Net Present Value and the Case for Discounted Cash Flow

ICAN Skills, Financial Management. Syllabus area C: Investment appraisal.

9 min read · Updated 8 November 2026

Download this topic

In this part

Net present value is the most important figure in this course. It converts every cash flow of a project, whenever it falls, into today’s money, adds them up and says in one number how much richer the shareholders will be if the project goes ahead.

If the number is positive, the project earns more than the cost of the money used and it adds value; if negative, it destroys value. Almost every later topic, from risk to leasing to capital rationing, builds on this calculation.

This topic explains how to calculate and interpret the net present value, the decision rules for one project and for mutually exclusive projects, a full worked example including working capital and scrap value, the sensitivity of the result to the discount rate, the advantages and limits of the method, and the case for discounted cash flow over non-discounting methods such as payback and the accounting rate of return.

The next topic covers the internal rate of return and compares it with net present value.

The net present value was the centre of the compulsory question in November Diet, 2025, Question 1 (30 marks): 16 marks for the calculation, then its sensitivity and the strengths of sensitivity analysis. Read the time value of money: discounting and annuities first.

In 30 seconds

Net present value (NPV) = present value of cash inflows − present value of cash outflows, discounted at the cost of capital (the return required by the investor). Rule: accept a project if the NPV is positive, because it adds that amount to shareholder wealth; among mutually exclusive projects choose the highest NPV.

Steps: list the relevant cash flows by year (including working capital and scrap value), apply the discount factors, sum, compare with zero. Advantages: uses cash flows and all of them, allows for the time value of money, is linked to shareholder wealth and is additive. Limits: needs an estimate of the cost of capital and of the cash flows, and gives an absolute figure.

discounted cash flow (DCF) methods beat payback and accounting rate of return (ARR) because they use cash flows, the time value of money and all returns.

Net present value

The net present value (NPV) method gives a present value to the expected costs and benefits of a project, using the cost of capital r as the return required by the investor or company. The NPV is the present value of the income or benefits minus the present value of the costs. A project adds value if its NPV is greater than zero, and it should then be undertaken.

A positive NPV of ₦1.7m means the project is expected to make the shareholders ₦1.7m better off in present terms, after earning the required return on the money invested.

  1. Identify the relevant cash flows for each year, from the previous topic: the initial outlay, annual net cash flows, working capital and its recovery, scrap value.
  2. Place each at its year: the outlay at time 0, the rest at year-ends.
  3. Multiply each by its discount factor at the cost of capital.
  4. Sum the present values to give the NPV, and apply the rule.

A worked example: Delta Packaging

Delta is considering a machine costing ₦7.5m. The project needs working capital of ₦1.0m at the start, recovered at the end of year 4. The relevant annual net cash flows are ₦2.6m, ₦3.1m, ₦3.4m and ₦2.8m in years 1 to 4, and the machine can be sold for ₦0.9m at the end of year 4. The cost of capital is 12%.

YearItemCash flow ₦mFactor at 12%present value (PV) ₦m
0Machine and working capital(8.5)1.000(8.50)
1Net cash flow2.60.8932.32
2Net cash flow3.10.7972.47
3Net cash flow3.40.7122.42
4Net cash flow 2.8 + scrap 0.9 + working capital 1.04.70.6362.99
Net present value1.70

The NPV is +₦1.70m, so the project should be accepted. If the cost of capital were 20% (factors 0.833, 0.694, 0.579 and 0.482), the NPV would fall to about +₦0.05m: the project is only just worth doing at that rate, which shows how sensitive the result is to the discount rate and leads to the internal rate of return in the next topic.

Choosing between projects

For a single project the rule is NPV above zero. For mutually exclusive projects (only one can be chosen) choose the highest NPV. For independent projects with no limit on funds, accept all with a positive NPV; where funds are limited the choice is more complicated, covered under capital rationing.

The case for discounted cash flow

MethodUses cash flowsTime value of moneyAll returnsLink to shareholder wealth
PaybackYesNoNo: stops at paybackNone
Accounting rate of returnNo: profitsNoYes, averagedNone
Net present valueYesYesYesDirect
Internal rate of returnYesYesYesIndirect

DCF methods are superior because they use cash flows (the money actually invested and returned), allow for the time value of money, count all the cash flows of the project and use a discount rate that reflects the cost and risk of the funds, an objective basis, unlike the arbitrary maximum payback period or target ARR.

