable for events that repeat many times than for a once-only capital project; and above all it gives no analysis of risk.

Decision trees

Some decisions are taken in stages, with the second decision depending on what happens after the first. A decision tree sets out all the possible outcomes and probabilities. It is drawn from the root (the first decision) outwards to the branches and then analysed from the branches back to the root.

There are two kinds of branching point: decision points (drawn as squares), where management chooses, and outcome points (drawn as circles), where chance decides and an expected value is calculated.

The steps are:

  • draw the tree
  • write the probability on each chance branch (they sum to 1 at each outcome point)
  • put the cash flow or value at the end of each path
  • fold back, taking the expected value at each outcome point and the best option at each decision point
  • state the decision at the start

A worked tree: a new product

A company can spend ₦30m on developing a new product (decision A) or do nothing. Development is successful with probability 0.7. If it succeeds, the company must decide (decision C) whether to launch, at an extra cost of ₦15m, or to sell the rights for ₦35m. If launched, demand is high with probability 0.6 (present value of cash flows ₦100m) or low with probability 0.4 (present value ₦30m).

If the development fails, the project is abandoned and nothing is received.

  1. Outcome point after launch:
    expected present value = 0.6 × 100 + 0.4 × 30 = 72; less the launch cost of 15 gives 57.
  2. Decision point C: launch (57) or sell the rights (35): choose to launch, value 57.
  3. Outcome point B (development):
    0.7 × 57 + 0.3 × 0 = 39.9.
  4. Decision point A:
    spend ₦30m to get an expected value of 39.9, an expected NPV of 39.9 − 30 = +₦9.9m, or do nothing for zero.
    Develop.

The possible results are: success and high demand, probability 0.7 × 0.6 = 0.42, NPV 100 − 15 − 30 = +55; success and low demand, 0.28, NPV 30 − 15 − 30 = −15; failure, 0.30, NPV −30. The expected value is 0.42 × 55 + 0.28 × (−15) + 0.30 × (−30) = 9.9, the same, and the standard deviation is ₦38.8m, large relative to the expected value. There is a 58% probability of a loss, and a manager unwilling to risk losing ₦30m might reject a project that the expected value would accept.

A decision tree for a new productFrom decision A, develop at a cost of 30 million or do nothing. Develop leads to an outcome point B: success with probability 0.7 or failure with probability 0.3 and value zero. After success, decision C: launch for an extra 15 million, or sell the rights for 35 million. Launch leads to an outcome point: high demand 0.6 with present value 100, or low demand 0.4 with present value 30, expected 72 less 15 equals 57. Folding back: B is 39.9, expected NPV at A is plus 9.9 million.A decidedevelop −30Bsuccess 0.7failure 0.3: value 0C decidelaunch −15sell rights +35high 0.6: value 100low 0.4: value 30Fold backlaunch: 72 − 15 = 57 (beats 35)B: 0.7 × 57 + 0.3 × 0 = 39.9A: 39.9 − 30 = +9.9 millionSquares are decision points, circles are outcome points

The ideas in more depth

Why the EV is not a promise

If the same project could be undertaken a thousand times, the average result would approach the EV. A company undertakes it once, and the outcome will be one of the possible results, so the EV is a guide and not a forecast. Where the loss from the worst outcome is large relative to the company’s resources, the spread matters as much as the average.

Why the tree is solved backwards

The best second decision depends on the situation reached, so it must be valued first, then the chance event that leads to it, then the first decision. Working forwards would require guessing what later choices will be.

Sources and references

  • No accounting standard governs probability analysis. The standard deviation and expected value are statistical tools described in the course on quantitative methods.

These points are stated as at 5 November 2026.

Worked examples

Example 1: the expected NPV. NPVs of ₦40m, ₦18m, ₦4m and −₦22m with probabilities 0.15, 0.35, 0.30 and 0.20. Required: the expected NPV.

  1. Sum.
    6.0 + 6.3 + 1.2 − 4.4 = ₦9.1m.

Example 2: the standard deviation. The variance is 372.2. Required: the standard deviation.

  1. Standard deviation. √372.2 = ₦19.3m.

Example 3: an outcome point. High demand 0.6 (PV 100) or low 0.4 (PV 30); launch cost 15. Required: the expected value after the cost.

  1. Expected PV.
    0.6 × 100 + 0.4 × 30 = 72.
  2. Net.
    72 − 15 = 57.

How to answer in the exam

  • Draw the tree clearly with probabilities on branches and values at the ends.
  • Fold back, showing the expected value at each outcome point and the choice at each decision point.
  • State the decision and the expected NPV, then comment on the risk and the probability of a loss.
  • Mention the limits of the EV for a once-only project.

Common mistakes in the exam

  • Probabilities that do not sum to 1 at a point.
  • Forgetting to deduct the initial cost at the decision.
  • Solving the tree from the start instead of folding back.
  • Taking an expected value at a decision point instead of choosing the best option.
  • Ignoring the risk when the EV is positive.
  • Multiplying probabilities wrongly for a second-stage outcome.

Quick revision

  • EV = Σpx; accept if the expected NPV is positive, if the risk is acceptable.
  • Standard deviation measures the spread; the EV does not measure risk.
  • Tree: squares for decisions, circles for chance; draw forwards, solve backwards.
  • Probabilities along a path multiply.

Practice questions

These are original questions written in the style of the Institute’s exams. Try each one before you open the answer. Section A is a recall check, because the paper itself is written.

Recall check: multiple choice

Question 1. The expected value is:

  1. The most likely outcome
  2. The highest outcome
  3. The sum of probability times outcome
  4. The lowest outcome
Show the answer

C. A probability-weighted average.

Question 2. On the basic rule a project is accepted if its expected NPV is:

  1. Negative
  2. Positive
  3. Zero always
  4. Equal to the outlay
Show the answer

B. Subject to the risk being acceptable.

Question 3. The expected value:

  1. Is not the value of any actual outcome
  2. Will certainly happen
  3. Is always the best outcome
  4. Is the standard deviation
Show the answer

A. It is an average of possible outcomes.

Question 4. A decision tree is solved:

  1. From the root forwards
  2. In any order
  3. Only at the root
  4. From the branches back to the root
Show the answer

D. This is folding back.

Question 5. In a decision tree, a decision point is usually drawn as:

  1. A circle
  2. A square
  3. A triangle
  4. A line
Show the answer

B. An outcome point is a circle.

Question 6. The probabilities on the branches leaving an outcome point sum to:

  1. 1
  2. 0
  3. 100
  4. Any number
Show the answer

A. One of the outcomes must happen.

Question 7. A major disadvantage of the EV is that it:

  1. Uses all outcomes
  2. Gives one figure
  3. Provides no analysis of risk
  4. Is complicated
Show the answer

C. The standard deviation is needed for risk.

Question 8. At a decision point you:

  1. Average the branches
  2. Add the probabilities
  3. Ignore the options
  4. Choose the option with the best expected value
Show the answer

D. Management chooses, not chance.

Question 9. The standard deviation of NPVs measures:

  1. The average
  2. The cost
  3. The spread of the outcomes
  4. The tax
Show the answer

C. A larger value means more risk.

Question 10. An advantage of the EV is that it:

  1. Uses all the possible outcomes and gives a single figure
  2. Removes risk
  3. Needs no probabilities
  4. Is exact
Show the answer

A. It helps a decision to be made.

Section B style: written questions

Question 11 (10 marks). (a) Define expected value and state the decision rule. (4 marks) (b) State TWO advantages and TWO disadvantages. (4 marks) (c) State why the standard deviation is also needed. (2 marks)

Question 12 (15 marks). A project has NPVs of ₦30m, ₦12m, −₦6m and −₦25m with probabilities 0.25, 0.40, 0.25 and 0.10. (a) Calculate the expected NPV. (6 marks) (b) State the probability of a loss. (2 marks) (c) The standard deviation is ₦16.9m; comment on the risk. (4 marks) (d) State the decision. (3 marks)

A further written question

Question 13 (20 marks). A company can spend ₦20m on developing a product. Development succeeds with probability 0.75. If it succeeds, the market is good (probability 0.5, present value ₦70m) or poor (probability 0.5, present value ₦10m, but the rights could be sold for ₦18m). If development fails, nothing is received.

(a) Draw and describe the tree. (4 marks) (b) Calculate the expected value at the outcome point after success, allowing for the option to sell. (6 marks) (c) Calculate the expected NPV of developing. (6 marks) (d) Comment on the risk. (4 marks)

Model answers

Show the model answer to Question 11

(a) A probability-weighted average of the possible outcomes, Σpx (2); undertake the project if the expected NPV is positive (2).

(b) Advantages: uses all outcomes; gives a single figure (2). Disadvantages: subjective probabilities; not a real outcome; no analysis of risk (any two, 2).

(c) The EV does not show how widely the outcomes vary (2).

Show the model answer to Question 12

(a)

  1. 0.25 × 30 = 7.5
  2. 0.40 × 12 = 4.8
  3. 0.25 × (−6) = −1.5
  4. 0.10 × (−25) = −2.5
  5. EV = +₦8.3m (6).

(b) 0.25 + 0.10 = 35% (2).

(c) The standard deviation of ₦16.9m is about twice the expected value, so the outcomes vary widely and there is a real chance of loss (4).

(d) Accept on the expected NPV if the company can bear a loss of up to ₦25m (3).

Show the model answer to Question 13

(a) Decision A: develop or not; outcome B: success 0.75 or failure 0.25; after success, an outcome point for the market, with a decision to sell in the poor market (4).

(b) In the poor market, sell for ₦18m, which is better than 10; expected value = 0.5 × 70 + 0.5 × 18 = ₦44m (6).