Advantages and limits of NPV

  • Advantages: considers the time value of money; uses cash flows and all of them; measures the absolute increase in wealth; NPVs of separate projects can be added; consistent with the objective of maximising shareholder wealth.
  • Limits: the cost of capital must be estimated and is assumed constant over the life; the cash flows are forecasts and treated as certain; it is harder to explain to non-financial managers than a percentage; and as an absolute figure it does not by itself show the scale of return per naira invested.
The net present value of Delta PackagingBars of present value at 12 per cent: year 0 outflow minus 8.50 million, then inflows 2.32, 2.47, 2.42 and 2.99 million for years 1 to 4, totalling 10.20 million. Net present value is plus 1.70 million. A note: at 20 per cent the net present value falls to about 0.05 million. Rule: accept if positive.Year 0Year 1Year 2Year 3Year 4−8.502.322.472.422.99NPV at 12%PV of inflows 10.20less outlay 8.50= +1.70 millionAt 20%: about +0.05Accept if NPV above 0

The ideas in more depth

Why the discount rate is the required return

The NPV asks whether the project earns more than the investors could earn elsewhere at similar risk. The discount rate is that alternative return. A zero NPV means the project exactly earns the required return, a positive NPV means it earns more, and the amount is the value created at today’s prices.

Why NPV and shareholder wealth are linked

If the market prices the company as the present value of its future cash flows, a project with a positive NPV raises the value of the company by about that amount, and so the share price. This is why NPV is the criterion consistent with the objective of maximising the wealth of the shareholders, studied at the start of the course.

Sources and references

  • No accounting standard governs investment appraisal. The discount factor and annuity tables are given on the formula sheet of the paper.

These points are stated as at 5 November 2026.

Worked examples

Example 1: the NPV. Outlay ₦8.5m; present values of inflows 2.32, 2.47, 2.42 and 2.99. Required: the NPV.

  1. PV of inflows.
    2.32 + 2.47 + 2.42 + 2.99 = ₦10.20m.
  2. NPV.
    10.20 − 8.50 = +₦1.70m: accept.

Example 2: year 4. Net cash flow ₦2.8m, scrap ₦0.9m, working capital recovered ₦1.0m; factor 0.636. Required: the present value.

  1. Cash flow.
    2.8 + 0.9 + 1.0 = ₦4.7m.
  2. PV.
    4.7 × 0.636 = ₦2.99m.

Example 3: an annuity. ₦5.9m a year for 5 years at 10% (factor 3.791) plus ₦2m scrap (factor 0.621), outlay ₦18m. Required: the NPV.

  1. PV.
    5.9 × 3.791 + 2 × 0.621 = 22.37 + 1.24 = ₦23.61m.
  2. NPV.
    23.61 − 18 = +₦5.61m.

How to answer in the exam

  • Set out a table with year, cash flow, factor and present value, and total it.
  • Use the annuity factor for level flows and show it.
  • State the decision and its meaning: value added to shareholders.
  • Comment on the weaknesses: the cost of capital, uncertainty, and the need for sensitivity analysis.

Common mistakes in the exam

  • Forgetting to include the recovery of working capital or the scrap value.
  • Discounting the initial outlay.
  • Using a profit figure, not a cash flow.
  • Choosing between exclusive projects on the internal rate of return (IRR) or on the size of investment.
  • Stopping at the NPV without stating accept or reject.
  • Saying that a negative NPV means a loss in the accounts, rather than a return below the required rate.

Quick revision

  • NPV = PV of inflows − PV of outflows at the cost of capital.
  • Accept if positive; among exclusive projects pick the highest.
  • Include working capital and scrap value.
  • DCF uses cash flows, the time value of money and all returns.

Practice questions

These are original questions written in the style of the Institute’s exams. Try each one before you open the answer. Section A is a recall check, because the paper itself is written.

Recall check: multiple choice

Question 1. The net present value is:

  1. Total profit
  2. Total cash flow
  3. The present value of inflows less the present value of outflows
  4. The payback period
Show the answer

C. Discounted at the cost of capital.

Question 2. A project should be accepted if its NPV is:

  1. Negative
  2. Positive
  3. Zero always
  4. Equal to the cost
Show the answer

B. It adds value.

Question 3. The discount rate in an NPV calculation is:

  1. The required return or cost of capital
  2. The inflation rate only
  3. The tax rate
  4. The dividend yield
Show the answer

A. The return investors could earn elsewhere.

Question 4. A positive NPV means the project:

  1. Loses money
  2. Has no risk
  3. Pays back quickly
  4. Adds to shareholder wealth
Show the answer

D. By the amount of the NPV.

Question 5. Among mutually exclusive projects, choose the one with the:

  1. Lowest NPV
  2. Highest NPV
  3. Shortest life
  4. Lowest cost
Show the answer

B. Provided the NPV is positive.

Question 6. DCF methods are better than payback because they:

  1. Allow for the time value of money and all cash flows
  2. Ignore cash
  3. Are simpler
  4. Ignore risk
Show the answer

A. Payback ignores both.

Question 7. The initial outlay at time 0 has a discount factor of:

  1. 0.5
  2. 0
  3. 1.0
  4. 10
Show the answer

C. It is already at present value.

Question 8. A limitation of NPV is that:

  1. It ignores cash
  2. It ignores time
  3. It is a percentage
  4. It needs estimates of the cost of capital and the cash flows
Show the answer

D. Both are uncertain.

Question 9. The recovery of working capital at the end of a project is:

  1. Ignored
  2. An outflow
  3. An inflow in the final year
  4. Depreciation
Show the answer

C. It is discounted like other flows.

Question 10. NPV is measured in:

  1. Naira, an absolute amount
  2. Years
  3. Percentages
  4. Ratios
Show the answer

A. Unlike the internal rate of return.

Section B style: written questions

Question 11 (10 marks). (a) Define net present value and state the decision rule. (4 marks) (b) State THREE advantages of NPV. (3 marks) (c) State THREE reasons why DCF is better than payback. (3 marks)

Question 12 (15 marks). A project costs ₦18m. It gives ₦5.9m a year for 5 years and ₦2m scrap at the end of year 5. The cost of capital is 10% (annuity factor 3.791; year 5 factor 0.621). (a) Calculate the present value of the annual flows. (4 marks) (b) Calculate the present value of the scrap. (3 marks) (c) Calculate the NPV. (4 marks) (d) State the decision and its meaning. (4 marks)

A further written question

Question 13 (20 marks). Two mutually exclusive projects are evaluated at 12%. X costs ₦10m now and gives ₦4m a year for 4 years (annuity factor 3.037). Y costs ₦14m now and gives ₦5.0m, ₦5.5m, ₦5.5m and ₦5.5m (factors 0.893, 0.797, 0.712, 0.636).

(a) Calculate the NPV of X. (4 marks) (b) Calculate the NPV of Y. (8 marks) (c) State which to choose and why. (4 marks) (d) State TWO limits of the analysis. (4 marks)

Model answers

Show the model answer to Question 11

(a) The present value of inflows less the present value of outflows, discounted at the cost of capital (2); accept if positive (2).

(b) Time value of money; uses all cash flows; measures the increase in wealth; additive; consistent with shareholder wealth (1 each, any three).

(c) It uses the time value of money; counts all cash flows, not only until payback; has an objective discount rate (1 each).

Show the model answer to Question 12

(a) 5.9 × 3.791 = ₦22.37m (4).

(b) 2 × 0.621 = ₦1.24m (3).

(c) 22.37 + 1.24 − 18 = +₦5.61m (4).

(d) Accept: the NPV is positive, so the project is expected to add ₦5.61m to shareholder wealth after earning the 10% required return (4).

Show the model answer to Question 13

(a)

  1. 4 × 3.037 = 12.148
  2. NPV = 12.148 − 10 = +₦2.15m (4).

(b) 5.0 × 0.893 = 4.465; 5.5 × 0.797 = 4.384; 5.5 × 0.712 = 3.916; 5.5 × 0.636 = 3.498 (4); total 16.263 (2); NPV = 16.263 − 14 = +₦2.26m (2).

(c) Choose Y, the higher NPV, which adds most to wealth, provided the extra ₦4m can be funded (4).

(d) (2 marks each, any two) The cash flows and the rate are estimates; the risk of the projects may differ; the lives are equal here but replacement would matter if they were not.

Pathfinder on Net present value and the case for discounted cash flow

These are the ICAN Pathfinder questions that test this topic. ICAN owns the questions and the suggested solutions, so we point you to them and do not copy them. Open your Pathfinder, attempt each question under exam conditions, then check your answer against the notes above.

November Diet, 2025: Question 1 (30 marks)

Part (a) asks for the net present value of manufacturing a new product at a cost of capital of 5%, using the annuity factor, to show whether to proceed (16 marks).

Revise first: Net present value

Source: ICAN Pathfinder, Financial Management. Diets covered: Every diet in the Pathfinder, November Diet, 2025 and May Diet, 2026, was reviewed here. The diets listed above test this topic directly..

Spotted a mistake? Tell us and we will check it.

Where this fits

See every past question on Financial Management and the topic each one tests in the Pathfinder question finder.