(c)

  1. At B.
    0.75 × 44 + 0.25 × 0 = 33
  2. expected NPV.
    33 − 20 = +₦13m (6).

(d) The outcomes are +50 (probability 0.375), −2 (0.375) and −20 (0.25); the standard deviation is ₦29.5m, large compared with the expected value of ₦13m, and there is a 25% chance of losing the whole ₦20m (4).

Spotted a mistake? Tell us and we will check it.

Where this fits

See every past question on Financial Management and the topic each one tests in the Pathfinder question finder.

After it, move on to Strategic Financial Management.

All Financial Management topics

You are reading topic 32 of 75.

  1. The nature and purpose of financial management01
  2. Financial objectives: shareholder wealth, profit, earnings per share and stakeholder value02
  3. Stakeholders and conflicts of objectives03
  4. Agency theory and the agency problem04
  5. Achieving stakeholder objectives: governance codes, listing rules and reward schemes05
  6. Evaluating corporate objectives: ratios and total shareholder return06
  7. Financial management in not-for-profit organisations07
  8. Macroeconomic policy targets, GDP and fiscal policy08
  9. Monetary policy, interest rates, inflation and the exchange rate09
  10. Money markets, banks and money market instruments10
  11. Capital markets and the stock exchange11
  12. The bond market and technology in financial markets12
  13. Working capital: nature, elements and objectives13
  14. The cash operating cycle, working capital ratios and overtrading14
  15. Inventory management: EOQ, reorder levels, just-in-time and ABC analysis15
  16. Managing receivables: credit terms and credit control16
  17. Debt factoring and invoice discounting17
  18. Early settlement discounts and trade payables18
  19. Cash flow forecasts and reasons for holding cash19
  20. Short-term investment and treasury management20
  21. Cash management models: Baumol and Miller-Orr21
  22. Working capital investment policy and determining needs22
  23. Working capital funding strategies23
  24. Capital expenditure, payback and accounting rate of return24
  25. Relevant cash flows in investment appraisal25
  26. The time value of money: discounting and annuities26
  27. Net present value and the case for discounted cash flow27
  28. Internal rate of return and NPV versus IRR28
  29. Taxation and capital allowances in DCF29
  30. Inflation in DCF: real and money terms30
  31. Risk and uncertainty in appraisal: sensitivity analysis31
  32. Expected value and decision trees32 here
  33. The value of perfect information33
  34. Simulation, risk-adjusted discount rates and discounted payback34
  35. Lease or buy and borrow-to-buy decisions35
  36. Asset replacement: equivalent annual cost and the lowest common multiple36
  37. Capital rationing: divisible and indivisible projects37
  38. Short-term sources of finance38
  39. Long-term sources of finance: equity, debt, hybrids and leases39
  40. Issuing shares: public offers, placings, introductions, underwriting and buy-backs40
  41. Rights issues41
  42. Islamic finance: riba, murabaha, ijarah, mudaraba, sukuk and musharaka42
  43. Internal finance and dividend policy43
  44. Cost of equity: the dividend valuation model44
  45. Portfolio theory and diversification45
  46. Systematic and unsystematic risk and the efficient frontier46
  47. The capital asset pricing model and arbitrage pricing theory47
  48. Cost of debt48
  49. Cost of preference shares and convertibles49
  50. The weighted average cost of capital50
  51. Project-specific cost of capital and adjusted WACC51
  52. Capital gearing, business risk and financial risk52
  53. The traditional view and Modigliani and Miller without tax53
  54. Modigliani and Miller with tax, market imperfections and gearing in appraisal54
  55. Pecking order theory and choosing the financing method55
  56. SME financing problems and remedies56
  57. SME finance: venture capital, business angels, crowdfunding and supply chain finance57
  58. Why value a business: reasons and information needed58
  59. Asset-based valuation59
  60. Income-based valuation: P/E, earnings yield and EV/EBITDA60
  61. Dividend valuation of shares61
  62. Discounted cash flow valuation of a business62
  63. Valuing bonds and preference shares63
  64. The efficient market hypothesis64
  65. Practical considerations in share valuation65
  66. Foreign exchange rates and quotations66
  67. Foreign exchange risk: transaction, translation and economic67
  68. Causes of exchange rate movements68
  69. Purchasing power parity, interest rate parity and four-way equivalence69
  70. Covered interest arbitrage and forward rates70
  71. Internal hedging: invoice currency, netting, matching, leading and lagging71
  72. Forward contracts and money market hedges72
  73. Foreign currency derivatives: futures, options and swaps73
  74. Interest rate risk and traditional hedging74
  75. Interest rate derivatives: FRAs, futures, options and swaps75
See the whole course

Get the complete Financial Management notes

Download as PDF or Word

  • Every topic as PDF and Word, ready to print
  • Edit it in Word or print the PDF. No retyping.
Get this course

Reading stays free. Access lasts 12 months. Pay by card, bank transfer, USSD or QR through Paystack. Your name and email appear on every page of your files. Read our Refund Policy.

PracticeNext topic