After it, move on to Strategic Financial Management.

All Financial Management topics

You are reading topic 27 of 75.

  1. The nature and purpose of financial management01
  2. Financial objectives: shareholder wealth, profit, earnings per share and stakeholder value02
  3. Stakeholders and conflicts of objectives03
  4. Agency theory and the agency problem04
  5. Achieving stakeholder objectives: governance codes, listing rules and reward schemes05
  6. Evaluating corporate objectives: ratios and total shareholder return06
  7. Financial management in not-for-profit organisations07
  8. Macroeconomic policy targets, GDP and fiscal policy08
  9. Monetary policy, interest rates, inflation and the exchange rate09
  10. Money markets, banks and money market instruments10
  11. Capital markets and the stock exchange11
  12. The bond market and technology in financial markets12
  13. Working capital: nature, elements and objectives13
  14. The cash operating cycle, working capital ratios and overtrading14
  15. Inventory management: EOQ, reorder levels, just-in-time and ABC analysis15
  16. Managing receivables: credit terms and credit control16
  17. Debt factoring and invoice discounting17
  18. Early settlement discounts and trade payables18
  19. Cash flow forecasts and reasons for holding cash19
  20. Short-term investment and treasury management20
  21. Cash management models: Baumol and Miller-Orr21
  22. Working capital investment policy and determining needs22
  23. Working capital funding strategies23
  24. Capital expenditure, payback and accounting rate of return24
  25. Relevant cash flows in investment appraisal25
  26. The time value of money: discounting and annuities26
  27. Net present value and the case for discounted cash flow27 here
  28. Internal rate of return and NPV versus IRR28
  29. Taxation and capital allowances in DCF29
  30. Inflation in DCF: real and money terms30
  31. Risk and uncertainty in appraisal: sensitivity analysis31
  32. Expected value and decision trees32
  33. The value of perfect information33
  34. Simulation, risk-adjusted discount rates and discounted payback34
  35. Lease or buy and borrow-to-buy decisions35
  36. Asset replacement: equivalent annual cost and the lowest common multiple36
  37. Capital rationing: divisible and indivisible projects37
  38. Short-term sources of finance38
  39. Long-term sources of finance: equity, debt, hybrids and leases39
  40. Issuing shares: public offers, placings, introductions, underwriting and buy-backs40
  41. Rights issues41
  42. Islamic finance: riba, murabaha, ijarah, mudaraba, sukuk and musharaka42
  43. Internal finance and dividend policy43
  44. Cost of equity: the dividend valuation model44
  45. Portfolio theory and diversification45
  46. Systematic and unsystematic risk and the efficient frontier46
  47. The capital asset pricing model and arbitrage pricing theory47
  48. Cost of debt48
  49. Cost of preference shares and convertibles49
  50. The weighted average cost of capital50
  51. Project-specific cost of capital and adjusted WACC51
  52. Capital gearing, business risk and financial risk52
  53. The traditional view and Modigliani and Miller without tax53
  54. Modigliani and Miller with tax, market imperfections and gearing in appraisal54
  55. Pecking order theory and choosing the financing method55
  56. SME financing problems and remedies56
  57. SME finance: venture capital, business angels, crowdfunding and supply chain finance57
  58. Why value a business: reasons and information needed58
  59. Asset-based valuation59
  60. Income-based valuation: P/E, earnings yield and EV/EBITDA60
  61. Dividend valuation of shares61
  62. Discounted cash flow valuation of a business62
  63. Valuing bonds and preference shares63
  64. The efficient market hypothesis64
  65. Practical considerations in share valuation65
  66. Foreign exchange rates and quotations66
  67. Foreign exchange risk: transaction, translation and economic67
  68. Causes of exchange rate movements68
  69. Purchasing power parity, interest rate parity and four-way equivalence69
  70. Covered interest arbitrage and forward rates70
  71. Internal hedging: invoice currency, netting, matching, leading and lagging71
  72. Forward contracts and money market hedges72
  73. Foreign currency derivatives: futures, options and swaps73
  74. Interest rate risk and traditional hedging74
  75. Interest rate derivatives: FRAs, futures, options and swaps75
See the whole course

Get the complete Financial Management notes

Download as PDF or Word

  • Every topic as PDF and Word, ready to print
  • Edit it in Word or print the PDF. No retyping.
Get this course

Reading stays free. Access lasts 12 months. Pay by card, bank transfer, USSD or QR through Paystack. Your name and email appear on every page of your files. Read our Refund Policy.

PracticeNext topic